Professional Documents
Culture Documents
Ajv DPW 10 525 El MSS 2198 - 00 PDF
Ajv DPW 10 525 El MSS 2198 - 00 PDF
PROJECT
CONTRACTOR
TITLE
Drawn Index/Rev.
Designed
AOD10-DD09-ADZ-8225477
AJV-DPW-10-525-EL-MSS-2198
Checked REV. A
0
Approved
ORIGINATOR PROJECT FACILITY SYSTEM CODE DISCIPLINE DOC. TYPE SEQUENTIAL Page No.
DUQM INTEGRATED POWER & WATER PLANT
Rev. A
(DIPWP) PROJECT
METHOD STATEMENT FOR INSTALLATION OF CABLES & RACEWAYS
Page 2 of 14
Document Ref. No(UEP): UE‐035/2019/S/S‐MS/002
CONTENTS
1.0 Purpose 03
2.0 Scope 03
3.0 Reference 03
5.0 Manpower 04
6.0 Procedure 04
8.0 Responsibilities 14
14
9.0 Emergency
14
10.0 Records
DUQM INTEGRATED POWER & WATER PLANT
Rev. A
(DIPWP) PROJECT
METHOD STATEMENT FOR INSTALLATION OF CABLES & RACEWAYS
Page 3 of 14
Document Ref. No(UEP): UE‐035/2019/S/S‐MS/002
1.0 Purpose
The purpose of this procedure is to describe the sequence of activities involved in
Laying of Cables & Installation of Raceways works and also it provides the necessary
guidelines to carry out the Power Cable Laying works.
2.0 Scope
This procedure shall be applicable for installation of Cables & Raceways, as per
approved drawings / documents under the project.
3.0 Reference
- Tender Specification
- Project HSE Plan
- Project Quality Plan
- Approved Drawings
- Manufacture erection procedure
- Approved vendor drawing
4.0 Plant, Machinery and Tools
100ton Crane
Trailer
Mobile Cable pulling Winch machine
Cable drum Jack stand
Cable drum loading spindle
Straight rollers
Cross rollers
Wire rope sling
Ramp
D shackle
Web slings
Electrical tool box
Electrical Extension code
Power fire extinguisher
First Aid kit
Mechanical Tools box
Torque wrench
Megger
Hydraulic cable cutter or cutting machine
Swivel Eye and End Socks
Heat gun and Hand Tools
PPE
DUQM INTEGRATED POWER & WATER PLANT
Rev. A
(DIPWP) PROJECT
METHOD STATEMENT FOR INSTALLATION OF CABLES & RACEWAYS
Page 4 of 14
Document Ref. No(UEP): UE‐035/2019/S/S‐MS/002
Method of Operation:
Setting out will be done for all cable trenches & locations.
The Cable drum shall be shifted from the Storage Area to the Cable trench location
in a safe manner.
Cable shall be tested on cable drums prior to removal and work site.
The value will be noted for core to core and armour.
The Cable drum will be offloaded on cable stand with spindle and position of pulling
ensured.
The Winch Machine is set at the far end of the Cable Drum. Winch machine is used
for Cable Pulling through the trenches. It has a Swivel eye fitted. The swivel eye
must be in good working conditions and able to freely rotate to prevent the cable
from twisting.
Rollers will be placed in trenches & Manholes. Rollers shall always be used for
pulling the Cables. Rollers shall be in serviceable condition moving easily on their
spindle. A leading roller shall be placed at the pulling end with slide rollers on the
bends.
The bond wire must be pulled from the far end of the Cable Drum tensioned to
ensure it does not damage other apparatus. This wire must be tightened with the
cable for pulling.
The rating of pulling wire tension should have maximum four times higher than
pulling tension of cable, for safety factor.
After all these settings, the winch Machine will be started for pulling the Cables.
All ducts shall be cleaned and passed through mandrel test (.i.e. passing a sponge
ball of appropriate size into the duct) prior to pull the cable in ducts.
Cable pulling lubricant such as Polywater is applied around cable to reduce the
friction between the cable and ducts. Remaining lubricant is brushed off from cable
surface on exit side of the duct.
The laid cable shall be placed on installed cable supports and secured with cable
cleats using nut and bots.
Ensure that the all the cable supports are earthed using appropriate earth conductor
and linked with substation main earth grid.
The rotating speed of the drum has to correspond to that of the pulling speed; the
rotating speed shall be controlled with a simple wooden brake, if necessary.
The cable shall be pulled up to the final locations, designated GIS bay which is inside
the existing 132kV GIS basement and lifted up to the supports using chain pulley.
For source end, it shall be ensured that the cable lifted/pulled up to the designated
Transformer cable box.
Before cutting the cables, both ends must be inspected to ensure sufficient length
provided for proper dressing and end termination.
The cable ends shall be sealed by using shrinkable PVC end cups after installation
for cable, to protect the cable from moisture ingress.
Proper care shall be exercised to ensure that the cables are never bent more than
the bending radius specified by the manufacturer.
Soon after the completion of every cable the cables will be tested for insulation
resistance.
Cable identification tags shall be installed soon after the cable pulling.
DUQM INTEGRATED POWER & WATER PLANT
Rev. A
(DIPWP) PROJECT
METHOD STATEMENT FOR INSTALLATION OF CABLES & RACEWAYS
Page 6 of 14
Document Ref. No(UEP): UE‐035/2019/S/S‐MS/002
Figure 6.1 – Cable drum lifting.
DUQM INTEGRATED POWER & WATER PLANT
Rev. A
(DIPWP) PROJECT
METHOD STATEMENT FOR INSTALLATION OF CABLES & RACEWAYS
Page 7 of 14
Document Ref. No(UEP): UE‐035/2019/S/S‐MS/002
Figure 6.2 – Method of cable pulling.
6.1 Installation Procedure for MV, LV, Control, Fiber, CAT, I&C & Ethernet Cables
Shifting of Cable Drum to Site:
It is necessary to ensure that the materials received at site are inspected and found in
accordance with the approved drawings/documents and specifications.
Inspect the cables for any abnormality, damage during transport.
Identify the cable drum as per approved cable schedule and shift the cable drum to the
respective site location from storage yard.
Spindle shall be inserted to the cable drum to ease the lifting process.
Load the cable drums on to a suitable vehicle by using an appropriate crane/trailer and
necessary lifting devices and transport it to work location. After loading the drum it
shall be secured properly in order to avoid any movement of the drum.
The cable drum shall be unloaded from the trailer and placed on to the cable drum
stands or a place selected for keeping cable drums with help of a crane and necessary
lifting devices.
Unpack wooden strips of the cable drums and the direction of the cables shall be
verified.
The cable drums shall stay above the ground level by minimum distance of 300mm and
proper brake shall be employed.
Cable pulling swivel eye and end socks shall be provided at the end of the cable to
ensure the convenient and safe pulling.
DUQM INTEGRATED POWER & WATER PLANT
Rev. A
(DIPWP) PROJECT
METHOD STATEMENT FOR INSTALLATION OF CABLES & RACEWAYS
Page 8 of 14
Document Ref. No(UEP): UE‐035/2019/S/S‐MS/002
Installation Procedure:
Inspect the cable route as per approved drawings and ensure the entire route is free
from other utility, adequate access available to lay the cable and most importantly clean
& tidy.
Before cable laying, for each and every drum of the cable, sheath and insulation
resistance test shall be carried by using 1kV Megger, if the cable is not tested during
material receiving inspection.
Stand rollers shall be placed for power cable laying at 1.5 meters intervals throughout
the cable tray/ladder path.
Manpower shall be deployed sufficiently throughout the length of the cable route to pull
the cable and ensure safe pulling.
Installation of control cable shall be carried out manually.
If the cable route length is short or within 50m interval then control cable can be cut at
site itself as per the exact route length and it shall be laid on tray/ladder directly
without placing the rollers.
Identify the tray in which the cables to be laid and marking on the cable should be done
for its destination panel.
Ensure the cable pulling is done with constant speed and minimum interruption.
Lubricant shall be provided if the cable passed through the duct/sleeve.
Continuous monitoring and proper communication shall be maintained throughout the
cable pulling process to ensure that the bending radius of cable is within the limit.
Ensure that extra loop length at terminations shall be provided, before cutting the
power & control cable.
For power cables, cut the cable at the required length by using hydraulic cable cutter
and provide shrinkable end caps to protect the cable from moisture ingress.
For control cables, cut the cable from the designation panel to source point using hand
cutter and insulate the cable end by using end caps.
Mark the phases of the cable end using colour tapes or cable identification tag to be
provided both side of the cable end once cable installed.
Post installation, proper safety of the cable shall be ensured.
Ensure exposed area of the cables shall be prevented from any damages caused after
cable laying.
After the completion of cable laying, remove the cable from the roller and place it on the
installed cable ladder/trays.
The laid cable shall be arranged in a trefoil or flat formation as per the approved
drawing and sufficient clearance shall be provided between each cable & circuits, if the
cable is power cable and for control cable it shall be arranged as per approved
drawings.
All the installed power cable shall be supported and fitted with cable cleats after
completion of cable dressing.
DUQM INTEGRATED POWER & WATER PLANT
Rev. A
(DIPWP) PROJECT
METHOD STATEMENT FOR INSTALLATION OF CABLES & RACEWAYS
Page 9 of 14
Document Ref. No(UEP): UE‐035/2019/S/S‐MS/002
All the installed control cable shall be dressed in a proper way and supported with cable
tray by using cable tie/clamp.
The maximum spacing of the support or cleat shall not be more than 1.5M.
All the cable support shall be earthed by appropriate earth conductor and linked with
substation main earth grid at both ends.
Sheath test and insulation resistance test shall be conducted after cable laying and
before termination, to ensure there is no damage on the cable post installation.
After completion of cable pulling, entire route shall be cleaned.
Cable Glanding and Termination Procedure;
Cable gland and termination works shall be performed by certified and approved
technicians under the supervision of competent person.
Cable gland and termination/jointing shall be complying with the manufacturer’s
instruction and recommendations.
Proper tolls shall be used to fitting gland plate and gland.
Adequate floor space shall be provided for cable gland & termination.
Identified the cables which are to be terminated and shall be stripped outside carefully
using heavy duty knives.
Select the proper size of the gland and insert the gland into the cables, lock the cable
with the base plate of the panel with help of lock nut.
Check the same procedure to be carried out, another end cable in the destination panel.
Ensure gland earthing is done properly with suitable size of earth wires.
MV & LV Cable termination:
It is mandatory to ensure that panel earthing is bar connected to substation main earth
grid to ensure the protection of panel.
Cable termination works shall be carried out under controlled environment condition
to prevent ingress of moisture & dust.
Complete preparation of cleaning, plumbing of metallic sheath and earth bonding shall
be carried out before the termination works commences.
Ensure suitable and approved size of lugs is being used for termination of the cables.
Crimp the cable lug with proper hydraulic crimping tool and ensure it is properly
crimped.
Heat shrink shall be done for the exposed portion of the conductor after crimping and
heat with baking gun all around until it is properly shrink with the cable.
Ensure the cable arrangement and continuity checks are to be carried out prior to
proceed for testing.
Megger and Hipot test shall be performed after the completion of cable termination
works and prior to terminate the cable with the equipment/panel/cable box, test
DUQM INTEGRATED POWER & WATER PLANT
Rev. A
(DIPWP) PROJECT
METHOD STATEMENT FOR INSTALLATION OF CABLES & RACEWAYS
Page 10 of 14
Document Ref. No(UEP): UE‐035/2019/S/S‐MS/002
reading to be noted.
Upon completion of hi‐pot test the cable shall be permanently terminated with the
equipment and contact resistance shall be carried out after termination, test reading to
be noted.
Ensure the provided cable tag is accordance with the approved cable schedule &
standards.
Clean the area after completing all the termination works.
Multicore Control Cables, I&C Cables, Fibre Optic, Ethernet & CAT Cables termination:
Identify the terminal block to which the wires have to be terminated.
Take out the wires from Multicore cable and remove the outer insulation till copper
core.
Ensure that the same types of lug are used for the termination of cables.
Insert the core into the lug, crimp the lugs using hand crimper and ensure it is properly
crimped.
Continuity and insulation resistance shall be carried out.
Follow the cable termination schedule for proper and correct termination and the
terminal shall be tightened using a washer and small screw.
6.2 Installation Procedure for Cable Raceways
Site preparation
Check the work area to ensure that no fire hazards including oily or greasy
materials are present.
Remove all combustible materials not necessary for the operation. Any
combustible material that cannot be removed should be covered with a flame‐
resistant material.
Check that all equipment is in good working condition
Inform workers in the immediate area and display warning signs at the
worksite to alert others of the potential hazards (tool box)
Install cutting shields/curtains to protect other workers from the sparks
and intense light associated with welding/cutting operations
When performing cutting, operations in areas on or around hazardous
materials, a hot work permit is required
Prior to cutting of cable trays, supervisory personnel must get a hot work
permit and shall verify that such cutting machine is working properly free
from damages any parts like power supply cable, other power tools
accessories.
DUQM INTEGRATED POWER & WATER PLANT
Rev. A
(DIPWP) PROJECT
METHOD STATEMENT FOR INSTALLATION OF CABLES & RACEWAYS
Page 11 of 14
Document Ref. No(UEP): UE‐035/2019/S/S‐MS/002
Correct Method Incorrect Method
If hand unloaded, workers should wear safety gloves.
To prevent damage to cable tray, never pull cable tray from a truck trailer
by chaining to the bottom rung and dragging cable tray out of the trailer.
Correct Method Incorrect Method
After unloading, inventory all items immediately using the manufacturer's
packing list.
Cable Tray & Support Installation
All support, tray and ladder shall be used in galvanized iron or as per IFC
drawings and it shall be installed free from sharp edges.
Support, trays and ladders shall be installed along the floor, ceiling/ sidewall
as per approved IFC drawings.
Distance from the top of the ladder or tray to the ceiling shall not be less
than 300mm or as per the approved construction IFC drawings.
DUQM INTEGRATED POWER & WATER PLANT
Rev. A
(DIPWP) PROJECT
METHOD STATEMENT FOR INSTALLATION OF CABLES & RACEWAYS
Page 12 of 14
Document Ref. No(UEP): UE‐035/2019/S/S‐MS/002
Support Ladders and trays shall be installed with a minimum free distance of
50mm or as per approved construction drawings (IFC) nearer to the wall, so
that the Cables can be accommodating between the ladders and the wall.
Expansion bolts for the installation of brackets/fixings shall be used with
such a distance between them, that the designated load for support, ladders
and trays will
Not be exceeded. When selecting the distance between the cantilever arms
or brackets/fixings, the bearing strength and designated load of ladders and
trays must be taken into consideration as per IFC drawings.
Galvanised iron cable trays, perforated types and ladders shall be installed with
two side joints I support brackets.
The holes along the trays shall be used for mounting with necessary accessories,
locking joints. Hold down clamps shall be used for fixing cable ladder with support.
Internal Cantilever arms shall be mounted on a vertical piece by using a T‐bolt.
Mounting rails shall be installed to reduce the surface pressure on a porous wall
when mounting an internal cantilever arm.
The internal cantilever arm is mounted onto the wall with an expansion bolt and
a concrete screw.
Internal cantilever arm shall be mounted right over support bracket/joint.
Support bracket/joint shall be used for straight jointing, push‐in
mounting.
End brackets shall be used as a vertical piece on a support bracket/ joint
mounted with screw sets.
Support bracket shall be used to achieve an invisible suspension in or in
connection with bends or junctions.
Support brackets shall be used for installation inside the cable
trays. Two side joints shall be used for straight jointing of the
cable trays.
Reducer shall be used for transition jointing from a wider to a narrower cable tray.
T joints shall be mounted in T or X branches on the side edges of the tray
with screw set.
T joints at straight angles by locking the lugs by using pliers or with
blind rivets or self‐tapping screws.
T joints at oblique angles in the same manner by locking the lugs by using
pliers or with blind rivets or self‐tapping screws.
End covers shall be mounted in cable trays locked with locking plug or
screw set. Adjustable bends shall be permitted horizontal angling for push‐
in installation.
Vertical risers shall be installed upward or downward angling up to 90
degree push‐in assembly. Vertical risers could be attached with a screw
set or Locking plug. Vertical risers could be flat and shall be bent on the
job site.
DUQM INTEGRATED POWER & WATER PLANT
Rev. A
(DIPWP) PROJECT
METHOD STATEMENT FOR INSTALLATION OF CABLES & RACEWAYS
Page 13 of 14
Document Ref. No(UEP): UE‐035/2019/S/S‐MS/002
- Project Engineer /Site supervisor will immediately correct any hazards observed or
reported to him. In the case of major hazards, work shall be stopped and
appropriate action will be performed to remove the hazard permanently.
- Ensure all HSE regulations are followed as per Client’s requirements.
-
8.0 Responsibilities
- Construction Manager is over all responsible for Safety, Quality and Progress of the
Project.
- Project Engineer/Permit holder is responsible for monitoring the daily activities at
site.
- HSE Officer will be monitoring all works are being carried out in accordance with
the safety requirements on site.
- Civil Engineer shall be responsible for the site construction activities and
implementation of all plans
9.0 Emergency
In case of Emergency,
- Stop the work.
- Switch off the work equipment, tools and machineries.
- Alert the nearby workers to reach to the nearest assembly point.
- Do not to get panic and do not run.
- Inform the site HSE officer and other key personnel from the emergency contacts
numbers displayed in the site.
- Call emergency services (9999 / 80077700) if required.
- Supervisor shall make head count and report.
10.0 Records
- Quality Records (Approved drawings & Shop drawings).
- Inspection forms (RFI/MRDR).
- As built drawings
- Test reports
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
Site:
DUQM INTEGRATED POWER AND WATER PROJECT
Name: NIZAR AHAMED Position: CONSTRUCTION MANAGER Date: 22/12/19
Assessed by:
Signed:
Residual
Risk
Risk
Task / Job Component Hazard Risk Persons at risk Rating Controls / Precautions to Reduce Risk
Rating
L/M/H
L/M/H
Ensure operator having Valid license/ third party
certificate
Inspect all lifting tools and tackles prior to start
lifting work.
Ensure Crane & lifting tools and tackles are valid
Personal third party certificate
Unloading of Cable drum‐ Injury/Fatality Installers, technicians Do not lift during adverse weather conditions
4*3=12 H L
Lifting failure Property and labourers Ensure no over headed power line
damage Ensure that outriggers are fully extended and it
shall not be close to the excavations
Ensure presence pf competent rigger
Ensure the proper clearance in between operator
and riggers
Cordoned off and affix sign board to avoid
unauthorized entry
Ensure ground is firm and stable
Fatality
Ensure proper soil compaction
Equipment Installers, technicians
Uneven /unstable ground 4*2=8 M Extend the outrigger fully L
damage due to and labourers
Keep wooden support beneath outrigger
fail.
Provide warning signboards
Doc
Rev A
Date 22/12/19
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
Ensure availability of banks man during heavy
equipment movement
Ensure first aid facility
All tools in use should be inspected and ensure
that they are appropriate to the task to be
performed.
Maintain good housekeeping and denial all
Injury to person
Dismantling of Packing Installers, technicians dismantled packing materials.
Damage to 2*2=4 L L
materials and labourers Remove all scattered nails from the surface.
assets
Do not store the packing materials in the site.
Ladders used must be in good condition.
Wear necessary PPE.
Presence of first aider at site
Strict supervision required
Only competent person to handle the tools
All electrical installations shall be inspected and
tested prior to use
All electrical installation and alterations shall be
undertaken by competent electricians only.
Adequate earth and ELCB with 0.03 A shall be
Unsafe handling of hand provided
and power tools Major/minor
Installers, technicians Regular inspection of electrical equipment, tool,
/Defective hand injuries/propert 4*4=16 H L
tools/equipment electric
and labourers and connections shall be carried out.
y damage
shock/poor earth Ensure properly rated cables, sockets are used
and safe condition of insulation cables.
Electrical equipment’s shall be away from water
to enter inside live wires.
Tools/equipment’s shall have relevant guards
fitted
Tools/fittings. Alignment and general condition
shall be inspected prior to use
Doc
Rev A
Date 22/12/19
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
Supervision should be present within the duration
of work
Skilled and experience workers shall be involved
Injury to in the activity
Unaware about work persons Installers, technicians TBT Should be conduct prior to start of work
3*3=9 M L
procedure Damage to and labourers Unauthorized employee not allowed to enter
assets Qualified first aider to be there in the site
Ensure good supervision
ERP should be communicated with concerned
work force
Ensure use of right type of tools for the job being
performed.
Upper limbs
All Tools should be Pre‐Inspected/calibrated.
disorder
Use of Home Made Tools Should not be used.
Muscular Installers, technicians
improper/substandard 2*3=6 L Routine inspections to check & replace poor L
Tools sculptor and labourers
conditioned tools.
Disorder
Periodic rest breaks & job rotation.
Personal Injury
Use proper PPE.
Work in early morning
Drink water frequently
Dehydration/Fat
Heat stress‐Working Wear loosely fitted clothes
igue Installers, technicians
under sunlight, Wearing 3*4=12 H Providing fans/blowers L
Injury to and labourers
tightly fitted clothes ERP(Emergency Response Procedure) should be
persons
communicated with all work force
Injury to person
Installers, technicians
Electrocution Damage to 5*4=20 H All work in the live equipment area shall be L
and labourers
assets carried out with Electrical Permit by authorized
Doc
Rev A
Date 22/12/19
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
Legal issues party.
Work shall only be under the guidance and
supervision of a competent supervisor
Tools shall be double insulated and only 110V
tools should be used.
ELCB to be tested before work starts.
Authorized and trained persons to carry out the
Job.
Prevent body contact with earthed surface
Ensure adequate information instruction, training
for all workers.
Isolate the machine/equipment and to be
connected to primary earth and double insulated
Affix sign board and cordoned off the area to
avoid unauthorized entry
All construction activities must be prohibited in
the panel erection area to avoid conflicting
activities
Complete PPE(Goggles, Safety shoes, safety
helmets ,coverall ,HV resistance hand gloves )
ERP communicated with concerned work force
Qualified first aider to be there in the site
Manual Handling‐ Resort to mechanical means (such as trolleys)
Heavy Objects where possible.
Injury to
Adopt safe manual handling method.
Sharp Edges persons
Installers, technicians Conduct necessary tool box meeting before start
Back Pain/Injury 3*4=12 H L
and labourers the activity.
Wrong Posture / Musculoskeletal
unsafe handling Use the strength of legs and not of the back while
Disorders.
lifting the load
Ergonomically Carry load with back straight, head erect, chin in,
Doc
Rev A
Date 22/12/19
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
issues arms close to the body and with watchful steps.
Maintain good ergonomically position
Check the weight to be handled and ask for
assistance (preferably a person of similar height &
physique) if it is unsafe to be handled alone.
If possible substitute with mechanical means of
lifting.
Be sure of the path in which the load to be
carried and the obstacles involved to avoid
sudden / awkward handling / manoeuvres
Period rest / job rotation.
Maintain good housekeeping.
Use appropriate PPE
Training in Safe Manual handling practice
Wear personal protective equipment’s like safety
helmet, hand gloves, coverall, safety shoes,
Pinch/nip point: goggles, etc.
Finger/hand struck Finger/Hand Installers, technicians
3*3=9 M Trained work force L
between injury and labourers
machine/equipment Maintain good housekeeping
Avoid horse play
Cordoned off the area and affix awareness signs
boards
Obtain valid Work permit from higher authority
prior to start work near the live area
Authorized Entry
Accidental
Valid gate pass
Entry into existing contact with Installers, technicians
5*4=20 H Competent person to be used L
Buildings/Premises energized part and labourers
Conduct Tool box meeting prior to work starts
Personal injury
Use all mandatory PPE.
Ensure Proper communication systems
ERP should be in place and communicated with
Doc
Rev A
Date 22/12/19
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
all work force.
Good supervision
Proper housekeeping should be done before start
the test.
Injury to
Use competent workers.
persons Installers, technicians
Slip, Trip and fall 3*5=15 H Inspect the work area thoroughly. L
Damage to and labourers
Plan the work and brief the crew.
assets
Safety induction & Tool box talk should be given
to work men.
Wear appropriate PPE like gloves, apron, and face
Heat shield.
Installers, technicians
Cable termination Burn injury 4*3=12 H Housekeeping to avoid fire L
and labourers
Fire Fire extinguisher standby
Fire watch to be present
Strict supervision required at all time
Major/minor Installers, technicians Access shall be free from obstruction of materials
Inadequate access and
injuries/propert 3*4=12 and labourers other H and to be identified easily L
egress
y damage contractor workers Suitable and sufficient safe access by means of
ramps or stair ways.
Strict supervision required at all time
Major/minor Installers, technicians Access shall be free from obstruction of materials
Inadequate access and
injuries/propert 3*4=12 and labourers other H and to be identified easily L
egress
y damage contractor workers Suitable and sufficient safe access by means of
ramps or stair ways.
Protect the floor opening with adequate
People and Installers, technicians
protective cover/ Barrication.
Floor openings material falling 5*4=20 and labourers other H L
Provide adequate illumination
down contractor workers
Provide warning signage
Doc
Rev A
Date 22/12/19
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
Never keep the openings open
Tool box talk shall be conducted every day before
starting work.
Inspection of ladders prior to use must carried
out and avoids using defective ladders.
Ladder must be secured at safe angle prior to use.
Do not carry any materials while climbing ladders.
Tool box meeting to be conducted on safe use of
ladder.
Assign competent supervisor to monitor the
activities
ERP Should be communicated with Workforce
Erect and inspect the scaffold by competent
Personal persons
Injury(Minor,
Scaffold should meet all required standard.
Major)/Fatality
Avoid conflicting activities and
Fall of person
Installers, technicians cordoned off the area to avoid unauthorized
Work at height Fall of tool. 4*3=12 H L
and labourers entry
Fall of materials
Use sufficient PPE
Collapse of
Comply the scaffold tag system for safe execution
scaffold, slip of
of work
ladder.
(Green‐ Safe for use
Yellow‐ Caution
Red‐ Danger)
Installation of physical guards/ railings.
Providing safe means of access/egress.
All scaffolds and inspectors required TPC.
Providing personnel fall arrest system (full body
harness).
Isolation of work area.
Weekly inspection to be done on
Doc
Rev A
Date 22/12/19
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
scaffolding/platforms.
Removal of all unnecessary equipment, tools and
materials from elevated locations.
While hot work at height use fire blanket to
prevent falling of spark, slag, and splatter.
Barricading the work area.
A string should be used to raise or lower tools
and materials, No throwing of materials.
Obtain valid Work permit from higher authority
prior to start work near the live area
Authorized Entry
Valid gate pass
Accidental
Competent person to be used
Entry into existing contact with Installers, technicians
Buildings/Premises
5*4=20 H Conduct Tool box meeting prior to work starts L
energized part and labourers
Use all mandatory PPE.
Personal injury
Ensure Proper communication systems
ERP should be in place and communicated with
all work force.
Good supervision
Hand or finger
bruise when
caught between
Use proper working platform.
supports and
Assistance must be there
floors
Avoid working on portable ladder for long
Installation/fixing of Back pain: Installers, technicians
M L
4*2=8 duration.
supports. extensive work and labourers
Proper concentration on work.
on floor by
Keep back bone straight.
sitting for long
Use of appropriate tools.
periods,
bending spine
for taking
Doc
Rev A
Date 22/12/19
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
measurements.
Extra care should be taken while doing grinding.
Double eye protection must be worn.
Fixed guards must be installed.
Only trained and experienced person should carry
out this task.
Unsafe /defective power tools must be reported
and mended.
Effective supervision at site.
Visitors must not be allowed nearby without eye
Hot sparks, protection.
flying metal Only angle grinder with dead man switch with no
particles locking system should be used.
Contact with Clutch system to avoid excessive pressure
rotating wheel Only approved wheel must be used.
Installers, technicians
Grinding /cutting Wheel 4*4=16 H Inspection of wheel before use. L
and labourers
disintegration Position correctly when not in use
Electrocution/el Position on metal head when grinding is finished.
ectric shock Speed rated of grinding wheel must be as low as
Fire and no load speed of grinding machine.
explosion. Cutting wheel should be used only for cutting
purposes and not for grinding.
Only inspected and colour coded drill machine
should be used.
Double insulated equipment.
Extension cord or outlet socket should be
connected through ELCB or GFCI.
Keep working environment dry.
Obtain work permit if atmosphere is explosive or
flammable.
Doc
Rev A
Date 22/12/19
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
Ensure that combustible materials are removed
before starting of job.
Safety glasses and face shield must be worn.
Adequate guard around the moving part should
Entanglement be installed.
with bit or Only experienced workers shall carry out the drill
chuck work.
Entanglement of Competent person inspect all power tools
long hair, finger Repairing and replacing defective items.
ring, loose Effective supervision shall be carried out of the
clothing work task.
Electrocution/ Safety talk should be conducted to drill machine
electrical shock users.
Ejection of Installers, technicians Crafts should hold the drill machines firmly.
Drilling 4*4=16 H L
broken bits of and labourers Piece should be secured with vice work.
work pieces Keep glove, clothing jewellery and long hair away
Impact from from rotating bit.
unsecured Only inspected and colour coded drill must be
work(revolving used.
work pieces) Double insulated equipment or ELCB or GFCI
Stabbing or should be used in the circuit.
puncture from Drill bit should be handled with care.
the end of drill Use centre punch preferably.
bit. Drill machine should be positioned perpendicular
on the job piece.
Job piece must be secured on the vice.
Welding‐ Welders Use of welding shields, goggles, fireproof aprons,
Radiation cataract gloves, screen etc.
Installers, technicians
harmful to Burn injury 5*4=20 H Proper ventilation L
and labourers
naked eyes. Lungs ailment Provision of proper earthing
Splinters/slag. Asphyxiation Proper maintenance and inspection of welding
Doc
Rev A
Date 22/12/19
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
Harmful Fumes. Electric shock machine
Heat.
Electricity
Damaged
welding
machine/cables
Inhalation: dust
Personnel should use appropriate face mask.
while brush or
Allergic personnel should be avoided.
cleaning
Personnel should wear hand gloves and safety
workshop/ store
boots.
area.
Installers, technicians All nails and sharp edges to be removed.
Waste materials Uneven 2*3=6 L L
and labourers Different waste to be stored in different
materials
container.
surfaces
Dispose in specific areas on daily basis.
Sharp edges
Procedures for hazardous waste must be
Collection of
followed.
waste
Barricade the working area
Hold the cable tray firmly.
Use right tool suitable for task.
Fall of cable
While drilling hold the drill machine firmly using
tray, hand tool,
auxiliary handle.
Cable rack, tray and tray twisting Installers, technicians
cover installation
3*4=12 H Keep clothing, long hair away from rotating bit. L
entanglement and labourers
with bit. Tool and machine has to be secured while
working at heights.
Electric shock
Use properly inspected and colour coded drill
machine and provide GFCI or ELCB to extension
cords.
Manual handling of cable incorrect Mechanical help to be used as possible and with
Installers, technicians
trays, supports and technique of 2*3=6 L good supervision. L
and labourers
accessories within site. manual handling Environment: floor condition‐ free of obstruction
Doc
Rev A
Date 22/12/19
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
insufficient or poor lighting conditions.
Individual capabilities: physical capability health
condition, sex, physical fitness strength.
Toolbox talk to be delivered regarding proper
manual handling techniques considering with
Task: the distance of the load from the trunk.
Body movement or posture especially twisting
the trunk.
Load: seek for help when necessary, bulky, and
sharp, temperature, weight.
Eliminate sharp edges: if not possible it shall
properly covered by cloth or other means to be
placed safely.
Nails to be removed or bended.
Nicks and Installers, technicians
Sharp edges 2*3=6 L Area to be barricaded as well as signs are L
scratches and labourers
indicating no entry for unauthorised person to be
posted.
Correct required PPE to be worn including gloves.
Installers, technicians Respiratory protection.
Harmful fumes Lung ailments 4*2=8 M L
and labourers Proper ventilation.
Dislocation / fall of job Burn injury. Installers, technicians
piece due to faulty Hit/ crush 4*4=16 and labourers, Other H Proper clamping of the job piece L
clamping. injury. contractors
Proper maintenance of the plant, use of
Loss of insulation/ loose Electric shock. Installers, technicians
5*4=20 H shockproof boots and hand gloves. L
connection of terminals. Fatality. and labourers
Provision of proper earthing
Fire /explosion Installers, technicians Ensure proper earthing
Improper earthing 4*2=8 M L
Electric shock and labourers Use proper PPE.
Doc
Rev A
Date 22/12/19
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
Use of trained personnel etc.
Installers, technicians Use of welding shields, goggles, fireproof apron,
Poor ventilation Asphyxiation 3*4=12 H L
and labourers gloves, screen etc.
Proper ventilation.
Regular inspection of welding machines prior to
Damaged cables of Installers, technicians
welding machines.
Electric shock 4*5=20 H use. L
and labourers
Replace damaged cables and wires.
Personal injury
Installers, technicians Guarding to be ensured.
Grinder without guards Cuts and 5*5=25 H L
and labourers Use PPE.
abrasions
Doc
Rev A
Date 22/12/19
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
I have read and understand how I am to carry out the activities listed in this RA.
I have been supplied with the personal protective equipment identified on this JSA and I have been given training in the safe use of this equipment.
I have read and understand the requirements set out in the material safety data sheets for the hazardous substances identified in this RA.
Date Position / Job title Name Signed Date Position / Job title Name Signed
Doc
Rev A
Date 22/12/19
Alghanim, Cobra, Tedagua, Sojitz, Power and Water LLC
RISK ASSESSMENT
Likelihood
How often could the hazard occur? Consider the task, frequency,
duration, method of work, employees involved.
Severity
How serious would the hazard’s effects be if
realised? Consider the type of hazard, biological, ergonomic, physical
and chemical.
Doc
Rev A
Date 22/12/19