ii.

a section entitled ―Drawings‖ which consists of conceptual drawings that are


sufficiently detailed to communicate the Bidder‘s Design intent for all
components of the proposed Sewage Treatment Plant.The conceptual
drawings shall include the following:
a. a site plan showing the location of the STP area, alignment and limits to
the Bidders construction activities; along with the land required for the
total planned area for STP. The site plan / layout shall include new STP,
Layout of various units of preliminary and secondary treatment, Layout
of piping between various units and unit bypass for each unit, plant
bypass, Layout of internal roads, hard standing, parking, compound wall
and gate house, etc. Location of power transformer, switch room, control
room and switchgear, Power wiring and underground cable layout,
Relative location of administrative office, lab and control centre, Internal
roads and parking provisions, Landscaping and reservations for future
expansion, possible future tertiary treatment and Any other features for
safe and efficient working during operations and maintenance.
b. a site plan showing all proposed works listed in the Bid Data Sheet;
c. a detailed narrative in support of the conceptual drawings setting out the
Bidder‘s plan for compliance with the Design-Build Services Schedule
and the technical standards set out in the Technical Standards Schedule,
to include construction quality assurance and control;
iii. a detailed program and schedule setting out the proposed sequence of works
to be undertaken, including estimated start date, finish date and time
allocations for individual units of the works, proposed resources to be
allocated and the identification of all major milestones, including the
submission of schematic Design documents, Design development documents,
the Design-Build Documents and the commissioning of individual units of
the Sewage Treatment Plant (STP); and
iv. an itemised list of the principal codes of practice and standards proposed to
be used for the Design-Build Services
3. a section specifying the power consumption for Operations and Maintenance of
the STP on an annual basis. The Bidder shall further provide the breakup of
electricity consumption in various facilities in the STP on an annual basis. The
Bidder shall provide the total estimated connected load in KW, maximum power
demand, average energy consumption in kWh per day with full load up to the
installed capacity of the STP, estimated power factor, any proposals for
improving efficiency in terms of lower power consumption.
g. For Interception & Diversion Works: Part-I of the Technical Section of the Bid for
Network and/or Interception & Diversion Worksshall consist of the following sub-
parts in the following order:
1. An Executive Summary of the Technical Section;