No.

Hari, Tanggal
1. 06 Mei 2019 - 31 Mei 2019

2. 01 Juni 2019 - 17 Juni 2019

3. 18 Juni 2019 - 01 Juli 2019

4 02 Juli 2019 - 13 Juli 2019

5. 14 Juli 2019 - 8 Agustus 2019


Job Description
1. Pembuatan dudukan kanal untuk gearbox project increase speed PM7
2. Welding and Grinding base plate for construction gearbox project increase speed PM7
3. Alignment base plate gearbox
4. Alignment gearbox sesuai gambar kerja
1. Check gap antara roda stretcher PM3
2. Cleaning chain Stretcher PM3
3. Change casing cover pump P19 SP3
4. Change bearing unit SP29 SP3
1. Change doctor blade size press top bottom PM7 (project increase speed PM7)
2. Change doctor blade dryer 41, and dryer 42
3. Assembly canvas roll group 9 bottom PM7
4. Change roll size press top bottom PM7
5. Preventive dan inspection PM7 (trial production)
6. Repair pipa oli yang bocor
1. Checking clearence bearing size press (spare) TS and DS
2. Check clearence bearing PM7 G3 CR08, G8 CR15
3. Change bearing pulley rope size press PM7 (2pcs)
4. Change bushing M-AP-1 PM5
5. Change and add Gland Packing
1. Install new pump area SP3 lt1
2. Welding and Grinding base plate for construction new pump project drum pulper
3. Alignment base plate for new pump SP3
4. Alignment new pump sesuai gambar kerja
5. Install coupling for motor new pump
6. Install new pump area SP3 lt0
7. Repair oscilating doctor DC10, 12
8. Repair Jumbo roll ex press1 top bottom
9. Project drum pulper alignment stopper drum pulper
10. Checking flatness drum pulper with dial indicator
11. Install screen drum pulper
12. Alignment base plate for new pump SP7
13. Install new pump area SP7
14. Assembly new pump for drum pulper area outside
15. Alignment base plate for new pump drum pulper area outside
16. Install new pump area outside
17. Assembly base frame for gearbox drum pulper