SHAMS AR-RIYADH PROJECT

Inspection and Test Plan


ITP No. PC-ITP-001
Creet International Contracting Co. Ltd Excavation and Backfilling Works
Date: 22-Jan-20
Inspection Test Requirements Inspection / Verfiation (Role)
Sl. No. Activity / Description Test / Acceptance Criteria Verifying Documents
Inspection Stage / Frequency Contractor Consultant Client

1 Approval / Permits /
Preliminaries:
Preparation of
- ITP
- Method Statement Prior to Start of
Approval Approval by Consultant E/H H R Approved Submittals
- Material Submittals Work
- Shop Drawings

2 Prepration of Excavation: - Level of excavatation as per


Including approved drawings.
- Survey, Mark-up - Irregularities encountered of the
- Excavation excavation the contractor shall
reinstate the area and fill to the Inspection Requests
Visual Upon Progress appropriate levels and compacted E W R (with approved shop drawings,
to the Consultant Satisfaction method statement as
reference)

3 Backfilling and Compaction - The Engineer shall check The


- Including Testing of results of The tests for The
Compaction adequacy of degree of compaction
Compaction
Once 1000sq.m
by comparison with The degree of
E Q1 R Inpection Request /
test compaction achieved Test Reports

Legends:
Q-Inspection, T-Test, W-Witness Point, H- Hold Point for Inspection (Mandatory), E-Execution,
R-Document Review, S-Surveillance, RE-Records, Q1- Inspection of 10% (Samples), Q2 - 100% Inspection

Submitted by: Approved by:


Name: Name:
Date: Date:
Sign and Stamp: Sign and Stamp:
Submitted by: Approved by:
Name: Name:
Date: Date:
Sign and Stamp: Sign and Stamp: