Professional Documents
Culture Documents
Cost
Cost
Cost
Estimation
Public Works Projects in Hong Kong:
The project will be even more expensive than the Hong Kong section of the controversial
high-speed rail project linking the city with Shenzhen and Guangzhou, which is set to cost
HK$84.4 billion after overrunning by HK$19.6 billion in 2015.
Construction of both the Sha Tin-Central link and the high-speed rail project is funded by the
government and carried out by the MTR.
A Transport and Housing Bureau spokesman declined to comment on the latest cost estimate but
stopped short of rallying behind the MTR – of which the government is the majority shareholder
with a 75 per cent stake.
“The government reserves comment on the cost estimate submitted by MTR Corp at this stage.
The Highways Department will ask MTR Corp to provide detailed information, and in
collaboration with its monitoring and verification consultant, critically scrutinise … [and] see if
there are sufficient justifications for the cost estimate,” the statement read.
Following confirmation, the government would then seek extra funding from the Legislative
Council “in a timely manner”, the spokesman added, so that construction works could carry on as
planned.
The corporation blamed the extra spending on preserving heritage sites uncovered near
the new Sung Wong Toi station, a delay in the handover of construction sites from the government
and incomplete works at the Exhibition Centre station in Wan Chai when it was handed over from
the government.
The government commissioned additional foundation works at Exhibition Centre station too,
MTR Corp said.
The rest stemmed from labour shortages, unfavourable ground conditions and tweaks to the design
and methodology, it said.
WHY ESTIMATING USING RISK ANALYSIS?
Estimating - All too often risk is either ignored or dealt with in an arbitrary way
by simply adding (about) 10% "contingency".
(a) Base Estimate: The "risk free" part i.e. the certain features,
the work that is unlikely to change, prepared by pricing the
known features using current rates and prices and standard
techniques appropriate to the stage of the project.
(b) Average Risk Estimate: The Base Estimate plus Average Risk
ERA Allowances.
There are two types of Risks viz :