Professional Documents
Culture Documents
OM - Case - Analysis - Donner Company Case Report
OM - Case - Analysis - Donner Company Case Report
Prepared by:
Preparation Stage
Punch
Customer Order Raw Artwork Inspect &
Tooling
Order Material Generation Shear
Holes
Image Transfer
Drilling DFPR
DFPR Panel Etch & Tin
Manual Metallization Laminate & DFPR Develop Electroplate Strip DFPR
Pre Sttip
CNC Drill Expose
Fabrication
Profile Inspect,
Solder
Solder Dip Puch Press test &
Mask
CNC Router pack
Company financials:
Donner has started registering profit from the 2nd year of its operations i.e.
1986. The profits have continued to increase exponentially until August 1987.
In September we observe that there is a sharp dip in profit as compared to
previous months. This might be because of the problems or concerns listed.
Productivity
Quality
Delivery
$95.00
$45.00
Overhead costs (selling expense, Admin expense and Total Selling &
Administrative have increase slightly over the years which impacts Net profit
Note:
Labour utilization:
The production process of Donner is identified as made to order. Donner is
capable of handling orders with high degree of variability in quantity and size
of the order facilitated by cross-trained workers. This offers great amount of
flexibility in handling customer orders, as the manpower is deployed as and
when required. This was demonstrated in the case when workers engaged in
manual drilling were shifted to other tasks.
However, utilization calculated across all the 3 stages comes to 40% (refer to
Section 2: Utilization calculation). So, there is opportunity to improve utilization.
Utilization is also brought down by factory layout design (as indicated by plater
spending 15% time in walking between desk and tanks)
<Include points>
Productivity, quality issue leading to returns & deadline misses are the issues
on the surface as highlighted by Donner management. A detailed analysis is
done in following section.
1. High variability in the order mix received on any given day is resulting
inefficient utilization of the workforce or available man-hours (from
below table in Section 2 we can see only 40% of man-hours available is
being utilized), because work is assigned randomly to each worker.
Additionally, there is a labour utilisation inefficiency that has come to
light recently (because of Wednesday’s events) where three workers
assigned to manual drilling had run out work.
2. The Plater worked at a desk inspecting panels and then carried the
panels to the plating times 18 feet away. Inserted them, and return to
inspect more panels. She interrupted her work at the desk every 3 or 4
mins, to inspect the panels in one of the tanks.
Altmeyer thought 15% of Plater’s time was spent simply walking
between the desk and the tanks
3. Since August, customer returns had increased from 1% to 3% (post-
delivery rejection rate). The company’s pre-shipment rejection rate has
amounted to 7%. Out of which, the incomplete operation rate is 6% (this
has to be reduced from 6% to 0%)
4. Amongst recent failures, a big problem with respect to the company’s
delivery efficiency was that their shipments had started averaging nine
days late. The delays were a result of the incomplete operation rate of
6% which were reworked
5. Flaherty delays the scheduling decision for several days until the raw
material arrives from the vendor. He only then estimates the labour
required in each step, examines the work in process, critical points, and
estimates the difficulties in meeting the new order’s expected shipping
dates
Assumptions:
Recommendations to Plummer: -
Finding minimum order size for using CNC drill against manual
drill
Let’s say the order size is N, then breakeven point will be given
by
15 + .004*500* N = 240 + 0.080*500*N
N = 5.92 ~ 6
Thus, if order size is greater than 6, CNC drill will be employed,
otherwise manual drill will be
used. However, Donner’s policy is to use CNC drill only when
the order size is great than 100
Finding minimum order size for using CNC drill against manual
drill
Let’s say the order size is N, then breakeven point will be given
by
15 + .004*500* N = 240 + 0.080*500*N
N = 5.92 ~ 6
Thus, if order size is greater than 6, CNC drill will be employed,
otherwise manual drill will be
used. However, Donner’s policy is to use CNC drill only when
the order size is great than 100
Finding minimum order size for using CNC drill against manual
drill
Let’s say the order size is N, then breakeven point will be given
by
15 + .004*500* N = 240 + 0.080*500*N
N = 5.92 ~ 6
Thus, if order size is greater than 6, CNC drill will be employed,
otherwise manual drill will be
used. However, Donner’s policy is to use CNC drill only when
the order size is great than 100
1. Finding optimal order size for using CNC drill vs Manual drill
This means, if the order size is greater than 6 CNC drill can used and for
order size less than 6 manual drill procedure to be used. This can help in
expediting the current process so as to avoid any delay. The current
strategy used at Donner (based on Exhibit 2 & 4) for order greater than
or equal to 140 is using CNC drill and the one less than 140 is being done
using manual drill method.
2. To find the optimal order size for choosing CNC Router over Punch Press
procedure.
This means, if the order size is greater than 200 boards CNC router can
used and for order size less than 200 boards punch press procedure to be
used.