Professional Documents
Culture Documents
Ongoing / Upcoming Activities at Manifa CHF Project: HSE HSE
Ongoing / Upcoming Activities at Manifa CHF Project: HSE HSE
HSE Manifa
Safety feedback Contact with live part
What happened
During the work activities, the employee came into contact with
energized lugs (400 volts) on the out-feed side of a breaker.
Why
He received instruction to replace two small transformer.
Fault analysis
Unusual wiring scheme was not considered by personnel in LOTO
process and an
Energized lugs
Transformers to
be replaced
HSE Manifa 2
Safety feedback Contact with live part
Causes
Wiring scheme outdated
Consequences
The employee was electrocuted from the shock,
fell against the lugs and due prolonged contact
died as a result of
VENTRICULAR FIBRILLATION
HSE Manifa 3
Lesson learned : Electrical Hazard
1. Electric shock / Electrocution
2. Electric fire & explosion
3. Electric flash & burns
Time
HSE Manifa
Lesson learned : Prevention
HSE Manifa
Safety : Administrative control Permit To Work System
Electrical Work Isolation Certificate Check list for electrical energization
This Certificate shall be used in conjunction The Electrical Competent Person should complete this
with the Permit to Work , for any activity to form and demonstrate that all necessary
be carried out on live electrical equipment isolations have been made and that the system or plant
or plant. is safe to be worked on.
Snamproget t i ELECTRICAL WORK Work Permit No
Issue date:
Location: 3rd NGL Ruwais ISOLATION CERTIFICATE
GENERAL INFORMATION
Answer with X where applicable: 1) Live work required ______ ; 2) Remote controls isolated ______ ; 3) Warning signs and barricades erected _____
4) Connected to ground/Earth ______ ; 5) Lock out and Tag out in place ______ ; 6) Suitable access/egress provede/available _____
7) Personal Protective equipment required ______ ; 8) Other hazard - specify ______ ; 9) Other disciplines/departments informed _____
WORK EQUIPMENT:
Associated Work Permits: 1) HOT _________ ; 2) COLD _________ ; 3) CONFINED SPACE _________
Is the prime mover to be Isolated from mechanical motive power? Yes No Tag & Lock Out No.
Is the prime mover to be Isolated from other power source? Yes No Tag & Lock Out No.
Is the power cable to be disconnected? Yes No Tag & Lock Out No.
Is control cable to be disconnected? Yes No Tag & Lock Out No.
Additional Safety Precaution
Special insteruction to be followed, in case of associated work permits (HOT, COLD or CONFINED SPACE):
The equipment and/or location where the work is to be done has been inspected and work is safe to do?
I hereby declare that the work is completed, all workers under my control have beed withdraw and warned that is is no longer safe to work on the apparatus
Subcontractor
specified in this permit and that tools, temporary earthing connection have been removed and the site restored to a safe tidy condition.
CANCELLATION
I accept that the work is completed/suspended and tht the site is restriced to a safe and tidy condition and that the apparatus
Contractor
HSE Manifa 6
Safety : Administrative control Access control
Contractor Signature
HSE Manifa 7
Safety measures : Lock Out Tag Out (LOTO)
TAG No.
DO NOT
OPERATE
CAUTION
REMARKS :
DATE :
SIGNED BY :
COMMISSIONING TEAM
FRONT OF TAG
Close or shut off all energy sources ,apply locks and/or tags, verify isolation
“Try method” - Try the switch Try the start button
HSE Manifa 8
Safety measures: LOTO application and Area segregation
HSE Manifa
Safety measures: HV Area segregation
HSE Manifa
Safety measures: Fire fighting and Rescue equipment
HSE Manifa
Thank you for your attention
HSE Manifa