Professional Documents
Culture Documents
Index Properties and Observations For Design of Chambers in Rock
Index Properties and Observations For Design of Chambers in Rock
ABSTRACT
Cording, E.J. and Mahar, J.W., 1978. Index properties for design of chambers in rock. In:
W.R. Judd (Editor), Near Surface Underground Opening Design. Eng. Geol., 12:
113--142.
The in-situ methods emphasized in this paper are used to relate rock index properties
to the performance of a tunnel or large chamber. The methods are carried out by explora-
tion prior to construction and by observations during excavation. The mechanics of the
deformation and the possible modes of tunnel failure should provide the basis for relating
the significant rock index properties to behavior.
Index properties of significance in tunneling can be divided into the following cate-
gories: the average quality of the rock mass, the properties of planar discontinuities, and
the properties of intact specimens. The average quality of the rock mass can be determined
from quantitative estimates of rock quality, fracturing, and weathering in the rock core.
Calibrated descriptive estimates may suffice. The average rock quality indices are partic-
ularly useful in the exploration stage in locating the low quality zones that may cause
tunneling difficulties. Properties of planar discontinuities, have a large influence on the
performance of large chambers but are more difficult to assess in the exploratory phase of
a project.
Loosening ground and highly stressed ground conditions and their influence on perfor-
mance of large chambers are summarized. The following design aspects are discussed:
(1) heading support requirements; ( 2 ) support spacing; (3) support displacements; (4)
support pressures and bolt lengths; (5) compatibility of initial and final support and inte-
gration of excavation and support sequences in large chambers. The size of the chamber
with respect to the wave length, continuity, and spacing of joints has an important
influence on support pressures and support selection.
Classification systems that directly relate rock indices to support can be used for a
preliminary estimate of support requirements. However, an additional step should be
included when evaluating performance:
(1) Evaluate geology and determine significant index properties.
(2) Outline expected ground behavior and its effect on construction. This additional
step requires a knowledge of construction procedures as well as the models of rock
behavior that are appropriate to the given geologic setting and excavation geometry. The
geologic data should be plotted in plan and cross-section views of the proposed opening
for each excavation sequence in order to identify potential problems and to check the
adequacy of the proposed support systems.
(3) Select support systems and construction procedures that permit the headings to he
safely and economically excavated, and that provide a permanent support suitable over
the intended life of the facility.
114
1. INTRODUCTION
made between methods used for small tunnels, large deep chambers, and
shallow chambers in rock. Most of the discussions refer to tunnels and
chambers excavated in loosening ground (rock fragments, blocks, and wedges
tending to separate from the surrounding rock mass and move under gravity
into the opening). Although other ground conditions such as squeezing, swell-
ing, slaking, flowing, and excessive water flows are encountered in tunnels,
treatment of these ground conditions is beyond the scope of this paper.
2. INDEX PROPERTIES
Method of OetemlnaUon
Field Happing,
Index Prolx~rty Regtonal Geology, Tuneel Application of the
Core Logging Lab Index Test In-Hole Tests R~ote Sensing, Exposures Index Property
Geophysical,
In Sttu Tests
Average RockMassQuahW
c. Creep properties Evidence of Constent load trl- Evaluate extent Observations Estimate presSUreS
she*red, ~ethered axisl creep tests of she~r zones of squeezing and defomttuns on
and low qunllty end plastlclty 11ntngs tn squeezing
rock indices ~ -- ground
4. In-Sltu Permeablhty Fracturing, open Simple penmb111ty 8orohele Evidence of fault Water problems In
zones In dr1111ng tests for porous mter pres- zones, civttles, tunnel
mtertsls sure tests, other hlgh perme-
punplng tests a b i l i t y zouns
--1
118
TABLE II
drilling process and subsequent moisture changes during storage may cause
the core to break along partings. Thin-bedded shales c o m m o n l y exhibit this
behavior, and if the breaks are included in the estimate, the RQD will be very
low.
(4) Smaller core size than NX. Additional breakage will take place using
smaller diameter core than NX, and the size of the pieces tends to be propor-
tional to the core diameter.
(5) Weathering. Weathered zones along joints or in the rock mass will
produce lower RQD values. At one site in a granite gneiss, the highly
weathered rock could be distinguished from the partially weathered zone on
the basis of RQD. The highly weathered zone had RQD values less than 50%,
and occurred in the upper 3 m (10 ft) of the rock profile. Below a depth of
6 m (20 ft.), the rock was unweathered, and RQD values were greater than
85%.
(6) Shear zones. In unweathered schistose gneisses in Washington, D.C.,
shear zones or fracture zones were usually present where the RQD for a 5-ft.
core run was less than 60%. In some of these cases, slickensides and clay
seams were n o t easily observed in the core, but the shear zone could be
observed in the exposures in the tunnel at the locations predicted from the
low RQD values.
(7) Closely jointed and fractured zones. The RQD can be directly related
to the degree of fracturing.
(8) Core disking. High in-situ stresses may cause disking of the core into
thin wafer-like pieces.
(~)
(AO~
j (nS)
HEIGHT o f
DIP H F EQUIVALENT M I N I M U M CONDITION
ANGLE ' ROCK LOAD FOR FAILURE
One p l a n e sheared, c o n t i n u -
45 °- 60° 4S°. 30~ ( 25 - 43)B ous and p l a n a r ,
One plane s l i g h t l y w a v y
L o w l a t e r a l stresses In a r c h ;
Surfaces p l a n a r, s m o o t h , pos-
75 ° . 90~ 15"- 0° >lOB s i b l y open, or progressive f a i l -
ure a i d e d by s e p a r a t i o n alan
low angle joints
i waviness
00--5 ° planar
5°--10 ° slightly wavy
10°--20 ° wavy
~20 ° very wavy
Failure of wedges formed by low-angle joints (Case 1: 0o--30 ° dip) is pos-
sible even if both sides of the wedges are wavy, offset, or rough. It is more
c o m m o n , however, if one joint is smooth and planar. For intermediate dip
angles (Case 2 : 3 0 ° - - 4 5 ° dip) wedge failures in the crown can occur if one
surface is planar and the other offset and wavy. In such a case the wedge will
tend to separate from the wavy surface. For joints dipping from 45 ° to 60 °
(Case 3) failure can occur even if one joint is wavy, although commonly, at
least one of the surfaces would be sheared.
For deep wedges to fail (Case 4 : 6 0 - - 7 5 ° dip), both surfaces must be
planar, smooth, and sheared. In this case, both surfaces are at their residual
strength.
The above discussions of wedge stability in the crown and resulting support
requirements assume t h a t displacements are small and that progressive loosen-
ing of deeper wedges is not allowed. Loosening in the haunches and sidewalls
can also influence the stability of the rock above the crown, particularly in
poorer quality rock, such as very blocky and seamy ground where the
loosened zone progresses from the walls into the arch along continuous, often
planar weaknesses. (For this reason, Terzaghi, 1946, considered both the
height and width of the opening in evaluating the height of rock load for
steel-supported tunnels.)
Planes that strike across the tunnel line will tend to cause support problems
at the face, if high-angle joints, and in the crown, if low-angle joints. The
orientations shown in Fig.4b are most critical.
FACEAFTERNEXT
i i •RIPTION--r/
tDRIVE
DISCONTINUITY/
PLAN
IAL FALL O U ~
5 4 3 2 1 12 3 45
SUCCESSIVEPOSITIONSOF DISCONTINUITYIN
TUNNELFACEASTUNNELIS ADVANCED
CROSSSECTIONAT TUNNELHEADING
(a) DIP DIRECTIONLESSTHAN (b) DIP DIRECTIONGREATERTHAN
90° FROMDIRECTIONOF 90° FROMDIRECTIONOF
DRIVE DRIVE
Fig.2. Relation of direction of driving to direction of dip.
oriented in such a way t h a t the rock block keys to other blocks and cannot
displace into the opening. In this case the rock mass has a strength due to the
interlocking effect of the rock blocks. In order for the block to fail it must
either shear through irregularities along the joint surfaces, or excavation
adjacent to the block must take place to free the block.
Minimal support is usually required when there is only one prominent set
of joints striking within 25 ° of the tunnel axis. When other intersecting joints
are absent, a single shear or joint will tend to cause only shallow slabbing and
overbreak near the perimeter of a circular tunnel; large block fallouts are not
likely (Fig.3). In a chamber with re-entrants, such as the haunch illustrated in
Fig.3, a single joint set can cause blocks to separate over a large portion of the
haunch, even in cases where the joint surface is irregular and has a high friction
angle. One could conclude from the above example that the design for a large
chamber would benefit from detailed exploration to locate all joint sets. This
detail is usually more feasible for a large chamber than a long tunnel, because
the exploration effort is concentrated in a small area.
2. 4. Stress slabbing
\
50' 24'
of material having a height equal to the distance to the top of the valley side.
For ot/a,, less than approximately 0.5, bursting would be expected (equivalent
to a oc/o v less than 10, assuming oc is 20 times or). Although stress conditions
near this limit do not produce major rock bursts, they may be of substantial
economic consequence in the excellent quality rock because of the require-
ment for support -- even light support -- in a cavern that would otherwise be
unsupported (Brekke, 1970).
Other investigators indicate that rock bursts or stress slabbing may develop
for values o f a c/ol less than approximately 4 to 6 (Cording et al., 1971; Cook,
1973; Barton et ah, 1974). In high strength quartzites, a¢ = 200 MPa (30,000
psi), Cook (1973) indicates that a ratio of o~/ol less than 1.5 results in
inability to keep a mine open. In a low strength rock, such as a t u f f having
% = 10 MPa (1500 psi), the same ratio would produce new fractures and
slabs around the openings as they are excavated, but a much smaller release
of energy. Popping rock rather than major bursts would be expected (Cording
et ah, 1971).
In heavily jointed and sheared rock, deformations take place along the
existing discontinuities, and rock slabbing or bursting is not as evident. How-
ever, massive rock adjacent to fault zones and fractured rock may exhibit
prominent stress-slabbing conditions.
Some of the early work regarding stress concentrations around openings
placed emphasis on determining maximum stress concentrations and shaping
the opening to reduce the stress concentrations to a minimum. However, the
location of the highest stress concentration occurs around the smallest radius
curves and does not involve a large volume of rock. Of more importance are
the zones where large stress differences exist to depth, behind the large radius
surfaces, such as the high side walls of a powerhouse. The stability of such
areas can be even more critical when joints or bedding planes parallel the
surface. For example, although stress slabbing developed to a depth of
1--2.5 m (3--8 ft.) on the surfaces of a 30-m (100-ft.)-diameter rock bolted
cavern in a highly stressed t u f f (~c/ol = 1.5) the most critical condition
occurred on the 36-m (120-ft.)-high planar sidewall where a high-angle joint
set almost parallel to the wall combined with new fractures due to high stress
to allow large block movements to a depth of 6--9 m (20--30 ft.) (Cording et
al., 1971). Nearby, in an identically shaped second chamber with the same
initial rock-bolt support, joints did not parallel the wall and stability problems
did not develop. Conversely, had the cavern been constructed in a rock mass
with the same joints almost parallel to the wall, but in a rock of higher intact
strength (for example oclol > 6), it is doubtful that major stability problems
would have developed.
From their experience in caverns in Norway, Selmer-Olsen and Broch
(1977) emphasize the importance of minimizing the length of planar walls of
a cavern that are parallel to the direction of the maximum principal compres-
sive stress. They show desirable cavern configurations to minimize the support
requirements for both highly stressed and moderately stressed ground, for
various ratios of horizontal to vertical stress.
125
In shallow chambers, and even in many chambers at depth, the stress levels
are low enough that major difficulties with stress-slabbing do not develop. In
these cases, the opening shape and the required rock support are primarily
determined on the basis of the geometry of the rock discontinuities so that
the critical rock wedges (such as those described in Section 2.3) are properly
supported.
3. SUPPORT
Steel Rtbs ~, I
! I
I
,,
I
__J
~aJ~ ! ~ Reach ~j
Fully grouteds p / ~
l
/ 7/¢
Fig.4. Support at heading, a. Examples of reach, b. Use of spiling for support ahead of the face.
127
Spacings for rock bolts typically range from 1 to 3 m (3--10 ft.), with the
wider spacings used in excellent quality rock or in rock having an inter-
mediate support system such as shotcrete and mesh. Rock-bolt spacings
should also be less than 1/2 the bolt length (Lang, 1962; Dept. of the Army,
1975).
In most small tunnels, and in some large chambers in excellent quality
rock, if the selected supports are spaced so that they provide adequate protec-
tion, they usually have sufficient capacity, or can be easily dimensioned, to
carry the anticipated rock loads. This is not the case in very large chambers
or in intermediate-sized chambers in poor rock.
Most rock tunnels and chambers, particularly those at shallow depth, are
located in loosening ground. For such tunnels, the support should be placed
as soon as possible to minimize rock loads. The loads that develop will be a
function of the geometry and strength of the discontinuities, the displace-
ments allowed, and the size and geometry of the opening.
Ground reaction curves for elasto-plastic or creep-sensitive materials, such
as those described by Rabcewicz (1969}, show that the pressure required to
support the opening decreases as the inward displacement is allowed to
increase (Fig.5a}. Delay in placing supports results in less load on the support.
In many loosening ground conditions, however, the rock mass is stiff enough
so that only small displacements are required to reduce the pressures to mini-
m u m levels, and the support placement need not be delayed to develop
minimum pressures. In fact, any delay in placing the support will result in
loosening of the ground and a reduction in the strength of the mass, so that
the rock loads increase (Fig.5b). In shallow rock chambers, it is particularly
important that loosening be limited by early placement of support so that
the thin rock arch is preserved.
Support
Pressure,
Pi
Displacement Ol
Support \
Pressure, Support
Pi ~ InstalIe d ~
, .
b DIsplacenmnt
d
Fig.5. Ground reaction curves, a. Squeezing ground, b. Loosening ground.
sidewall than in the arch. However, the high sidewalls used in many large
chambers can present a more critical stability condition than the arch when
major shear zones or joints intersect the chamber surface. Substantially
longer bolts and higher support pressures may be required on the walls when
adversely oriented joints or weak zones are present.
Since Terzaghi's work, many rock-classification systems have been
developed for use in evaluating tunnel ground conditions and support require-
ments. A large number of classifications are developed for specific sites, and
are appropriate for specific geologic and construction conditions. Such classi-
fications provide a basis for communicating between various parties engaged
in the project. Other investigators have developed systems for more general
use. Lauffer's well-known classification (1958) relates standup time to tunnel
rock behavior and opening width. More recently Linder (1963) has correlated
Lauffer's rock descriptions with support design for use in tunnels. Deere et al.
(1969} summarize typical support types and dimensions for 6--12 m (30--
40 ft.)-wide tunnels as a function of the RQD. Wickham et al. {1972), Barton
et al. (1974) and Bieniawski (1976) have each developed classification
systems that include RQD and other significant rock indices. From these
indices a classification number can be obtained that is correlated with support
requirements. The description of significant index properties is one of the
most useful aspects of the classifications. In many cases, the individual indices
may be of more benefit in describing potential tunnel ground conditions than
a combined classification number, particularly when using the systems with
different geologic and construction conditions.
a relatively small area. Not only should the average quality of the rock
throughout a large chamber be determined, the major shear zones and other
low-quality zones should be specifically located and oriented with respect to
the walls and intersections of the chamber. Support of benches, haunches,
and intersections in the opening may be affected by a single, unfavorably
oriented joint set and consequently the orientation of all major joint sets
should be determined in the exploration. Although information can be
obtained from borings, the most complete exploration information is
obtained from a pilot tunnel driven at the location of the chamber.
In long tunnels it is not usually possible or necessary to locate all major
shear zones. An estimate should be made of the relative percentages of the
various tunnel ground conditions expected. The orientation of the major
structures and an estimate of their frequency and character should be deter-
mined for given reaches of the tunnel.
Once the geometry and strength of the rock mass and its discontinuities
have been estimated, critical wedges can be selected on the basis of criteria
such as those outlined in Fig.1. Analyses of displacements and stress around
the opening, using finite element models with joints, may also provide insight
into the extent of the critical wedges that must be supported in highly
stressed ground. Proposed excavation and support sequences should be tested
against the given wedge geometries to determine if the chamber will remain
stable as it is excavated. Support pressures are selected so that the stability
of the critical wedges is maintained.
3. 7. Size effect
above bolt pattern. This may be the case for the Norwegian chambers des-
cribed by Brekke (1970}, where rock support, if used at all, is nominal and
bolt pressures required are small.
Some of the factors that affect the relation between support pressure and
opening size in loosening ground are outlined below and illustrated in Fig.6:
(1) Joint spacing with respect to size o f opening. For small openings with
widely spaced joints, the rock mass acts as if it has a cohesive c o m p o n e n t of
strength, and the pressure, P1, required to support the opening is reduced by a
cohesive term, C:
Pi = nB~--C
where C is a function of the ratio of joint spacing of the critical joint sets to
the tunnel diameter. In a small opening, little or no support may be required,
while in a large opening, where joints are closely spaced with respect to the
width of the tunnel, the cohesive component approaches zero, and support
pressures are large.
{2) If a large chamber is excavated and supported in increments, the
loosening of the rock around the opening will primarily be a function of the
width of the individual excavation increments, whereas a small tunnel
excavated full face will have a loosened zone proportional to its full width.
However, if through-going discontinuities are present in both cases, the rock
pressures may still be proportional to the width of the opening.
(3) If the continuity of shears or joints is substantially less than the width
of the opening, then large wedges may not be able to form, and the rock
pressures will not increase in direct proportion to the width of the opening.
The wavelength of the irregularity with respect to the width of the tunnel is
another scale effect that influences pressure. In the Washington, D.C.
chambers, the joints and shears are planar and continuous so that the pressures
tend to scale with the width of the opening.
(4) Support of a large tunnel is made more difficult not only because of
increases in rock pressure, and changes in the scale of the joint spacing with
respect to opening width, but also because of the increased construction
problems in excavating and installing support, and the limitations of the
support system. For example, if a straight-leg steel support is placed in a
small tunnel, it can be braced to provide resistance to side loading by placing
an invert strut across the b o t t o m of the tunnel. In a tunnel with a high side-
wall, a heavy straight-leg steel support would not be capable of providing
substantial lateral support even when an invert strut is installed. In a large
tunnel heading, not only are the rock loads increased, but the size of the face
and the disturbed zone ahead of the face is enlarged, making it more difficult
to install the support safely in the heading.
the procedures used for the 18-m (60-ft.)-wide stations in the foliated schists
on the Washington, D.C. Metro, where rock cover over the crown may be as
little as 9 m (30 ft.).
The running tunnels (R) are excavated with tunnel-boring machines
through the station area prior to the construction contract for the main
station. The running tunnels and pilot tunnel (P) provide an opportunity for
rock-bolt support to be placed, n o t only immediately adjacent to the existing
excavations, b u t also over the arch of the station, above the areas y e t to be
excavated (Figs.7a and 7b). The bolts perform a similar function as the
spiling in Fig.4, b u t are placed laterally over the arch prior to excavating the
main portion of the station.
Once the rock arch is pre-supported with fully grouted rock bolts, the
upper heading can be excavated, placing the arch support on the foundations
set in the running tunnels (Fig.7c). The height of the upper heading and
volume of material excavated in this stage is greater than would be possible
without the bolted arch, because the grouted bolts in the arch have reduced
the potential for failure above and ahead of the face. In one of the station
excavations in Washington, it was observed that the face of the excavation
had broken ahead approximately 3--4.5 m (10--15 ft.) further than the ends
of the blast holes. The fallout of rock was confined to the excavation limits by
the rock bolts, and did not proceed above the arch, as would have occurred
had the bolts n o t been present (Cording et al., 1977).
Because of the shallow cover and the presence of steeply dipping shear
zones striking parallel to the station axis, the rock bolts alone do not provide
sufficient support for the arch. A final lining of light steel ribs encased in
shotcrete or concrete is installed as the upper heading is excavated. The
amount of support required using this procedure is much less than would be
required if heavy steel ribs were installed to support the arch, and then the
permanent concrete lining were placed at a later date, after excavation was
completed.
4. OBSERVATIONS
The observation program for a large chamber differs from the program for
a tunnel. A large chamber opened b y excavations in sequence is much more
difficult for the miners and engineers to observe, compared to a small tunnel
that is opened full face and immediately supported. Thus, more reliance must
be placed on measurements of rock movement and support performance with
a large chamber. R o c k displacement measurements can provide early warning
of potentially unstable conditions. For a large chamber, opened in increments,
there is an. opportunity to monitor the displacements during several sequences
of excavation. Movements and support loads observed during one sequence
can be used to determine the adequacy of method for the next sequence, and
corrections to the excavation and support procedures can be made, if needed.
b~
135
Fig.7. Excavation and support sequence, a. Excavation of running tunnels (R) and pilot
tunnel (P) and installation of rock bolts, b. Enlargement of pilot tunnel (Stage 1 ) excava-
tion of corner (Stage 2) and installation of wall plate (Stage 3). c. Excavation of main
heading (Stage 4). Installation of arch (Stage 5). Removal of remainder of invert (Stage 6).
136
Displacement magnitude
Elastic or elasto-plastic continuum solutions are quite useful for compari-
son with the observed displacements in a rock tunnel or chamber, even
though the rock mass may suffer large displacement along joint surfaces and
not behave as a continuum. The continuum solution is valuable because it
provides an estimate of the displacements the mass would undergo if loosen-
ing along the joints were minimized. Unstable conditions may exist if displace
ments are large with respect to the displacements predicted from elastic
theory.
Either a closed elastic solution, assuming simple boundary conditions, or a
finite-element elastic solution that approximates the more complex boundary
conditions in a chamber, can be used to estimate the elastic displacements.
The rock movements measured in deep tunnels and chambers, such as
those constructed for powerhouses, are typically on the order of 1--3 times
the movements one would calculate from elastic theory, using an appropriate
in-situ rock modulus that accounts for the stiffness of the joints in the rock
mass (Deere et ah, 1967). Normal displacements in most of these chambers
were in the range of 2.5--7.5 m m (0.1--0.3 inch). Movements that occurred
where shear zones or other major discontinuities were not adequately
supported were typically in the range 12.5--75 mm {0.5--3.0 inch), approxi-
mately 5--10 times the elastic displacements. In most cases, movements of
this magnitude were recognized as being excessive, and corrective measures
were taken (Cording et al., 1971).
Displacement measurements previously obtained in stable sections of a
tunnel can be used to establish the typical behavior to be expected in other
portions of the project. For example, in the shallow Washington Metro
tunnels where the in-situ stresses were low, the calculated elastic displace-
ments were extremely small -- on the order of 0.25--1.25 mm (0.01--0.05
inch). Observed displacements for well-supported excavations were typical,
2--5 times the elastic displacements, and ranged from 0.5 mm (0.02 inch} for
small tunnels to 5 mm (0.2 inch) for larger excavations. Displacements of
0.5--1.25 mm (0.02--0.05 inch) were typical for 1.2--1.8-m (4--6-ft.) wide
rock blocks supported by a 50-mm (2-inch) thick shotcrete layer and fully
grouted, non-tensioned rock bolts (Cording et al., 1977). The displacements
represented the small a m o u n t of separation along the joints that occurred as
the tension increased in the bolts. The movements would not have been
substantially less than 0.5--1.25 mm (0.02--0.05 inch), even if the calculated
elastic displacement had been much smaller.
Rate of displacement
Displacement rates should be examined closely when evaluating the
stability of a tunnel. Sudden increases in the rate of rock movement that are
larger than would be expected for the increment of excavation carried out in
the vicinity of the extensometer may provide an early indication of an
138
dipping toward the excavation) and were planar and continuous. The sidewall
movements also caused loosening of rock to a distance of 6 m (20 ft.) above
the crown.
The magnitude of the displacements that will cause loss of strength of the
rock mass depends on the a m o u n t of displacement it takes to override or
shear off the irregularities so that the block will fall out or so that residual
strength will be reached on the joint surfaces. Where joints are planar and
slickensided, and sufficient joint sets are present to form blocky rock, the
displacements required to cause failure will be less than those where surfaces
are irregular and joints are discontinuous. This range of displacements is
estimated to be approximately 2.5--25 m m (0.1--1 inch) in Washington, D.C.
4. 3. Supplemental observations
6. CONCLUSIONS
The in-situ methods emphasized in this paper are used to relate rock index
properties to the performance of a tunnel or large chamber. The methods are
carried o u t by exploration prior to construction and b y observations during
excavation. In most cases, the estimation of tunnel stability and support
requirements is benefited more by careful observations of the geology and its
influence on tunneling than b y an extensive program of in-situ testing.
Index properties of significance in tunneling can be divided into the
following categories: the average quality of the rock mass, the properties of
planar discontinuities, and the properties of intact specimens. The average
quality of the rock mass can be determined from quantitative estimates of
rock quality, fracturing, and weathering in the rock core. Calibrated descrip-
tive estimates may suffice. The average rock quality indices are particularly
useful in the exploration stage in locating the low quality zones that may
cause tunneling difficulties.
Properties of planar discontinuities, such as the thickness of clay filling,
may be lost unless procedures for obtaining full core recovery are carried out.
The large-scale features of planar discontinuities, such as continuity and
waviness can only be observed in exposures.
Pilot tunnels not only provide exposures of the geology but can also serve
as an in-situ test in which the influence of rock properties on overbreak and
support requirements can be studied and used as an indication of conditions
to be expected in a large chamber. However, pilot tunnel support require-
ments may not be related directly to those for a large tunnel because of size
effects. The amount and type of support required may differ considerably.
As described in Section 3, support pressures in loosening ground will tend to
increase in proportion to the width of the opening. The relation is affected
by the geologic conditions illustrated in Fig.6; joint spacing with respect to
opening width, the continuity and waviness of joints, the size of the indivi-
dual excavation sequences, and the timeliness of support placement.
In comparing a small tunnel with a large tunnel, it should be recognized
that not only will support pressures differ b u t there will be a significant differ-
ence in the construction methods required to stabilize the heading and install
supports. Extrapolation of the observations from a small to a large tunnel can
be most appropriately made by "taking apart" and examining the geologic
features and construction procedures in the small tunnel, then putting these
features back together in the larger tunnel. The effect of the geologic indices
on the performance should then be examined by proceeding through potential
construction sequences for the large tunnel, step by step. One may find, in
"taking apart" and then putting the elements back together that pieces are
missing or do not fit. Such an exercise will clearly highlight the areas in
which behavior or support conditions are unknown.
141
A similar approach can be taken when using core borings and other
exploration data to estimate support and construction requirements. Although
classification systems and rules of thumb that directly relate rock indices to
support requirements can be useful, it is the writers' conclusion that an addi-
tional step is needed in the evaluation of support:
(1) Evaluate geology and determine significant index properties.
(2) Outline expected ground behavior and its effect on construction. This
additional step requires a knowledge of construction procedures as well as the
models of rock behavior that are appropriate to the given geologic setting and
excavation geometry. The geologic data should be plotted in plan and cross-
section views of the proposed opening for each excavation sequence in order
to identify potential problems and to check the adequacy of the proposed
support systems.
(3) Select support systems and construction procedures that permit the
headings to be safely and economically excavated, and that provide perma-
nent support suitable over the intended life of the facility.
Much can be gained by observing overbreak, fallout, evidence of slabbing
due to stress, rock movement, and support distress. The information should
be collected at the heading of the tunnel, as the rock is excavated and sup-
ported. Observations of support procedures immediately after blasting are
particularly important. Rugged, reliable instruments that can be installed,
read, interpreted, and related to geologic conditions in a timely manner can
contribute much to the observation program.
REFERENCES
Barton, N., Lien, R. and Lund, J., 1974. Engineering classification of rock masses for the
design of tunnel support. Rock Mech., 6(4): 189--236.
Bieniawski, Z.T., 1976. Rock mass classifications in rock engineering. In: Z.T. Bieniawski
(Editor), Exploration for Rock Engineering. Balkema, Rotterdam, 1: 97--106.
Brekke, T.L., 1970. A survey of large permanent underground openings in Norway. Proc.
Int. Syrup. Large Permanent Underground Openings, Universitetsforlaget, Oslo,
pp. 15--30.
Cook, N.G.W., 1973. The siting of mine tunnels. Assoc. Mine Managers, No. 3/73.
Cording, E.J. and Mahar, J.W., 1974. The effects of natural geologic discontinuities on
behavior of rock in tunnels. Proc. Rapid Excavation and Tunneling Conf. AIME,
San Francisco, 1: 107--138.
Cording, E.J., Hendron Jr., A.J. and Deere, D.U., 1971. Rock engineering for underground
caverns. Syrup. Underground Rock Chambers, Phoenix, ASCE, pp.567--600.
Cording, E.J., Hendron Jr., A.J., MacPherson, H.H., Hansmire, W.H., Jones, R.A., Mahar,
J.W. and O'Rourke, T.D., 1975. Methods for Geotechnical Observations and Instru-
mentation in Tunneling. NSF Rep., UILU-ENG 75 2022, University of Illinois, Urbana,
Ill.,Vols. 1 and 2.
Cording, E.J., Mahar, J.W. and Brierley, G.S., 1977. Observations for shallow chambers in
rock. Int. Syrup. Field Measurements in Rock Mechanics, Zurich, pp.485--508.
Deere, D.U., Hendron Jr.,A.J., Patton, F.D. and Cording, E.J., 1967. Design of surface
and near-surface construction in rock. Syrup. Rock Mech., 8th, Minnesota.
Deere, D.U., Peck, R.B., Monsees, J.E. and Schmidt, B., 1969. Design of Tunnel Liners
and Support Systems. U.S. Department of Transportation, Washington, D.C., Contr.
No. 3-0152.
142