PROJECT : BEACON TOWER

LOCATION: Don Chino Roces St. cor. Arnaiz Ave., Makati, Metro Manila, Philippines

BILLS OF MATERIALS
MAT'LS LABOR EQUIP'T
ESTIMATED
ITEM WORK DESCRIPTION UNIT UNIT COST AMOUNT
QTY
UC UC UC
I. MOVILIZATION
MOBILIZATION / INSPECTION 10.00 Days 1,000.00 12,000.00 12,000.00

II. CLEARING/GRUBBING
Kitchen 3.00 Days 1800 1000 4600 6400
Shower Inclosure 2.00 Day 1800 1000 2800 4600
III. KITCHEN CABINETS 1.00 lot 47000 12000 1000 53000 60000
IV SHOWER INCLOSURE 1.00 lot 12500 5000 16000 17500
V KITCHEN DOOR 1.00 lot 5000 2000 6000 7000
VI FLOOR REPAIR 1.00 lot 1100 2000 500 2100 4100
VII PAINTING
Living / Kitchen Dining Area 3.00 gal 1000 5400 1000 7150 9400
Room-1 3.00 gal 1000 3600 1000 7150 7600
Room-2 2.00 gal 1000 3600 1000 6300 6600
CR 1.00 gal 850 1800 2650 2650
Ceiling 3.00 gal 1000 5400 1000 8950 9400
Grand Total 147,250.00