Minutes of The Meeting
Minutes of The Meeting
POINTS OF DISCUSSION
A GENERAL
1 DINING AREA MOCK UP YET MADE ,SAME TO BE MADE AND SHOWN BEFORE
FINALISATION.
2 MAIN DOOR MOULDING AND FLUTE SAMPLE APPROVAL TO BE GIVEN BY NKI.
3 TOILET VANITY DETAIL WORK TO BE STARTED AS PER SITE DISCUSSION WITH BOTH
VANITY FINISH TO BE PU
4 BOTH THE TOILET MIRROR DETAIL GIVEN TO SIRAJBHAI,SAME TO BE COMPLETED.
B KITCHEN
1 KITCHEN OVER HEAD SHUTTERS TO BE FINISHED IN PU AND CABINET BELOW THE
COUNTER TO BE FINISHED IN LAMINATE AS APPOROVED BY THE CLIENT.
2 KITCHEN AREA CHIMNEY SWITCHBOARD TO BE SHIFTED AS PER SITE DISCUSSION
KEEPING IT IN THE SHUTTER WHERE CHIMNEY WILL BE INSTALLED.
3 TALL UNIT WORK TO BE STARTED AS DISCUSSED ON SITE WITH MICROWAVE OVEN
SHELF HT TO BE 14” AND FLOOR TO WASHING MACHINE HT TO BE 41.75”.
4 SHUTTER TO BE MADE ABOVE THE MICROWAVE IN THE TALL UNIT.
5 ALL DRAWERS TO BE BASKET DRAWERS IN THE KITCHEN EXCEPT ALL THE DRAWER
OF 4” TO BE TANDEM AS CONFIRMED BY THE CLIENT.
6 PULL OUT DRAWER TO HAVE ONE VERTICAL AND ONE HORIZONTAL DIVISION IN
THE BASKET TROLLEY AS DISCUSSED ON SITE.