Professional Documents
Culture Documents
Ua5000 Installation PDF
Ua5000 Installation PDF
Installation Process
Contents
4.1.2 Installation Process
4.1.2.1 Preparing for the Installation
4.1.2.1.1 Tools and Meters
4.1.2.1.2 Checking the Construction Environment
4.1.2.2 Unpacking and Accepting Products
4.1.2.2.1 Checking Before Unpacking
4.1.2.2.2 Unpacking the Carton
4.1.2.2.3 Unpacking the Board
4.1.2.2.4 Accepting the Product
4.1.2.3 Installing the Cabinet on a Concrete Floor
4.1.2.3.1 Outline of the Installed Cabinet
4.1.2.3.2 Installation Process
4.1.2.3.3 Recommended Tools
4.1.2.3.4 Checking Before the Installation
4.1.2.3.5 Marking Reference Lines
4.1.2.3.5.1 Marking Reference Lines Based on the Construction Plan Drawing
4.1.2.3.5.2 Marking Reference Lines Based on the Marking-off Plate
4.1.2.3.6 Drilling Holes
4.1.2.3.7 Installing Expansion Bolts
4.1.2.3.8 Placing the Cabinet
4.1.2.3.9 Leveling the Cabinet
4.1.2.3.10 Fastening the Cabinet
4.1.2.3.11 Testing the Resistance
4.1.2.3.12 Attaching Cabinets
4.1.2.3.13 Recovering the Cabinet
4.1.2.4 Installing the Cabinet on an ESD floor
4.1.2.4.1 Outline of the Installed Cabinet
4.1.2.4.2 Installation Process
4.1.2.4.3 Recommended Tools
4.1.2.4.4 Checking Before the Installation
4.1.2.4.5 Marking Reference Lines
4.1.2.4.5.1 Marking Reference Lines Based on the Construction Plan Drawing
4.1.2.4.5.2 Marking Reference Lines Based on the Marking-off Plate
4.1.2.4.6 Drilling Holes
4.1.2.4.7 Installing Expansion Bolts
4.1.2.4.8 Installing a Single Support
4.1.2.4.9 Installing a Row of Supports
4.1.2.4.10 Placing the Cabinet
4.1.2.4.11 Leveling the Cabinet
4.1.2.4.12 Fastening the Cabinet
4.1.2.4.13 Testing the Resistance
4.1.2.4.14 Attaching Cabinets
4.1.2.4.15 Recovering the Cabinet
4.1.2.4.16 Recovering the ESD floor
4.1.2.5 Installing the surge protector
4.1.2.5.1 Installation Preparations
4.1.2.5.2 Installation Procedure
4.1.2.6 Routing External Cables
4.1.2.6.1 Rules for Routing Cables
4.1.2.6.2 External Connections of the ONU-F02A Cabinet
4.1.2.6.3 External Connections of the N66E-18 Cabinet
4.1.2.6.4 Process of Routing External Cables
4.1.2.6.5 Ports of HABA Shelf
4.1.2.6.6 Removing Side Covers
4.1.2.6.7 Routing External Power Cables and Ground Cable
4.1.2.6.7.1 Preparations
4.1.2.6.7.2 Routing Power Cables from Overhead (AC Power Supply)
4.1.2.6.7.3 Routing Power Cables from Underfloor (AC Power Supply)
4.1.2.6.7.4 Routing Power Cables from Overhead (DC Power Supply)
4.1.2.6.7.5 Routing Power Cables from Underfloor (DC Power Supply)
4.1.2.6.8 Routing Battery Connecting Cables
4.1.2.6.8.1 Preparations
4.1.2.6.8.2 Procedure
4.1.2.6.9 Routing Subscriber Cables
4.1.2.6.9.1 Preparations
4.1.2.6.9.2 Routing Subscriber Cables from Overhead in the Distributed Configuration (Rear Access)
4.1.2.6.9.3 Routing Subscriber Cables from Overhead in the Distributed Configuration (Front Access)
4.1.2.6.9.4 Routing Subscriber Cables from Underfloor in the Distributed Configuration (Rear Access)
4.1.2.6.9.5 Routing Subscriber Cables from Underfloor in the Distributed Configuration (Front Access)
4.1.2.6.9.6 Routing Subscriber Cables from Overhead in the Integrated Configuration
4.1.2.6.9.7 Routing Subscriber Cables from Underfloor in the Integrated Configuration
4.1.2.6.10 Routing Trunk Cables
4.1.2.6.10.1 Preparations
4.1.2.6.10.2 Routing Trunk Cables from Overhead
4.1.2.6.10.3 Routing Trunk Cables from Underfloor
4.1.2.6.11 Routing Network Cables
4.1.2.6.11.1 Preparations
4.1.2.6.11.2 Routing Network Cables from Overhead
4.1.2.6.11.3 Routing Network Cables from Underfloor
4.1.2.6.12 Routing Optical Fibers
4.1.2.6.12.1 Preparing for the Connection
4.1.2.6.12.2 Routing Optical Fibers from Overhead
4.1.2.6.12.3 Routing Optical Fibers from Underfloor
4.1.2.6.13 Installing Side Covers
4.1.2.6.14 Installing the Sensors
4.1.2.6.14.1 Installing the Smoke Sensor
4.1.2.6.14.2 Installing the Water Sensor
4.1.2.6.14.3 Installing the Battery Temperature Sensor
4.1.2.6.15 Sealing Cable Apertures
4.1.2.6.15.1 Sealing Apertures for Power Cables and Ground Cables
4.1.2.6.15.2 Sealing Apertures for Optical Fibers
4.1.2.7 Checking the Installation
4.1.2.7.1 Checking the Cabinet Installation
4.1.2.7.2 Cable Connections Inside the Cabinet
4.1.2.7.3 Checking the Installation of Terminal, Alarm box, and NMS
4.1.2.7.4 Checking the Power and the Grounding
4.1.2.7.5 Checking the Installation Environment
4.1.2.7.6 Checking the Equipment Room
4.1.2.7.7 Checking the Connectivity of the Cables
4.1.2.8 Powering On the System
4.1.2.8.1 Power-On Process
4.1.2.8.2 Powering On the surge protector
4.1.2.8.3 Power On the AC Power Module
4.1.2.8.4 Powering On the PDU
4.1.2.8.5 Powering On the Service Shelf
4.1.2.8.6 Powering On the Battery
4.1.2.8.7 Powering Off the Device
4.1.2.8.7.1 AC-Powered ONU-F02A in Integrated Configuration
4.1.2.8.7.2 AC-Powered ONU-F02A in Distributed Configuration/AC-Powered N66E-18 Configuration
4.1.2.8.7.3 DC-Powered ONU-F02A/N66E-18 Configuration
Drilling Tools
Table 2 lists the drilling tools to be arranged before the installation.
Fastening Tools
Table 3 lists the fastening tools to be arranged before the installation.
Table 3 Fastening tools to be arranged before the installation
Name Description Illustration
Pliers
Table 4 lists the pliers to be arranged before the installation.
Auxiliary Tools
Table 5 lists the auxiliary tools to be arranged before the installation.
Special Tools
Table 6 lists the special tools to be arranged before the installation.
Meters
Table 7 lists the meters to be arranged before the installation.
z Fill in the Checklist of the Construction Environment according to the actual conditions.
z Sign the Kickoff Agreement with the customer if all the items are available, and then draft the Project
Installation Plan.
z If requirements are not met, fill in the Onsite Work Liaison Form and specify the reason for postponing
the kickoff.
z Sign a memo for any engineering project that cannot be rectified or that does not meet the requirements
even after it is rectified.
1 Site selection Keep a equipment room away from inflammable materials, explosive materials,
electromagnetic interference such as large radar station, launching tower, and
transformer substation (at least 100 m away). Do not build a telecommunications
room near a pool or a chemical plant.
2 Inside a z All cable apertures are sealed securely.
telecommunications z No people lives in the telecommunications room.
room
z The telecommunications room is free from piled sundries, rats, or water
leakage.
3 Air conditioner If the temperature in the equipment room is higher than 35°C, install an air
conditioner (which can be restarted after power-off). Make sure that the air from
the air conditioner is not directed towards the device.
4 Weight bearing Before installing the cabinet, check the weight bearing capacity of the installation
capacity site according to the device layout of the installation site. If the bearing capacity
does not meet the requirement, prepare the installation site to bear the device
weight. Consult a professional construction company and find a solution for
strengthening the installation site. The strengthening process must be completed by
a professional construction team.
5 Moisture-proof If the relative humidity is greater than 70%, install the dehumidifying device, such
measures as air conditioner with dehumidification function or special dehumidifier. Ensure
that the equipment room is protected from moisture and water seepage.
6 Heating measures If the average temperature is lower than 5°C for 90 or more days in a year, install
the heating system. If the average temperature is lower than 5°C for 60 or more
days but less than 90 days, Huawei recommends that you install the heating
system.
7 Dust-proof For the equipment room near the dust source, such as the coal mine, rural highway,
measures and farmland, seal the window properly, and use an anti-theft and fireproof door.
Place a partition board between the device and the door of the room.
8 Lightning proof The equipment room is installed with the surge protection devices, such as
measures lightning proof rod or lightning proof strip. The surge protection ground and the
protection ground of the room share one grounding body.
9 Grounding The device working ground, the protection ground and the surge protection ground
resistance in the equipment room should share one grounding body. The communication
device and power supply in the equipment room should share one ground bar, if
possible. The grounding resistance of the grounding system should be less than 10
ohms.
10 Grounding Connect the ground bar properly to the grounding network. The distance between
connecting cable the ground bar and the grounding network should not be more than 30 m. Use 40 x
4 mm2 or above galvanized flat steel to connect them; or use a cable with a cross-
sectional area of more than 95 mm2 to connect them. Take insulation and anti-
corrosive measures for the galvanized flat steel and the cable. The galvanized flat
steel and the cable should not have a breaking-point on them. Take mechnical
protection measures for the unearthed part.
11 AC power supply Prepare the AC power supply before the construction. The AC voltage for the
equipment room is in the range of 90 V to 290 V (rated voltage: 220 V) or 88 V to
155 V (rated voltage: 110 V). Install the AC distribution switch and AC power
cable properly. When the power is off or faulty, an alarm shall be reported. To
ensure the normal running of the maintenance terminal, the UPS is recommended
in the equipment room.
12 AC grounding Do not connect the neutral line of the power cable to the protection ground of the
communication devices.
13 AC lightning proof Install a surge protector with a nominal discharging current not less than 20 kA.
measures Ground the surge protector reliably.
14 DC voltage and z The DC voltage in the equipment room is in the range of -38.4 V to -57.6 V
battery (rated voltage: -48 V) or -48 V to -72 V (rated voltage: -60 V).
z The battery meets the power supply requirements on the device. Arrange the -48
V power cable near the DC power distribution unit.
15 DC grounding The central offices where the device locates should adopt joint grounding. That is,
the working ground and the protection ground of the device, and lightning
grounding of the building should be connected together.
Connect the working ground in the DC power distribution cabinet to the protection
ground in the equipment room. The cross-sectional area of the cable should not be
less than 95 mm2.
16 Subscriber cable Ground the metallic jackets of all external subscriber cables at the MDF or connect
them to the protection ground bar.
17 Trunk cable Do not place the trunk cable outside the equipment room. If you require to place
the trunk cable outside the equipment room, use the double-layer shielded cable or
the cable with a metallic jacket, and connect the external shield layer or the
metallic jacket of the cable properly to the protection ground bar.
18 MDF The terminal capacity of the main distribution frame (MDF) meets the
requirements. Install the MDF before the construction. Consider the capacity of the
MDF according to the project capacity and future planning.
Install a protective unit for each pair of subscriber lines in the MDF. Connect the
grounding end of the protective unit and the busbar of the MDF properly. The
cross-sectional area of the ground cable should not be less than 16 mm2. The
ground cable is connected properly to the indoor ground bar. The busbar of the
MDF is connected properly to the protection-ground bar to avoid oxide corrosion.
If the MDF is located near the remote module, connect them to the same ground
bar.
19 DDF The digital distribution frame (DDF) is installed, and its terminal capacity meets
the requirements. The cross-sectional area of the ground cable should not be less
than 6 mm2. The ground cable is connected properly to the indoor ground bar. The
busbar of the DDF is connected properly to the protection-ground bar to avoid
oxide corrosion.
20 ODF The installation of external optical fiber is complete. The optical distribution frame
(ODF) or the fiber distribution box is installed. The fibers are welded.
21 Transmission unit Route the optical cables and weld the patch cords before the construction. If there
are too many optical fibers, install the ODF, and jumper the patch cords on the
ODF. Use the fiber splicing box for the remote office if the number of optical
fibers is less, and weld the optical fibers. Install and commission the transmission
unit to ensure that it operates in the normal state. The transmission unit is installed
in compliance with the international regulations.
22 Transportation The transportation passage, such as lift and corridor, is large enough to carry the
passage cabinet.
23 Fire protection z Configure the fire retardant cover for the reserved holes on the equipment floor,
and ensure that the holes can be sealed for insulation. If cable routing is
required, fill the holes with fire-protection mud.
z Adopt fire retardant materials for the new decoration in the equipment room.
For example, adopt fire retardant materials for insulation when the equipment
room is in the buildings or stores.
z Process fire protection by using PVC fire retardant tape, and fill the apertures
for cables with fire-protection mud.
z The fire-fighting equipment is available in the equipment room, such as the fire
extinguisher.
NOTE:
z If the package is defective, stop unpacking and report the condition of the package to the local Huawei representative. If the
quantity of the product is correct and the product is in good condition, unpack and accept the product.
z To identify the front, rear, left, and right sides of the device, read the instructions on the packing case.
Procedure
1. Read the carton label to obtain the information about the number and the type of the board in the
carton.
2. Cut the straps by using the diagonal pliers.
3. Cut the pressure-sensitive adhesive tapes along the seams of the carton cover by using a knife.
4. Open the carton and take out the foam plates.
5. Cross-check the contents of the box of the board. Ensure that the number of the boards listed on the
labels of the board box is consistent with the number listed on the labels of the carton, and then take
out the board box. Figure 1 shows how to unpack the carton.
Figure 1 Unpacking the carton
Precautions
NOTICE:
Electronic components are sensitive to the ESD. When handling the board, wear the ESD gloves or the
ESD wrist strap that is grounded properly and hold only the edge of the board.
NOTE:
The desiccant in the ESD bag is used for absorbing moisture inside the bag.
Procedure
1. Check whether the board package is damaged. If the board packet is damaged, stop unpacking and
report the condition to the local representative office. If the board package is in good condition,
proceed as follows.
2. Wear the ESD gloves or the ESD wrist strap and connect its ground end to the ESD jack on the
cabinet.
3. Unpack each package and check for damages. Figure 1 shows how to unpack the board.
Figure 1 Unpacking the board
If... Then...
5. Place all the materials on the antistatic surface to discharge the static electricity, and then install the
board.
6. Use the original package materials for packing the board. Keep them in a dry and cool place, away
from sunlight and strong electromagnetic radiation sources.
Procedure
1. Check the product type and quantity according to the Packing List. Sign the document on site.
2. Check each product according to the Packing List. If there is a mismatch in the number of packages, or
if the cargo is damaged, or if the consignment is wrong, sign the Unpacking Memo. The project
supervisor should also fill in the Cargo Inspection Feedback Form and report the problem to the local
representative office within three days.
3. Store the unpacked product in a room if the product does not match the contents of the Packing List.
Take photographs of the storage site, the rusty or corroded product, and the case or package material.
Archive the photographs and store the empty case and materials.
4. Unpack other packages after confirming the contents of one package.
5. The project supervisor and the customer must sign the Packing List.
Installation Process
Before installing the cabinet, you should be familiar with the process of installing the cabinet on a concrete
floor. Install the cabinet according to the installation process.
Recommended Tools
To facilitate the installation, arrange for the required installation tools.
Drilling Holes
Drill holes before installing the expansion bolts.
Attaching Cabinets
When installing multiple cabinets, you need to connect the equipotential subtending cables on both sides of
each cabinet and connect the connecting plates at the top of the cabinet to fasten the cabinets.
1. Recommended Tools
This topic lists the recommended tools for installing the cabinet on a concrete floor.
2. Checking Before the Installation
This topic describes how to check the installation space required for installing the cabinet and how to
check the cabinet and the accessories.
3. Marking Reference Lines
This topic describes how to mark reference lines for installing the cabinet. You can mark reference
lines based on the construction plan drawing or marking-off plate.
4. Drilling Holes
After installing the expansion bolts, place the cabinet onto the expansion bolt holes, and then pre-
fasten the expansion bolts.
7. Leveling the Cabinet
Use the leveling foot to level the cabinet according to the position of the bubble in the spirit level.
8. Fastening the Cabinet
After leveling the cabinet, fasten the expansion bolts at the bottom of the cabinet to fasten the cabinet.
9. Testing the Resistance
When multiple cabinets are installed, you need to connect the equipotential subtending cables on both
sides each cabinet and the connecting plates at the top of the cabinet.
11. Recovering the Cabinet
This topic describes how to recover the cabinet after the installation.
z hammer drill
z Multimeter
z Claw hammer
z Rubber hammer
z Flathead screwdrivers: M3-M6
z Phillips screwdrivers: M3-M6
z Adjustable wrench
z Socket wrenches: M6, M8, M12, M14, M17 and M19
z Steel tape
z marker
z Powder marker
z Tape measure
z Spirit level
z Angle square
z Vacuum cleaner
z Ladder
Test and adjust the meters and special tools before using them.
Precautions
Pay attention to the following points when installing the cabinet:
z Lock the cabinet door before carrying the cabinet to protect the components and cables.
z Ensure that the cabinet is powered off before the installation.
z During the installation, take measures to protect the cabinet surface from being scratched. If the cabinet
surface is scratched, paint it.
z Check the cabinet completely after the installation, and rectify the faults in time.
z After installing the cabinet, clean the cabinet if it is dirty
z You can change the installation methods according to the actual situation based on this guide.
Procedure
1. Check the space in and around the cabinet.
z Reserve a space of 8 U (1 U = 44.45 mm) vertically at the bottom of the cabinet for installing the
expansion bolts. If the space is insufficient, remove certain parts from the lower part of the cabinet.
For how to install and remove the parts, see "Installing and Removing the Subrack."
z Reserve sufficient space around the cabinet for maintenance, ventilation, and heat dissipation. For
more information about the space to be reserved, see "Marking Reference Lines."
Context
You can mark reference lines based on the construction plan drawing or the marking-off plate.
Ensure that the reference lines are marked correctly before the installation. Otherwise, mark the reference
lines again.
Figure 2 shows the construction plan drawing for installing cabinets side by side.
Figure 2 Construction plan drawing for installing cabinets side by side on a concrete floor
Procedure
1. Mark several points by using the measuring tape. Draw two lines parallel to the wall based on the
marked points, and reserve a space of 487 mm between the two lines.
2. Mark the position of the first expansion bolt.
3. Mark the positions of the other three expansion bolts based on the position of the first expansion bolt.
4. To install a row of cabinets, refer to the marked hole positions and mark the positions of the holes for
other cabinets one by one.
5. Measure all the lines and check the position of the holes again. Ensure that the dimensions of the holes
are correct.
Marking-off Plate
Figure 1 shows the marking-off plate.
Figure 1 Marking-off plate for a concrete floor
NOTE:
Reserve sufficient space around the cabinet for maintenance, ventilation, and heat dissipation. For more information about the
space to be reserved, see "Marking Reference Lines Based on the Construction Plan Drawing."
Procedure
1. Place the marking-off plate on the floor based on the layout of the cabinet. The semi-circle notch on
the marking-off plate identifies the front direction of the cabinet.
2. Mark holes for all the expansion bolts based on the marking-off plate, that is, four holes for each
cabinet.
Precautions
Pay attention to the following when you drill the holes:
z Use a punch tool to chisel a hole so that you can position the drill bit if the floor is very hard or slippery.
z Hold the drill firmly and ensure that the drill bit is vertical to the floor. The drill should be steady when
you drill holes to avoid uneven or slanting holes.
z Ensure that all the holes are of equal depth.
Procedure
1. Select a Ф16 drill bit.
2. Drill a hole by using a hammer drill on the marked position of the expansion bolt, as shown in Figure 1.
The depth of the hole must be equal to the length of the expansion tube plus the length of the
expansion nut, and the depth of the hole should range from 52 mm to 60 mm.
Figure 1 Drilling a hole
Structure
Figure 1 shows the components of an expansion bolt.
Figure 1 Components of an expansion bolt
Precautions
z Insert the guide rib into the guide trough beforehand. Otherwise, the expansion bolt cannot be fastened.
z Ensure that the expansion tube is completely inserted into the concrete pedestal. The length of the
expansion tube should not exceed the depth of the floor. Otherwise, the installation of the cabinet is
affected.
Procedure
1. Insert the expansion bolt into the hole.
2. Do not fasten the spring washer, flat washer and nut on the expansion bolt very tightly.
3. Knock the expansion bolt by using a rubber hammer or a claw hammer until the expansion tube is
completely inserted into the expansion hole, as shown in Figure 2.
Figure 2 Installing an expansion bolt
4. Fasten the expansion bolt clockwise by using a spanner to expand the tube.
5. Remove the spring washer, flat washer, and nut by turning them anticlockwise, as shown in Figure 3.
Figure 3 Removing the spring washer, flat washer, and nut
Parent topic: Installing the Cabinet on a Concrete Floor
Precautions
Pay attention to the following points when placing the cabinet:
z There are two insulating plates between the cabinet and the floor. The expansion bolt has an insulating
tube. Install the insulating parts correctly during construction so that the entire device is not connected
to the ground before the ground cables are installed.
z If it is easy to fasten the expansion bolts at the bottom of the cabinet, there is no need to remove the
front door, the rear door, and the ground cable between the front door and the cabinet.
z If the cabinets are not combined, there is no need to remove the side cover and the ground cable of the
cabinet.
z Fine fasten the bolts in turn in a diagonal sequence to reduce the stress between the bolt and the cabinet.
Procedure
1. Remove the ground cable between the door and the cabinet, as shown in Figure 1.
Figure 1 Removing the ground cable
2. Remove the front and rear doors of the cabinet, as shown in Figure 2.
Figure 2 Removing the rear door of the cabinet
3. Remove the air filter at the bottom of the cabinet, as shown in Figure 3.
Figure 3 Removing the air filter
4. Place the insulating plates on the floor, two for each cabinet.
5. Place the cabinet on the marked position to align the installation holes of the cabinet with the holes for
the expansion bolts on the ground, and then fasten the expansion bolts halfway into the holes, as
shown in Figure 4.
Figure 4 Placing the cabinet
Procedure
1. Place a spirit level on the cabinet in a mutually vertical direction to check whether the cabinets are
leveled.
2. If the cabinet is not leveled, adjust the corresponding leveling foot to level the cabinet, as shown in
Figure 1.
Procedure
1. Place the spring washer, flat washer, and insulting washer on the bolt M12 x 65.
2. Fasten the bolt in a diagonal sequence with a torque of 45 N•m, as shown in Figure 1.
Figure 1 Fastening the cabinet
NOTE:
Fasten the bolts one by one in a diagonal sequence to reduce the stress between the bolt and the cabinet.
Insulation Requirement
The resistance between the cabinet and the ground should be greater than five megohms.
Procedure
1. Set the multimeter to the megohm level to measure the resistance between the expansion bolt M12 x
65 and the ground bolt, as shown in Figure 1.
Figure 1 Testing the resistance
If... Then...
The measured resistance value is more than or equal to five megohms The installation is completed
The measured resistance value is less than five megohms Go to 3
3. Remove all installation components, and check whether the insulating parts are missing or whether the
insulating parts are damaged.
4. Fasten the cabinet and test the resistance again.
Context
NOTICE:
To attach multiple cabinets, proceed with this topic. Otherwise, skip this topic.
Before proceeding this step, ensure that the cabinets to be attached are installed.
z If multiple cabinets are attached, remove the ground cable between the side cover and the cabinet when
removing the ground cable between the front door and the cabinet.
z If multiple cabinets are attached, mark reference lines, install, fasten, and attach the cabinets based on
one cabinet.
Procedure
1. Remove the side cover of the cabinet, as shown in Figure 1.
Figure 1 Removing the side cover of the cabinet
2. Connect the equipotential ground cables between adjacent cabinets, as shown in Figure 2.
Figure 2 Connecting the equipotential ground cables
3. Fasten the top of the cabinet, as shown in Figure 3.
Figure 3 Fastening the top of the cabinet
Procedure
1. Install the front door and the rear door of the cabinet, as shown in Figure 1.
Figure 1 Installing the front door and the rear door of the cabinet
2. Connect the ground cables between the front door and the cabinet, as shown in Figure 2.
Figure 2 Connecting the ground cables between the front door and the cabinet
3. Install the air filter at the bottom of the cabinet, as shown in Figure 3.
Figure 3 Installing the air filter
Installation Process
Before installing the cabinet, you should be familiar with the process of installing the cabinet on an ESD
floor. Install the cabinet according to the installation process.
Recommended Tools
To facilitate the installation, arrange for the required installation tools.
Drilling Holes
Drill holes before installing the expansion bolts.
Attaching Cabinets
When installing multiple cabinets, you need to connect the equipotential subtending cables on both sides of
each cabinet and connect the connecting plates at the top of the cabinet to fasten the cabinets.
This topic lists the recommended tools for installing the cabinet on an ESD floor.
2. Checking Before the Installation
This topic describes how to check the installation space required for installing the cabinet and how to
check the cabinet and the accessories.
3. Marking Reference Lines
This topic describes how to mark reference lines for installing the cabinet. You can mark reference
lines based on the construction plan drawing or marking-off plate.
4. Drilling Holes
After installing the expansion bolts, place the cabinet onto the expansion bolt holes, and then pre-
fasten the expansion bolts.
8. Leveling the Cabinet
Use the leveling foot to level the cabinet according to the position of the bubble in the spirit level.
9. Fastening the Cabinet
After leveling the cabinet, fasten the expansion bolts at the bottom of the cabinet to fasten the cabinet.
10. Testing the Resistance
When multiple cabinets are installed, you need to connect the equipotential subtending cables on both
sides each cabinet and the connecting plates at the top of the cabinet.
12. Recovering the Cabinet
This section describes how to recover the cabinet after the installation.
13. Recovering the ESD floor
z hammer drill
z Multimeter
z Claw hammer
z Rubber hammer
z Flathead screwdrivers: M3-M6
z Phillips screwdrivers: M3-M6
z Adjustable wrench
z Socket wrenches: M6, M8, M12, M14, M17 and M19
z Steel tape
z marker
z Powder marker
z Tape measure
z Spirit level
z Angle square
z Vacuum cleaner
z Ladder
Test and adjust the meters and special tools before using them.
Precautions
Pay attention to the following points when installing the cabinet:
z Lock the cabinet door before carrying the cabinet to protect the components and cables.
z Ensure that the cabinet is powered off before the installation.
z During the installation, take measures to protect the cabinet surface from being scratched. If the cabinet
surface is scratched, paint it.
z Check the cabinet completely after the installation, and rectify the faults in time.
z After installing the cabinet, clean the cabinet if it is dirty
z You can change the installation methods according to the actual situation based on this guide.
Procedure
1. Check the space in and around the cabinet.
z Reserve a space of 8 U (1 U = 44.45 mm) vertically at the bottom of the cabinet for installing the
expansion bolts. If the space is insufficient, remove certain parts from the lower part of the cabinet.
For how to install and remove the parts, see "Installing and Removing the Subrack."
z Reserve sufficient space around the cabinet for maintenance, ventilation, and heat dissipation. For
more information about the space to be reserved, see "Marking Reference Lines."
Context
You can mark reference lines based on the construction plan drawing or the marking-off plate.
Ensure that the reference lines are marked correctly before the installation.
Figure 2 shows the construction plan drawing for installing cabinets side by side.
Figure 2 Construction plan drawing for installing cabinets side by side on an ESD floor
Procedure
1. Mark several points by using the measuring tape. Draw two lines parallel to the wall based on the
marked points, and reserve a space of 504 mm between the two lines.
2. Mark the position of the first expansion bolt.
3. Mark the positions of the other three expansion bolts based on the position of the first expansion bolt.
4. To install a row of cabinets, refer to the marked hole positions and mark the positions of the holes for
other cabinets one by one.
5. Measure all the lines and check the position of the holes again. Ensure that the dimensions of the holes
are correct.
Marking-off Plate
Figure 1 shows the marking-off plate.
Figure 1 Marking-off plate of the cabinet when a support is installed
NOTE:
Reserve sufficient space around the cabinet for maintenance, ventilation, and heat dissipation. For more information about the
space to be reserved, see "Marking Reference Lines Based on the Construction Plan Drawing."
Procedure
1. Place the marking-off plate on the floor based on the layout of the cabinet. The semi-circle notch on
the marking-off plate identifies the front direction of the cabinet.
2. Mark holes for all the expansion bolts based on the marking-off plate, that is, four holes for each
cabinet.
Precautions
Pay attention to the following when you drill the holes:
z Use a punch tool to chisel a hole so that you can position the drill bit if the floor is very hard or slippery.
z Hold the drill firmly and ensure that the drill bit is vertical to the floor. The drill should be steady when
you drill holes to avoid uneven or slanting holes.
z Ensure that all the holes are of equal depth.
Procedure
1. Select a Ф16 drill bit.
2. Drill a hole by using a hammer drill on the marked position of the expansion bolt, as shown in Figure 1.
The depth of the hole must be equal to the length of the expansion tube plus the length of the
expansion nut, and the depth of the hole should range from 52 mm to 60 mm.
Figure 1 Drilling a hole
Structure
Figure 1 shows the components of an expansion bolt.
Figure 1 Components of an expansion bolt
Precautions
z Insert the guide rib into the guide trough beforehand. Otherwise, the expansion bolt cannot be fastened.
z Ensure that the expansion tube is completely inserted into the concrete pedestal. The length of the
expansion tube should not exceed the depth of the floor. Otherwise, the installation of the cabinet is
affected.
Procedure
1. Insert the expansion bolt into the hole.
2. Do not fasten the spring washer, flat washer and nut on the expansion bolt very tightly.
3. Knock the expansion bolt by using a rubber hammer or a claw hammer until the expansion tube is
completely inserted into the expansion hole, as shown in Figure 2.
Figure 2 Installing an expansion bolt
4. Fasten the expansion bolt clockwise by using a spanner to expand the tube.
5. Remove the spring washer, flat washer, and nut by turning them anticlockwise, as shown in Figure 3.
Figure 3 Removing the spring washer, flat washer, and nut
Parent topic: Installing the Cabinet on an ESD floor
Installation Process
Figure 1 shows the process of installing the support.
Figure 1 Process of installing the support
Procedure
1. Adjust the height of the support.
a. Adjust the height of the support so that it is the same as the height of an ESD floor.
b. Fasten the height-locking bolt with a torque of 45 N•m. Fasten the height-locking bolts in the
middle, and then fasten the bolts on the two sides of each support, as shown in Figure 2.
Figure 2 Outline of the support
a. Assemble the supports and guide rails together by using the bolt M12 x 30, spring washer, and flat
washer, as shown in Figure 3.
Figure 3 Assembling the support and guide rail together
b. Align the position of the support and ensure that the diagonals (as shown in Figure 3) of the guide
rails are equal.
c. Fasten the bolts, but ensure that you do not fasten the bolts completely before the support is
leveled.
a. Align the installation holes in the support with the expansion bolt holes in the ground, and install
the expansion bolt.
b. Adjust the support location and check the level of the support by using the spirit level.
Procedure
1. Adjust the height of each support and install the guide rails.
2. Adjust the relative positions between supports, align the front of each support in a line, and then adjust
the space between adjacent supports to fit an insulating plate.
3. Fasten the support. The positions of a row of supports are shown in Figure 1.
Figure 1 Positions of a row of supports
Precautions
Pay attention to the following points when placing the cabinet:
z There are two insulating plates between the cabinet and the support. The expansion bolt has an
insulating tube. Install the insulating parts correctly when placing the cabinet so that the entire device
does not touch the ground before the ground cables are connected.
z If it is easy to fasten the expansion bolts at the bottom of the cabinet, do not remove the front door, rear
door, and ground cable between the front door and the cabinet.
z If the cabinets are not attached, there is no need to remove the side cover and the ground cable of the
cabinet.
z Fasten the bolts one at a time in a diagonal sequence to reduce the stress between the bolt and the
cabinet.
Procedure
1. Remove the ground cable between the door and the cabinet, as shown in Figure 1.
Figure 1 Removing the ground cable
2. Remove the front door and the rear door of the cabinet, as shown in Figure 2.
Figure 2 Removing the door of the cabinet
3. Remove the air filter at the bottom of the cabinet, as shown in Figure 3.
Figure 3 Removing the air filter
4. Place the insulating plates on the support. There should be two insulating plates for each cabinet.
5. Place the cabinet on the marked position to align the installation holes of the cabinet with the holes on
the support, and then fasten the bolts halfway into the holes, as shown in Figure 4.
NOTE:
For the bolts holes of different cabinets, see Figure 1 in "Marking Reference Lines Based on the Marking-off Plate."
Procedure
1. Place a spirit level between the combined cabinets to check whether the cabinets are leveled.
2. If the cabinet is not leveled, adjust the corresponding leveling foot to level the cabinet, as shown in
Figure 1.
Procedure
1. Place the spring washer, flat washer, and insulting washer on the bolt M12 x 65.
2. Fasten the bolt in a diagonal sequence with a torque of 45 N•m, as shown in Figure 1.
Figure 1 Fastening the cabinet
NOTE:
Fasten the bolts one by one in a diagonal sequence to reduce the stress between the bolt and the cabinet.
Insulation Requirement
The resistance between the cabinet and the ground should be more than or equal to five megohms.
Procedure
1. Set the multimeter to the megohm level to measure the resistance between the expansion bolt M12 x
65 and the ground bolt, as shown in Figure 1.
Figure 1 Testing the resistance
2. Read the measured resistance value.
If... Then...
The measured resistance value is larger than or equal to five megohms The installation is completed
The measured resistance value is smaller than five megohms Go to 3
3. Remove all installation components, and check whether the insulating parts are missing or whether the
insulating parts are damaged.
4. Fasten the cabinet and test the resistance again.
Context
NOTICE:
To attach multiple cabinets, proceed with this topic. Otherwise, skip this topic.
Before proceeding this step, ensure that the cabinets to be attached are installed.
z If multiple cabinets are attached, remove the ground cable between the side cover and the cabinet when
removing the ground cable between the front door and the cabinet.
z If multiple cabinets are attached, mark reference lines, install, fasten, and attach the cabinets based on
one cabinet.
Procedure
1. Remove the side cover of the cabinet, as shown in Figure 1.
Figure 1 Removing the side cover of the cabinet
2. Connect the equipotential ground cables between adjacent cabinets, as shown in Figure 2.
Figure 2 Connecting the equipotential ground cables
Procedure
1. Install the front door and the rear door of the cabinet, as shown in Figure 1.
Figure 1 Installing the front door and the rear door of the cabinet
2. Connect the ground cable between the front door and the cabinet, as shown in Figure 2.
Figure 2 Connecting the ground cable between the front door and the cabinet
3. Install the air filter at the bottom of the cabinet, as shown in Figure 3.
Figure 3 Installing the air filter
Process
Figure 1 shows the process of recovering the ESD floor.
Figure 1 Process of recovering the ESD floor
1. Installing the floor holder
Procedure
1. Install the floor holder. Fasten the floor holder to the support by using the bolt M12 x 30, spring
washer and flat washer, as shown in Figure 2.
Figure 2 Installing the floor holder
2. Adjust the height of the holder to align the top surface of the holder with the bottom surface of the
ESD floor.
3. Cut and recover the floor. According to the conditions around the cabinet, cut the floor to a proper size
and lay the floor around the cabinet, as shown in Figure 3.
Figure 3 Recovered ESD floor
Parent topic: Installing the Cabinet on an ESD floor
Installation Preparations
This topic describes the materials to be prepared for installing the surge protector.
Installation Procedure
This topic describes how to install the surge protector.
z In case of 110 VAC power supply, use an SPD32SZ surge protector for single-phase 110 VAC power.
z In case of 220 VAC power supply, use an SPD28SZ surge protector for single-phase 220 VAC power.
z Two M6 screws
z AC power cables and ground cable from the power supply to the surge protector (These two types of
cables must have a cross-sectional area of at least 4 mm2, and their lengths are determined by the
distance between the cabinet and the surge protector.)
Precautions
NOTE:
z Ensure no dangerous voltage exists on the lines when installing the surge protector.
z attch labels to the switches that are allowed to be used.
Procedure
1. Select a position 5 m to 10 m away from the cabinet for installing the surge protector. In general, you
can fasten the surge protector to the wall. No obstacle should be around the surge protector.
2. Use screws to fasten the surge protector to the wall through the four holes on the surge protector.
3. Open the front panel of the surge protector. Connect the AC power cable and ground cable based on
the wire connection diagram on the internal side of the surge protector. Table 1 describes the meanings
of terminals in the surge protector.
Lin Live line input terminal of the AC power Live line of the AC power supply
supply
Nin Neutral line input terminal of the AC power Neutral line of the AC power supply
supply
PE Grounding terminal Ground cable
4. Ensure that all connections comply with the connection diagram on the panel of the surge protector.
5. Measure the grounding resistance of the surge protector and confirm that it is 10 ohms at most.
External Connections
This topic describes the external connections from the ONU-F02A cabinet to the telecommunications
room.
External Connections
This topic describes the external connections from the N66E-18 cabinet to the telecommunications room.
Installing OT Terminals
Abide by the following rules when installing two or more OT terminals on one stud, as shown in Figure 1.
z Do not overlap the OT terminals. If there are two or more OT terminals to be installed on one stud,
maintain a 45 degree angle between the two OT terminals.
z Place the larger OT terminal under the smaller OT terminal.
z To prevent the cable cores from being damaged, do not apply too much force when bending the cables
at the turning, especially to the trunk cables and the optical fibers.
z The bending radius of the cable should be more than twice the size of the cable diameter. The bending
radius near the connector is four to six times the cable diameter.
z The bending radius of the optical fiber should be more than 20 times the cable diameter. In general, the
bending radius of the optical fiber is greater than or equal to 40 mm.
Bundling Cables
Abide by the following rules when bundling the cables:
z Bundle the cables on both sides of the bending radius by using cable ties, as shown in Figure 2.
Figure 2 Bundling the cables at the bending radius
z Bundle the cables evenly with equal space between cable ties. Space two adjacent ties 250 mm at most
(the subscriber cables should be bundled every 200 mm). When the cables are bundled outside the
cabinet, the space between the cable ties is subject to the space between the beams (if the beams are not
available, the space between the cable ties must be 250 mm at most).
z Bundle the cable with the cable ties properly. Do not bundle the cables, especially the optical fibers,
very tightly.
z Arrange all cable ties in the same direction. The cable ties should not have any sharp points at the ends.
z Coil the extra optical fibers and cables neatly.
z Fix the protective caps on the optical fiber connectors that are not currently used.
z Ensure that the cable connectors made on site meet the requirements, and are firm, reliable, and neat.
z Arrange the bundled cables close to each other, without crossing or twisting them.
z You may not bundle the cables when the cables pass the side of the subrack, but ensure that the cables
are arranged neatly without crossing or twisting them.
Arranging Cables
Abide by the following rules when arranging the cables:
z Place the cables in a proper order and keep the sheath intact.
z Do not apply too much force when bundling the cables.
z Route different types of cables separately.
z Route the cables according to the construction plan drawing, such as the specifications, path, cross-
sectional area, and position.
z Take future maintenance and capacity expansion into account when arranging the cables and the ports.
z Bundle every eight cables together. When less than eight cables are reserved, bundle them together.
Arrange the cables hierarchically. The adjacent binders should be interconnected to ensure that all
cables are arranged together after routing.
Routing Cables
Cables can be routed in the overhead cabling or underfloor cabling.
Abide by the following rules when routing the cables in the overhead cabling:
z All cables are laid on the cable tray over the cabinet.
z If the distance between the cable tray and the holes at the top of the cabinet is less than or equal to 0.8
m, route the cables directly through the holes. If the distance between the cable tray and the holes is
more than 0.8 m, you need a climbing ladder to hold the cables to protect the cables from being
damaged.
z If the cable ladder is used, the cables should be led through the cable ladder, as shown in Figure 3.
Figure 3 Leading the cables through the cable ladder
z If the cable trough is used, the cables should be lead downwards from the side of the cable trough, as
shown in Figure 4.
Figure 4 Leading the cables downwards from the side of the cable trough
Abide by the following rules when routing the cables in the underfloor cabling:
z All the cables are placed under an ESD floor or routed along the cable trough.
z When the cables are placed under an ESD floor, the height of cable bundles should not exceed three-
fourth of the net height under an ESD floor.
Figure 2 shows the external connections of the ONU-F02A cabinet in the underfloor cabling mode.
Figure 2 External connections of the ONU-F02A cabinet in the underfloor cabling mode
NOTE:
The working ground and the protection ground in the telecommunications room share one grounding body.
NOTE:
The working ground and the protection ground of the telecommunications room share one grounding body.
NOTE:
Perform the connectivity test for the cables to be routed to ensure that the cables are normal.
This topic provides the outline of battery connecting cables, and describes the connection preparations
and the connection procedures of battery connecting cables.
2. Routing External Power Cables and Ground Cables
This topic provides the appearance of external power cables and ground cables, and describes the
connection preparations, the overhead and the underfloor connection procedures of power cables and
ground cables.
3. Routing Subscriber Cables
This topic provides the outline of subscriber cables, and describes the connection preparations and the
connection procedures of subscriber cables.
4. Routing Trunk Cables and Network Cables
This topic provides the appearance of trunk cables and network cables, and describes the connection
preparations and the connection procedures of trunk cables and network cables.
5. Routing Optical Fibers
This topic provides the appearance of optical fibers, and describes the connection preparations and the
connection procedures of optical fibers.
6. Sealing Cable Apertures
Table 1 and Table 2 describe the ports on the backplane of the HABA shelf.
Table 1 Ports on the backplane of the HABA shelf
Marks in Figure 1 Mapping Transfer Mapping Board Meaning
Board
J7 - - (Reserved)
J8 - - (Reserved)
J10 - - (Reserved)
Context
NOTE:
Check whether to remove the side cover of the cabinet according to actual conditions, such as the flexibility of routing external
cables.
Procedure
1. Remove the eight M6 x 12 screws by using the Phillips screwdriver, as shown in Figure 1.
Figure 1 Removing the screws on the side cover of the cabinet
2. Remove the side cover, and put the eight screws away.
3. Repeat 1 and 2 to remove the other side cover, as shown in Figure 2.
Figure 2 Removing the screws on the other side cover of the cabinet
Parent topic: Routing External Cables
Preparations
Before routing the external power cables, check the cable connections and ensure that the necessary
precautions are complied with.
4.1.2.6.7.1 Preparations
Before routing the external power cables, check the cable connections and ensure that the necessary
precautions are complied with.
Precautions
Pay attention to the following when routing the power cables and the ground cable:
z The ground resistance of the ground bar in the telecommunications room must be smaller than or equal
to 10 ohms.
z The protection ground and the working ground in the telecommunications room must be jointly
grounded.
z The power cables and the ground cable must be bound separately. Do not bundle them with other
cables.
z The cross-sectional area of the ground cable must be greater than or equal to 25 mm². Keep the cable
short without interweaving.
Table 1 Mapping between the input cables and the input terminals on the EPS75-4815AF power
system
Cable Type Color One End Connects The Other End Connects to...
to...
Cable L Black Output terminal "L" Terminal "AC-L" of the power system
of the surge
protector
Cable N White Output terminal Terminal "AC-N" of the power system
"N" of the surge
protector
PGND Yellow Ground bar in the Terminal " " at the top of the cabinet
and telecommunications
green room
Table 2 Mapping between the input cables and the input terminals on the PDU
Power Input Input Terminal -48 VDC Polarity Color
NOTE:
z NEG1(-) and NEG2(-) in Table 2 are connected internally, and so are RTN1(+) and RTN2(+).
z When inputs are connected, choose any input terminal.
z On the loaded cabinet side, the label marked with "A01/B08--48 V2" indicates that the cable is for -48
V2 DC supply. It comes from the 8th terminal on -48 V wiring bar of row B in the power distribution
cabinet of row A and column 01.
z On the power distribution cabinet side, the label marked with "B03--48V2" indicates that the cable is
for -48 V2 DC supply. It comes from the loaded cabinet of row B and column 03.
Procedure
1. Route the AC power cables and the ground cable into the cabinet through the aperture shown in Figure
1.
Figure 1 Routing the AC power cables and the ground cable into the cabinet
2. Route the yellow and green ground cable (from the surge protector to the cabinet side) from the
aperture at the top of the cabinet and connect the ground cable to the terminal, as shown in Figure 2.
Figure 2 Connections of the ground cable
NOTE:
If the lap resistance between the ground cable of the device and the ground bar exceeds 0.1 ohms, route the ground cable
again.
3. The AC power cables and the EPS75-4815AF power system in the underfloor mode are connected in a
similar way as in the overhead mode. For details, see Routing Power Cables from Overhead (AC Power Supply).
Procedure
1. Route the DC power cables and the ground cable into the cabinet through the aperture shown in Figure
1.
Figure 1 Routing the DC power cables and the ground cable into the cabinet
2. Route the yellow and green ground cable from the aperture at the top of the cabinet and connect the
ground cable to the terminal, as shown in Figure 2.
Figure 2 Connections of the ground cable
NOTE:
If the lap resistance between the ground cable of the device and the ground bar exceeds 0.1 ohms, route the ground cable
again.
3. The DC power cables and the DC PUD in the underfloor mode are connected in a similar way as in the
overhead mode. For details, see Routing Power Cables from Overhead (DC Power Supply).
Preparations
This topic describes the preparations and precautions for routing battery connecting cables.
Procedure
This topic describes the procedure for routing battery connecting cables. (Consider the F02A cabinet as an
example)
4.1.2.6.8.1 Preparations
This topic describes the preparations and precautions for routing battery connecting cables.
Precautions
Pay attention to the following when installing the batteries:
Battery interconnecting Positive lead of the battery Negative lead of the other battery
cable
Negative lead of the battery Positive lead of the other battery
Battery lay out cable lay out cable of the BATT(-) terminal Negative lay out cable (blue) of one set of
on the AC power supply batteries
lay out cable of the BATT(+) terminal Positive lay out cable (black) of one set of
on the AC power supply batteries
Checking Items
Check the batteries and ensure that they meet the requirements listed in Table 2.
Measure the open circuit voltage of the batteries with the multimeter. The open circuit voltage must not be
lower than 12.48 V (for 12 V batteries). Otherwise, recharge the batteries through the background
monitoring system. Huawei recommends forcing an even charging manually with the charging coefficient
0.15 for 16 to 20 hours.
NOTE:
The following table lists the maximum dimensions of the battery in the cabinet. You can refer to these dimensions during
installation.
4.1.2.6.8.2 Procedure
This topic describes the procedure for routing battery connecting cables. (Consider the F02A cabinet as an
example)
Parent topic: Routing Battery Connecting Cables
Preparations
Before routing subscriber cables, confirm the positions of the cables and ensure that the necessary
precautions are complied with.
Routing Subscriber Cables from Overhead in the Distributed Configuration (Rear Access)
This topic describes how to route subscriber cables from overhead in the distributed configuration in the
rear access mode. (Consider the F02A cabinet as an example)
Routing Subscriber Cables from Overhead in the Distributed Configuration (Front Access)
This topic describes how to route subscriber cables from overhead in the distributed configuration in the
front access mode. (Consider the F02A cabinet as an example)
Routing Subscriber Cables from Underfloor in the Distributed Configuration (Rear Access)
This topic describes how to route subscriber cables from underfloor in the distributed configuration in the
rear access mode.
Routing Subscriber Cables from Underfloor in the Distributed Configuration (Front Access)
This topic describes how to route subscriber cables from underfloor in the distributed configuration in the
front access mode.
4.1.2.6.9.1 Preparations
Before routing subscriber cables, confirm the positions of the cables and ensure that the necessary
precautions are complied with.
32-channel subscriber cable (rear Transfer board or cabling area of the MDF outside of the cabinet
access) shelf backplane
32-channel subscriber cable Front panel of a service board
(front access)
Internal 32-channel subscriber Cabling area of the shelf backplane Exchange side terminal block in the
cable cabinet
External subscriber cable Subscriber side Cable side terminal block in the
cabinet
NOTE:
In the integrated configuration, connect the exchange side terminal block and the cable side terminal block with jumpers.
attching Labels
attch labels at both ends of a subscriber cable, as shown in Figure 1. For how to attch labels, see Cable Labels.
Figure 1 attching a label to a subscriber cable
The principles and procedure for routing subscriber cables from underfloor are the same as those for
routing subscriber cables from overhead. The only difference is the aperture. As shown in Figure 1, in the
underfloor mode, subscriber cables are routed from the aperture at the bottom of the cabinet. For detailed
connection procedures, see Routing Subscriber Cables from Overhead in the Distributed Configuration (Front Access).
Figure 1 Routing subscriber cables from underfloor
Parent topic: Routing Subscriber Cables
The principles and procedure for routing subscriber cables from underfloor are the same as those for
routing subscriber cables from overhead. The only difference is the aperture. As shown in Figure 1, in the
underfloor mode, external subscriber cables are routed from the aperture at the bottom of the cabinet. For
detailed connection procedures, see Routing Subscriber Cables from Overhead in the Integrated Configuration.
Figure 1 Routing external subscriber cables from underfloor
Preparations
This topic describes the preparations and precautions for routing trunk cables.
4.1.2.6.10.1 Preparations
This topic describes the preparations and precautions for routing trunk cables.
Confirming the Connections
Table 1 shows the connections of trunk cables.
Trunk cable from EDTB to DDF Connect the DB-44 connector of the DDF outside of the cabinet
former eight E1 signals to the upper DB-
44 port on the E1TB transfer board.
Connect the DB-44 connector of the later
eight E1 signals to the lower DB-44 port
on the E1TB transfer board.
Trunk cable from SDLE to DDF Connect the DB-68 connector to the DB- Connect E1 bare wires to the DDF
68 port on the front panel of SDLE. outside of the cabinet
NOTE:
SDLE has the DB-68 port on the front panel to provide eight channels of E1 signals. In addition, it also provides eight channels
of SHDSL signals through the cabling area of the backplane.
For SHDSL access, the 32-channel subscriber cable (rear access) is used. The bare wires of such a subscriber cable are
connected to the MDF outside of the cabinet. For details of connections, see Routing Subscriber Cables from Overhead in the
Distributed Configuration (Rear Access).
In the underfloor mode, the apertures for the trunk cables are at the bottom of the cabinet, as shown in
Figure 2.
Figure 2 Apertures for the trunk cables in the underfloor mode (top view)
NOTE:
Reserve sufficient space between trunk cables and subscriber cables for future capacity expansion and maintenance.
attching Labels
attch labels at both ends of a trunk cable, as shown in Figure 3. For how to attch labels, see Cable Labels.
Figure 3 attching a label to a trunk cable
The principles and procedure for routing trunk cables from underfloor are the same as those for routing
trunk cables from overhead. The only difference is the aperture. As shown in Figure 1, in the underfloor
mode, trunk cables are routed from the aperture at the bottom of the cabinet. For detailed connection
procedures, see Routing Trunk Cables from Overhead.
Figure 1 Routing trunk cables from underfloor
Parent topic: Routing Trunk Cables
Preparations
This topic describes the preparations and precautions for routing network cables.
4.1.2.6.11.1 Preparations
This topic describes the preparations and precautions for routing network cables.
Network cable Upstream Ethernet port on the front panel Transmission equipment or other
of the control board upper-layer equipment
Upstream Ethernet port on the front panel Maintenance terminal
of the control board
attching Labels
attch labels at both ends of a network cable, as shown in Figure 1. For how to attch labels, see Cable Labels.
Figure 1 attching a label to a network cable
The principles and procedure for routing network cables from underfloor are the same as those for routing
network cables from overhead. The only difference is the aperture. As shown in Figure 1, in the underfloor
mode, network cables are routed from the aperture at the bottom of the cabinet. For detailed connection
procedures, see Routing Network Cables from Overhead.
Figure 1 Routing network cables from underfloor
Parent topic: Routing Network Cables
Optical fiber The optical port on the front panel of the control board Transmission unit or ODF
NOTE:
Different transmission units or ODFs use different connectors. When the optical fibers are connected to the transmission unit or
the ODF with non-LC/PC ports, a converter is required.
Confirming the Positions of Apertures
In the overhead cabling, the apertures for the optical fibers are at the top of the cabinet, as shown in Figure
1.
Figure 1 Apertures for the optical fibers in the overhead cabling (top view)
In the underfloor cabling, the apertures for the optical fibers are at the bottom of the cabinet, as shown in
Figure 2.
Figure 2 Apertures for the optical fibers in the underfloor cabling (top view)
z "A01-01-05-05-R" indicates that the local end of the optical fiber is connected to optical receive port 05
in slot 05, shelf 01 in the cabinet in row A, column 01.
z "G01-01-01-01-T" indicates that peer end of the optical fiber is connected to optical transmit port 01 in
slot 01, shelf 01 in the cabinet in row G, column 01.
Figure 4 shows a label on the optical fiber from the device to the ODF.
Figure 4 Example of a label on the optical fiber from the device to the ODF
z "ODF-G01-01-01-R" indicates that the local end of the optical fiber is connected to optical receive port
in row 01, column 01 of the ODF in row G, column 01.
z "A01-01-05-05-R" indicates that the peer end of the optical fiber is connected to optical receive port 05
in slot 05, shelf 01 in the cabinet in row A, column 01.
The principles and procedure for routing optical fibers from underfloor are the same as those for routing
optical fibers from overhead. The only difference is the aperture. As shown in Figure 1, in the underfloor
mode, optical fibers are routed from the aperture at the bottom of the cabinet. For detailed connection
procedures, see Routing Optical Fibers from Overhead.
Figure 1 Routing optical fibers from underfloor
Context
NOTICE:
When attaching cabinets, install two side covers on both the sides of the outermost cabinets. You do not
need to install the side covers of the adjacent cabinets.
Procedure
1. Place the side cover on the side of the cabinet. Align the holes on the side cover with the holes on the
cabinet, and fasten the eight M6 x 12 screws in the eight screw holes by using the Phillips screwdriver,
as shown in Figure 1. Do not fasten the screws completely.
Figure 1 Fastening the screws on one side cover of the cabinet
2. Fasten the eight M6 x 12 screws.
3. Repeat 1 and 2 to install the other side cover, as shown in Figure 2.
Figure 2 Fastening the screws on the other side cover of the cabinet
Context
The requirements for installing the smoke sensor are as follows:
z To install the smoke sensor at the middle of the cabinet top or of the ceiling, comply with the following
requirements:
No blocking materials within 0.5 m around the sensor
Horizontal distance from the inhaling vent of the air condition > 1.5 m
Horizontal distance from the inhaling vent at the top > 0.5 m
Horizontal distance from the exhausting vent of the air condition > 1.5 m
z Install the smoke sensor in a place where smoldering happens and heavy smoke is generated at the
preliminary stage. Do not install the smoke sensor in the following places:
Only black smoke is generated in burning, and no smoke or little smoke is generated.
The relative humidity is larger than 95% for a long period.
The airflow speed is larger than 5 m/s.
Heavy dust and spray are existing.
Erosive gas may be generated.
Smoke is stagnated even in normal conditions.
Organic substances, such as alcohols, ether, and ketone, are generated.
z Before powering on the sensor, ensure the probe is connected correctly with the controller. The red
LED blinks properly after the sensor is powered on for 30s, with the blinking period of 9s to 15s.
z Dust may be accumulated on the smoke sensor. Remove dust from the sensor periodically to avoid error
alarming.
Precautions
Before applying the probe, to protect it from being polluted, do not remove the dust-proof cover on the
probe.
Installation instructions
Use the auxiliary base when installing the smoke sensor.Figure 1 shows the auxiliary base and Table 1 lists
the specifications of the base. When connecting the probe to the controller, use the 2-wire mode without
polarity and use the cable connecting port as the input end.
Figure 1 Structure of the auxiliary base
Outline (W x D x H) 75mm×51mm×5mm
Fixing hole 5mm×10mm
Fixing hole spacing 52mm-66mm
Procedure
1. Use two M4 screws and fixing holes A and B to fasten the matched base to the cabinet component.
2. 2. Install the smoke sensor to the matched base, as shown in Figure 2
Figure 2 Installing the smoke sensor
3. Connect the sensor cable. Figure 3 shows the connections of the smoke sensor.
Figure 3 Connections of the smoke sensor
NOTE:
In the above figures, JTDx refers to the digit parameter port on the ESC, which is determined by the main label on the
monitoring cable. Insert the monitoring cable to the corresponding digit port.
Context
The water sensor can be installed in both the indoor cabinet and outdoor cabinet.
z For the indoor cabinet: The indoor cabinet is installed in the equipment room. Install the water sensor
also on the floor of the equipment room, near the cabinet.
z For the outdoor cabinet: Install the water sensor at the bottom of the equipment compartment in the
cabinet.
Precautions
z Do not supply power reversely.
z Do not measure acetone, chloride solvent.
z Do not open the cover of the water sensor to avoid damages.
z During the application, it is recommended to maintain the water sensor every one to six months, keep
the surface of the solid-state liquid-level sensing head free from dust, and check whether the sensor
cover is damaged or has any other abnormality (If yes, replace the water sensor immediately).
Procedure
1. Install the water sensor.
z For the indoor cabinet: Find a fixed object, such as vertical wooden attach, in the equipment room,
install the water sensor on the floor, and use a cord to bundle the water sensor on the fixed object.
Ensure that the solid-state liquid-level sensing head faces upward.
z For the outdoor cabinet: Install the water sensor vertically at the bottom of the equipment
compartment in the cabinet, and use a cord to bundle the water sensor in the cabinet. Ensure that the
solid-state liquid-level sensing head faces upward.
2. Connect the sensor cable. Figure 2 shows the connections of the water sensor when it connects to the
esc. Figure 3 shows the connections of the water sensor when it connects to the sensor transfer box.
Figure 2 Connections of the water sensor
Context
z The battery temperature sensor is used to sample the ambient temperature of the battery set.
z Install the temperature probe at a position that best represents the temperature in the battery
compartment, and do not connect the temperature probe to other heating devices.
Precaution
Install the temperature probe at a position that best represents the temperature in the battery compartment,
and do not connect the temperature probe to other heating devices.
Procedure
1. Connect the connector of the cable to the BAT-WE port of the sensor transfer box, as shown in Figure 1.
2. The other end is the temperature probe with a ring terminal, which is bundled with the negative lead of
a single battery, as shown in Figure 1.
Figure 1 Connection of the battery temperature sensor
Context
After the power cables and the ground cables are inserted into the cabinet through apertures on the rubber
cover, the rubber cover shrinks automatically. No extra sealing is required.
Context
The optical fibers are lead into the corrugated pipe, and then routed into the cabinet. After routing the
optical fibers, use an adhesive tape to seal the entry of the corrugated pipe.
1 The cabinet (chassis) must be stable, and must comply with the shockproof Observe
requirements in the project files.
2 Each support (foot) must be secured correctly to all the expansion bolts in the Observe
ground. Insulating pads, big flat washers, spring washers, and nuts (bolts)
must be installed in the correct sequence. The installation holes of the support
(foot) cooperate with the expansion bolts properly.
3 The cabinet accessories must be installed correctly and properly. The door and Observe
the door lock must open and close properly.
4 The appearance of the cabinet should not be distorted. No part of any cabinet Observe
is deformed.
5 The active parts of the cabinet must function in the normal state. Observe
6 Other connecting bolts of the cabinet must be installed correctly and properly. Refer to this document
The flat washers and the spring washers must be installed in the correct
sequence (install the flat washers, and then install the spring washers).
7 The paint on the surface of cabinet should not flake, there should not be any Observe
dent on the surface of the cabinet, and the surface of the cabinet should not be
dirty. Otherwise, paint the cabinet again or clean it.
8 All cable apertures must be sealed. Observe
9 The cabinet (chassis) must be placed according to the project files. Check the installation
position
10 Insulating parts must be installed between the delivered support (foot filling Observed and
pad) and the ground, floor holder and guide rail according to the requirements. confirmed by the
Ensure that the insulation is provided. The filling pad made by the customer customer
must meet the requirements.
11 The vertical deviation of the cabinet must be less than 3 mm (you can use the Measure
plumb to measure the vertical deviation).
12 The cabinet rows near the main aisle must be aligned in a straight line, with a Measure
deviation of less than 5 mm.
13 The surfaces of the cabinets in a row must be in one plane, and the cabinets Observe
must be installed close to each other and in proper order.
14 The boards can be inserted and removed smoothly. If the front panel of the Refer to this document
board has screws, fasten the screws properly so that it is easy to remove them
when required. The spring wires must be intact.
15 There should be no redundant objects such as cable ties and screws inside the Observe
cabinet, at the bottom of the cabinet, or on the top of the cabinet.
16 The floor gaps around the cabinet are filled. There should not be any cable Observe
ties, screws, or other redundant objects under the floor.
17 Connect the ESD wrist strap to the ESD jack on the cabinet. Observe
-48 V feeder cable of the service shelf HABA AC power module LOAD(-) 3-
JP1 AC power module LOAD(+) 3+
-48 V feeder cable of the service shelf HABA AC power module LOAD(-) 4-
JP2 AC power module LOAD(+) 4+
ESC monitoring cable HABA RS485/RS232
JD3
Fan monitoring cable HABA Sensor transfer box JTD1
JD1(FAN- Sensor transfer box JTD2
ALM)
Door status sensor connecting cable Sensor 1-pin connector
transfer
box JTM1
Door status sensor communication cable Door 1-pin connector
status
sensor of
the front
door
Door status sensor communication cable Door 1-pin connector
status
sensor of
the rear
door
Communication cable between door status 1-pin 1-pin connector
sensors connector
PGND feeder cable Grounding Grounding point on the side cover of the cabinet
point on
the side
cover of
the cabinet
PGND feeder cable Grounding Grounding point on the side cover of the cabinet
point on
the rear
door of the
cabinet
PGND feeder cable Grounding Grounding point on the side cover of the cabinet
point on
the side
cover of
the cabinet
PGND feeder cable Grounding Grounding point on the side cover of the cabinet
point on
the front
door of the
cabinet
Battery connecting cable Negative Positive lead of battery 2
lead of
battery 1
Battery connecting cable Negative Positive lead of battery 3
lead of
battery 2
Battery connecting cable Negative Positive lead of battery 4
lead of
battery 3
Battery connecting cable Positive Terminal at the left of the AC PDU BAT1(+)
lead of
battery 1
Battery connecting cable Negative AC PDU BAT1(-) B1
lead of
battery 4
MDF monitoring cable Sensor MDF monitoring point
transfer
box JTP1
MDF ground cable MDF MDF monitoring point
monitoring
point
MDF ground cable MDF Cabinet busbar grounding point
grounding
point
-48 V feeder cable of the HABA JP1 J1-type PDU -48V1, the first channel
service shelf HABA JP2 J1-type PDU BGND1, the first channel
J1-type PDU -48V1, the second channel
J1-type PDU BGND1, the second channel
-48 V feeder cable of the Subtended HABA JP1 J1-type PDU -48V3, the first channel
service shelf Subtended HABA JP2 J1-type PDU BGND3, the first channel
J1-type PDU -48V3, the second channel
J1-type PDU BGND3, the second channel
-48 V power cable of the ESC BOX JP3 J1-type PDU -48V2, the first channel
ESC J1-type PDU BGND2, the first channel
ESC monitoring cable HABA JD3 ESC BOX JC1
ESC BOX JC3
Fan monitoring cable HABA JD1(FAN-ALM) ESC BOX JTD1
ESC BOX JTD2
Fan monitoring cable Subtended HABA JD1(FAN- ESC BOX JTD3
ALM) ESC BOX JTD4
Monitoring signal HABA JD0 Subtended HABA JD0
subtending cable HABA JD2 Subtended HABA JD2
Door status sensor ESC BOX JTM1 1-pin connector
connecting cable
Door status sensor Door status sensor of the front 1-pin connector
communication cable door
Door status sensor Door status sensor of the rear 1-pin connector
communication cable door
Communication cable 1-pin connector 1-pin connector
between door status sensors
HW cable HABA HWCB HW Subtended HABA HWTB HW
PGND feeder cable Grounding point on the side Grounding point on the side cover of the
cover of the cabinet cabinet
PGND feeder cable Grounding point on the rear door Grounding point on the side cover of the
of the cabinet cabinet
PGND feeder cable Grounding point on the side Grounding point on the side cover of the
cover of the cabinet cabinet
PGND feeder cable Grounding point on the front door Grounding point on the side cover of the
of the cabinet cabinet
PGND feeder cable ESC BOX JP1 Cabinet grounding point
-48 V feeder cable of the HABA JP1 J2-type PDU -48V1, the first channel
service shelf HABA JP2 J2-type PDU BGND1, the first channel
J2-type PDU -48V1, the first channel
J2-type PDU BGND1, the first channel
-48 V feeder cable of the Subtended HABA JP1 J2-type PDU -48V3, the second channel
service shelf Subtended HABA JP2 J2-type PDU BGND3, the second channel
J2-type PDU -48V3, the second channel
J2-type PDU BGND3, the second channel
-48 V power cable of the ESC BOX JP3 J2-type PDU -48V2, the third channel
ESC J2-type PDU BGND2, the third channel
ESC monitoring cable HABA JD3 ESC BOX JC1
ESC BOX JC3
Fan monitoring cable HABA JD1(FAN-ALM) ESC BOX JTD1
ESC BOX JTD2
Fan monitoring cable Subtended HABA JD1(FAN- ESC BOX JTD3
ALM) ESC BOX JTD4
Monitoring signal HABA JD0 Subtended HABA JD0
subtending cable HABA JD2 Subtended HABA JD2
Door status sensor ESC BOX JTM1 1-pin connector
connecting cable
Door status sensor Door status sensor of the front 1-pin connector
communication cable door
Door status sensor Door status sensor of the rear 1-pin connector
communication cable door
Communication cable 1-pin connector 1-pin connector
between door status sensors
HW cable HABA HWCB HW Subtended HABA HWTB HW
PGND feeder cable Grounding point on the side Grounding point on the side cover of the
cover of the cabinet cabinet
PGND feeder cable Grounding point on the rear door Grounding point on the side cover of the
of the cabinet cabinet
PGND feeder cable Grounding point on the side Grounding point on the side cover of the
cover of the cabinet cabinet
PGND feeder cable Grounding point on the front door Grounding point on the side cover of the
of the cabinet cabinet
PGND feeder cable ESC BOX JP1 Cabinet grounding point
1 The delivered alarm monitoring system, such as MDFs, batteries, and alarm box must Observe
be connected correctly and properly. Protective units on the MDF must work in the
normal state and must be grounded properly.
2 The NMS device should be installed correctly and must be working properly. Observe
3 The floppy drive, CD-ROM, keyboard, mouse, and monitor must work normally. The Observe
monitor does not have magnetic deviation.
4 The delivered terminals, NMSs, alarm boxes, and inverters must be installed according Observe
to the engineering design.
5 The shell of the maintenance terminal must be grounded properly. Observe
6 The cables of the terminal, NMS, and alarm box must be bundled properly. Cut the Observe
redundant parts of the cable ties neatly.
7 The cables of the terminal, NMS, and alarm box must be smooth at the bending for Observe
proper contact.
8 You should be able to open the front cover of the alarm box smoothly. The keyboard Observe
lock must have control functions. The paint on the alarm box must not flake.
9 A PVC trough should be installed for power cables and signal cables of the alarm box Observe
near the wall. The redundant parts must be placed under the floor or on the cable tray
beside the box.
10 The alarm box must be grounded properly. Observe
1 Power cables and ground cables should be connected correctly and Observe
properly.
2 Delivered surge protector should be installed correctly. Reserve 5 m to 10 Observe
m of the AC power cable from the surge protector to the device. The
redundant part should be coiled.
3 Power cables or ground cables must be whole copper core cables without Observe
any joint on the cable.
4 Power cables and ground cables should be properly connected with the Observe
lugs.
5 Power cables, ground cables, and signal cables must be routed separately Observe
inside the cabinet. The space between power cables, ground cables, and the
signal cables outside the cabinet must conform to the engineering design. It
is recommended that the space between the cables be more than 3 cm.
6 When connecting the power cables and the ground cables to the DC power Observe
distribution cabinet, cut the redundant parts. The cables cannot be coiled.
7 The PGND cables of the MDF and the DDF must be connected properly. Observe
Adjacent MDFs or DDFS must be interconnected to the protection ground
busbar.
8 The cross-sectional area of power cables, ground cables, and equipotential Observe
cables between cabinets must meet the power distribution requirements:
z Check whether the cross-sectional area is consistent with the delivery.
z Check whether the cross-sectional area meets the installation
requirements.
9 Equipotential cables between the combined cabinets should be connected Measure
correctly and properly.
10 Ring terminal tails of power cables and ground cables and the bare wires Observe
must be wrapped with protection pipe or PVC insulation tape. There
should not be any bare parts on lugs or terminals. Flat washers and spring
washers must be installed correctly.
11 All devices with metal shell or partial metal shell inside the cabinet or Measure
chassis should be connected to the protection ground correctly.
12 Delivered power supply systems, such as batteries must be installed Observe
according to the engineering design.
13 Power cables and ground cables should be routed according to the Observe
engineering design and should facilitate maintenance and expansion in the
future.
14 Colors of power cables and ground cables must be consistent with the Observe
delivery, or must meet the requirements of the customer.
15 Ground cables must be connected correctly and properly on the cabinet Measure
door.
16 The routed power cables and ground cables must be bundled neatly and in Observe
a straight line.
17 Power cables and ground cables must be smooth at the turning. Adopt Observe
protection measures when connecting cables with edged ports.
18 The power-on process of the device is normal, the fans rotate in the normal Observe
state, and the alarms should be normal.
19 The length of the ground cable must be within 10 m. Measure
1 AC power parameters meet the requirements for the long-term running of the Confirmed by the
device. The AC power supply system is equipped with the surge protector. The customer
surge protector is grounded properly. DC power parameters meet the requirements
for the long-term running of the device.
2 The shield layer of the external subscriber cable is grounded correctly. Confirmed by the
customer
3 PGND cables of the AC power supply are connected properly to the AC Confirmed by the
protection ground busbar, and PGND cables of the DC power supply are customer
connected properly to the DC protection ground busbar. GND busbar and PGND
busbar provided by the customer are connected to the same grounding body.
4 The grounding resistance of the equipment room is less than 10 ohms. The Confirmed by the
grounding resistance should comply with the national or local regulations. customer (according
to the level of the
equipment room)
5 For the cross-sectional area and the power mode of the PGND cable of the Confirmed by the
customer, GND cable of the primary power, and -48 V cable to the power customer
distribution cabinet or power distribution unit (PDU), the engineering design or
actual delivery of Huawei counts. The requirements for running the device and the
requirements for expansion in the future are met.
6 The output current fuse of the power distribution cabinet and the primary power Confirmed by the
must meet the requirements for running the device. customer
7 Do not rout outdoor cables to the equipment room in the overhead mode. Observe
Otherwise, adopt lightning-proof measures when routing the outdoor cables to the
equipment room in the overhead mode.
1 The equipment room is clean and neat. Sundries such as discarded packing cases Observe
are removed. Redundant spare parts are placed in order.
2 Configure the fire retardant cover for the reserved holes on the equipment floor, Observe
and ensure that the holes can be sealed for insulation.
3 Adopt fire retardant materials for the new decoration in the equipment room. Observe
4 The fire-fighting equipment is available in the equipment room, such as the fire Observe
extinguisher.
1 The trunk cables from the cabinet to the DDF are connected according to the Engineering Design.
2 The optical fibers from the cabinet to the ODF are connected correctly.
3 The network cables from the cabinet to the MDF are connected correctly.
4 The subscriber cables from the cabinet to the MDF are connected correctly. Check the connectivity
of the cables for each pair on the MDF by using a multimeter according to the following method.
Power-On Process
Before performing the power-on check, you must be familiar with the power-on process and the power-off
process of the device, and ensure that the device can be powered on and powered off successfully.
This topic describes how to check and ensure that the surge protector can be powered on successfully.
2. Power On the AC Power Module
This topic describes how to check and ensure that the AC power module can be powered on
successfully.
3. Powering On the Service Shelf
This topic describes how to check and ensure that the service shelf can be powered on successfully.
4. Powering On the Battery
This topic describes how to check and ensure that the battery can be powered on successfully.
This topic describes how to check and ensure that the surge protector can be powered on successfully.
2. Power On the AC Power Module
This topic describes how to check and ensure that the AC power module power the system
successfully.
3. Powering On the Service Shelf
This topic describes how to check and ensure that the service shelf can be powered on successfully.
This topic describes how to check and ensure that the service shelf can be powered on successfully.
Procedure
1. Turn off the AC input switch on the AC power module.
2. Open the cover of the surge protector.
3. Ensure that all cable connections comply with the connection diagram on the internal side of the surge
protector. Turn on the AC input switch of the surge protector.
4. Use a multimeter to measure the voltage of the input terminals of the AC power supply, and check
whether the voltage is normal. The voltage should range from 88 V to 155 V for the 110 V power
supply, and from 90 V to 290 V for the 220 V power supply.
5. Turn on the circuit breaker in the surge protector, and ensure that the green LED is on.
6. After confirming that all the previous steps are right, close the cover of the surge protector.
7. Turn off the AC input switch.
Table 1 describes the meanings of the LEDs on the panel of the surge protector.
Procedure
1. Ensure that the -48 VDC feeder cables of the battery, load control switches, and service shelves are
disconnected.
2. Turn on the AC input switch of the surge protector.
3. Use a multimeter to measure the voltage of the input terminals of the AC power supply, and check
whether the voltage is normal. The voltage should range from 88 V to 155 V for the 110 V power
supply, and the voltage should range from 90 V to 290 V for the 220 V power supply.
4. Turn on the AC input switch on the EPS75-4815AF power system.
5. Observe the LEDs of the rectifier unit of the EPS75-4815AF power system, and check whether the
EPS75-4815AF power system works in the normal state.
Table 1 describes the meanings of the LEDs on the front panel of the rectifier unit.
Table 1 Meanings of the LEDs on the front panel of the rectifier unit
LED Name Description
The load output terminals of the J1–type DC PDU are on the top right of the PDU, as shown in Figure 2.
Figure 3shows the wiring connections of the DC load tributaries. Table 1 shows the match-up between the
output tributary switch and the load tributary.
Figure 3 Wiring connections of the DC load tributaries
Table 1 Match-up between the output tributary switch and the load tributary
Output Tributary Switch Controlled Load Controlled Load Tributary
The load output terminals of the J1–type DC PDU are on the top right of the PDU, as shown in Figure 5.
Figure 6shows the wiring connections of the DC load tributaries. Table 2 shows the match-up between the
output tributary switch and the load tributary.
Figure 6 Wiring connections of the DC load tributaries
Table 2 Match-up between the output tributary switch and the load tributary
Output Tributary Switch Controlled Load Controlled Load Tributary
Procedure
1. Ensure that the -48 VDC feeder cables of the service shelves (each service shelf has two -48 VDC
inputs) are disconnected.
2. Ensure that the switches SW1 and SW2 on the panel of the PDU are turned off.
3. Check whether the connections of the input power cables of the PDU are correct (see "Routing External
Power Cables and Ground Cable"). Use a multimeter to check whether the input terminals of the PDU are
short-circuited.
4. Use a multimeter to measure the voltage of the output terminals of the DC power distribution cabinet,
and check whether the voltage of the output terminals is normal. The voltage should range from -38.4
V to -57.6 V. If the output voltage is normal, power on the cabinet.
5. Use a multimeter to measure the voltage of the input terminals of the PDU, and check whether the
voltage is normal. The voltage should range from -38.4 V to -57.6 V.
6. Turn on the -48 V output control switches SW1 and SW2. Use a multimeter to measure the voltage of
the -48 V output terminals of the PDU, and check whether the voltage is normal. The voltage should
range from -38.4 V to -57.6 V.
Context
After checking the power system or the PDU, power on the service shelf.
Procedure
1. Use a multimeter to measure the voltage of the connector of the -48 VDC feeder cable, and check
whether the voltage is normal. The voltage should range from -38.4 V to -57.6 V.
2. Use a multimeter to measure the voltage of the -48 VDC input terminals of the power supply, and
check whether the terminals are short-circuited.
3. Disconnect the load control switch on the power system or the -48 VDC output control switch SW1 on
the front panel of the PDU.
4. Connect the -48 VDC feeder cables (each service shelf has two -48 VDC inputs).
5. Turn on the load control switch on the power system or the -48 VDC output control switch SW1 on the
front panel of the PDU.
6. Check the status of the fan tray. If the fans start rotating, the green STATUS LED on the front panel
starts blinking.
7. Turn on the -48 VDC output control switch DC SW2 on the front panel of the PDU, and check the
status of the two fan trays of the HABA.
8. Turn on the power switch and the alarm switch on the front panel of the PWX board, as shown in
Figure 1.
Figure 1 Turning on the power switch and the alarm switch on the front panel of the PWX board
9. Check the LEDs on the PWX board and the audio alarms of the PWX board. When the PWX board is
powered on successfully, no audio alarm is generated. Table 1 lists the LEDs on the PWX board when
the PWX board works in the normal state.
NOTE:
Boards related to the narrowband services can start successfully only after the PWX board works in the normal state.
10. Check the LEDs on other boards. Observe the RUN LEDs and the ACT LEDs on other boards, and
check whether the boards work in the normal state. For the meanings of the LEDs on the boards, see
"Introduction to Boards" of the UA5000 Hardware Description.
Procedure
1. Check the polarities at both ends of the battery switch with the multimeter.
2. Turn on the "BATT" battery control switch of the power system.
3. Touch the side of the battery and the jacket of the cable connected to it. If no obvious heat is felt, it
indicates that the connection is correct.
Power-off Process
Figure 1 shows the power-off process of the AC-powered ONU-F02A in integrated configuration.
Figure 1 Power-off process of the AC-powered ONU-F02A in integrated configuration
Procedure
1. Turn off the "BATT" battery control switch of the power system.
2. Turn off the power switch and the alarm switch on the front panel of the PWX board.
3. Turn off the "LOAD4" switch of the power system.
4. Turn off the "AC INPUT" switch of the power system.
5. Turn off the power input for the surge protector.
Process
Figure 1 shows the power-off process of the AC-powered F02A in Distributed Configuration/AC-Powered
N66E-18 Configuration.
Figure 1 Power-off process of the AC-powered F02A in Distributed Configuration/AC-Powered N66E-18
Configuration
Procedure
1. Turn off the power switch and the alarm switch on the front panel of the PWX board.
2. Turn off the LOAD4 switch of the power system.
3. Turn off the AC INPUT switch of the power system.
4. Turn off the power input for the surge protector.
Process
Figure 1 shows the power-off process of the DC-powered ONU-F02A/N66E-18 configuration.
Figure 1 Power-off process of the DC-powered ONU-F02A/N66E-18 configuration
Procedure
1. Turn off the power switch and the alarm switch on the front panel of the PWX board.
2. Turn off the DC SW1 switch and the DC SW2 switch on the front panel of the PDU.
3. Turn off the power input switch of the PDU.