Mud Gas Separator (Poor Boy Degasser) Plays

A Vital Role in Well Control Situation


Post Views: 4,804

Mud gas separator located at downstream of the choke manifold is one of the important
well control equipment that you need to focus. It separates gas out of the mud after the
gas comes out of hole. Gas will be vent to atmosphere via the vent line in derrick
(offshore operation) or the line away from the rigs (land operation) and the mud will be
returned back to the pit.

In the oilfield, people have several names for the mud gas separator as “poor boy
degasser” or “gas buster”. While drilling, the mud gas separator should be lined up at all
times and filled with the present mud weight currently used.

The concept of this equipment is density difference between liquid and gas. When the
mud coming out from the choke manifold goes into the mud gas separator, mud will hit
the baffle plates which are used to increase travelling time and allow gas to move out of
the mud. Gas which has lower density than air will move up and mud will goes down due
to gravity (see – Figure 1). Mud leg will provide hydrostatic pressure in order to prevent
mud going through the separator into the rig.
Figure 1 – Mud Gas Separator Diagram

The mud gas separator is strictly used for well control only. There are some events that
this equipment is utilized in a well testing operation. Additionally, inspection for the gas
buster must be performed frequently the same as other well control equipment. People
tends to forgot about this since it is just only a vertical separator tank without high
pressure specification like BOP, choke manifold, valves, etc. Erosion is one of the worst
enemies to the vessel like this and it can be seen at the points where the drilling mud
impinges on the internal wall vessel.

Each mud gas separator has limitation on much it can safely handle volume of gas. If the
volume of gas exceeds the maximum limit, gas can blow through into the rig. It is very
important that you must estimate gas flow rate on surface based on pit gain and kill rate
in order to see how much expected gas on surface. This will be the limitation on how
much you can circulate for well killing operation. You can estimate the volume gas on
surface by using well control kill sheet provided by several companies. You need to
ensure that the vent line should be as straight as possible with a larger ID in order to
minimize back pressure while venting the gas out.

What’s more, a pressure gauge should be installed on the mud gas separator and
frequently calibrated. This is very important because you will use this gauge to monitor
the gas blow through situation. If the pressure in the vessel is more than hydrostatic
pressure provided by mud leg, gas will blow through the vessel. By carefully monitoring,
you will be able to react in a timely manner. If the pressure gauge shows you that
pressure will reach the limit, you should reduce current circulation rate to control
volume of gas coming into it.

There are several considerations for mud gas separator design. You need to know the
reservoir gas because if it is a sour gas (H2S), the mud gas separator should be able to
handle this. The normal vessel will not work safely with H2S. Even though it has a name
as “poor boy gasser”, it does not mean that it can be built in a cheaper way by some
machine shops. The vessel must be fabricated to meet ASME specification and there must
be a third party to certify it. What’s more, the scheduled preventive maintenance must be
in place and strictly followed.

How Much Pressure Will Cause Blow Through?

This is a very important concept of blowing through while performing well control. Mud
leg length is 20 ft and mud weight is 9.5 ppg (see – Figure 2)
Figure 2 – Mud
Gas Separator and Blow Through

Pressure to blow through = Hydrostatic pressure provided by mud leg = 0.052 × Mud
Weight (PPG) × Mud Leg (ft)

Pressure to blow through = 0.052 × 9.5 × 20 = 9.88 psi

More details about blow through is here Blow Through Situation in Mud Gas
Separator.

References

Cormack, D. (2007). An introduction to well control calculations for drilling operations.


1st ed. Texas: Springer.
Crumpton, H. (2010). Well Control for Completions and Interventions. 1st ed. Texas: Gulf
Publishing.

Grace, R. (2003). Blowout and well control handbook [recurso electrónico]. 1st ed. Paises
Bajos: Gulf Professional Pub.

Grace, R. and Cudd, B. (1994). Advanced blowout & well control. 1st ed. Houston: Gulf
Publishing Company.

Watson, D., Brittenham, T. and Moore, P. (2003). Advanced well control. 1st ed.
Richardson, Tex.: Society of Petroleum Engineers.

You might also like