Professional Documents
Culture Documents
SPE 90829 Transition Time of Cement Slurries, Definitions and Misconceptions, Related To Annular Fluid Migration
SPE 90829 Transition Time of Cement Slurries, Definitions and Misconceptions, Related To Annular Fluid Migration
SPE 90829 Transition Time of Cement Slurries, Definitions and Misconceptions, Related To Annular Fluid Migration
different types of laboratory test devices in a standard for our testing, which is roughly
order to attempt to develop such standards. equal to one complete rotation in about 23
One of the test devices being evaluated is an hours. It is the drag of the slurry on this very
ultrasonic test device (SGSA) that uses slowly turning paddle that is used to compute
interpretation of ultrasonic transmissions the SGS. Typically, once a slurry has obtained
passing through the cement slurry to an SGS of 500 lbf/100 sq ft (240 Pa), the test
determine the developing SGS. is considered to be finished and is terminated.
atmospheric consistometer. Once conditioned and a low temperature retarder (LTR). In this
and stable at case, the GMR was not of sufficient quantity or
type to prevent gas influx.
temperature for 20 minutes, the slurry was
transferred into a pre-heated cell jacket (of
same temperature). As described in the Basic testing criteria for this slurry used a
equipment section, a pressure of 1,000 psi was BHCT of 138°F (58.9°C), an initial pressure
used to simulate the hydrostatic head. of 550 psi, a final pressure of 4,900 psi and a
Pressures of 500 psi and 300 psi, respectively, ramp rate of 40 minutes. All slurry preparation
were used to simulate high and low-pressure and conditioning was done according to API
zones. Although these pressures can be RP 10-B specifications.
altered to simulate actual well conditions, it
The Gas Model test was conducted first,
was found that these parameters provide a
using the same procedure discussed
standardized test procedure under a worse
previously. Figure 12 shows the results of this
case scenario. The slurry was then kept static
Gas Model test.
at temperature and pressure for the duration
of the test, normally 24 to 48 hours. The The SGS of the slurry was then tested as
parameters discussed above, along with the described in the equipment section of this
fluid loss, volume reduction and gas volume, paper with the temperature and pressure
were automatically monitored and recorded ratings listed for Slurry 2. In this case, the
for the duration of the test. The data was slurry was conditioned for 4 hours to
transferred to a computer where it was simulate total job time. After conditioning
plotted against time as seen in Figure 9. the motor was switched to SGS mode, as
The SGS of the slurry was then tested as described for Slurry 1. The results of this
described in the equipment section of this testing is shown in Figure 13.
work. The slurry was ramped up to pressure
Slurry 3: In this test, the authors investigated
and temperature while being sheared at 150
rpm (such as it would be in an HPHT the ability of a slurry that exhibits an extremely
thickening time test). After conditioning for 2 long transition time to control annular gas
hours, (which is the time to mix, pump and migration. This slurry consisted of a blend of
displace the slurry), the top-drive motor was Portland cement containing a GMR, DA and
turned off and the secondary motor was fluid loss additive (FLA). The fluid loss of
activated and attached to the strain gauge to Slurry 3 was controlled to less than 50 cc's/
initiate SGS testing. A lanyard attached the 30 minutes. The combination of the low fluid
strain gauge to the paddle, which pulled it loss to control volume reduction and the GMR
through a rotation of 0.26 °/min. The force to reduce the matrix permeability of the
required for that rotation was then monitored slurry during hydration, has been shown to
through the data acquisition system and aid in preventing gas migration.
plotted on a chart recorder. As mentioned
previously, the time from 100 lbf/100 sq ft (48 The test criterion used for Slurry 3 was
Pa) to 500 lbf/100 sq ft (240 Pa) is the measure identical to that used for Slurry 2.
of transition time. Figure 10 exhibits the
results of this test. The Gas Model was conditioned and run similar
to those tests previously mentioned for Slurry 1
This fmal test of the slurry was a and 2. The result of the gas model for this
thickening time determination on a slurry is shown in Figure 14.
conventional HTHP consistometer to record
its set profile. The same pressure and The SGS or transition time was run using the
temperature parameters were also used for procedure described previously in this work.
this test. The consistency of the slurry was Job time for this specific design was 3 hours
measured and the test stopped when it prior to starting the SGS test. The result for
reached 70 Bc. The results of this testing can this test is shown in Figure 15.
be seen in Figure 11.
Slurry 4: The fmal slurry design was chosen to
Slurry 2: Represents a multi-functional slurry
exhibit the typical misconception that SGS
design that exhibits a satisfactory transition development (transition time) and a "right-
time, yet allows gas intrusion when tested on angle-set" demonstrated on the conventional
the Gas Model. This slurry is similar to Slurry HPHT consistometer are related. In this
1, with the addition of Potassium Salt (KCL) example the slurry used is known as a liquid
storable cement (LSC) system. Although
8 SPE 90829
initially developed for use in remote locations, from 40 Bc to 70 Bc. This set profile would be
its unique properties have established a considered a 'right angle set'.
broader market in many parts of the world.
For some specific jobs, a long transition time The slurry provided a pass scenario for all
is the main requirement requested by the three catergories evaluated. Although, this
operator. The composition of this slurry was a may be desirable it is not always practical
mixture of Portland cement, a combination of considering the varability and quality issue
silica flour (325 mesh) and sand (100 mesh), with the numerous cements on the market. It
cement plasticizer, retarder, FLA, anti settling is important not to dismiss a specific design
agent and an intensifier, for activation. that has a long transition time, if the slurry is
still capable of passing a gas flow test.
For this application the slurry was ramped to
a BHCT of 180°F (82°C) in 1 hour at an initial Figure 13 of slurry 2 demonstrate an excellent
pressure of 700 psi and a fmal pressure of transition time of 33 minutes from 100 lbf/100
7700 psi. The slurry temperature was held sq ft (48 Pa) to 500 lbf/100 sq ft (240 Pa).
constant for 1 hour to simulate job time. After Although the transition time exhibited by
this period the slurry was ramped to BHST of slurry 2 is considered satisfactory to prevent
222°F (105.5°C) over a 3 hour period. This is fluid or gas intrusion, it can be observed in
following guidelines established by the figure 12 that the slurry exhibited gas
operator to simulate actual job conditions. migration 71/2 hours into the gas flow test. It
also should be noted that the slurry design
Since this is a special slurry design it is exhibited less than 40 cc's fluid loss in the
not mixed in accordance with API standard fluid loss cell. In the gas model more
procedure. A standard laboratory procedure than 85 cc's of filtrate was produced for the
has been established to provide mixing duration to the test. The last 20 cc's of
instructions that more closely simulate field filtrate was made during the onset of
applications. This procedure has been used hydration, which has been observed in many
successfully, to mix and store LSC, for over 8 failed tests over the years. A possible
years. The thickening time profile is shown in explanation for this is that the rapid volume
figure 16. reduction caused by increased permeability
during initial hydration allowing gas influx
The transition time was conducted using the into the matrix of the slurry.
procedure established earlier in this work. A
condition time of 2 hours was used prior to Slurry 3 is a classic case of a gas flow test
initiating the SGS mode. The result of this test that passes (figure 14) and a transition time
is shown in figure 17. that fails (figure 15).. The slurry pore
pressure drop started at approximately 41/2
Discussion
hours into the test, and continued for 10
As noted in figure 9 for slurry 1, the hydration hours before stabilizing. The transition time
of the slurry began to occur about 4 hours into chart demonstrates what is considered to be a
the gas model test. At this time the filtrate very slow gel strength development. Basically
production leveled out at approximately 40 it took 4:19 hours to go from 100 lbf/100 sq ft
cc's. The pore pressure of the cement slurry (48 Pa) to 500 lbf/100 sq ft (240 Pa).
continued to drop for 7 hours after the initial
pressure drop was noted. No influx of gas was Slurry 4 was a special case in which it was
recorded during this 24-hour evaluation. necessary to design a slurry to provide an
extremely long transition time. This was
Figure 10 of slurry 1 exhibits the transition time accomplished by use of a special LSC system.
of this slurry design.. The SGS development Figure 17 shows the results of the transition
from 100 lbf/100 sq ft (48 Pa) to 500 lbf/100 sq time or SGS test. It can be noted that the slurry
ft (240 Pa) was 47 minutes. Although at the obtained 100 lbf/100 sq ft (48 Pa) within 30
upper limits of what would normally be minutes after switching to the SGS mode.
considered acctable by the authors, this However, it took nearly 24 hours to reach 500
design provided satisfactory SGS results. The lbf/100 sq ft (240 Pa). This slow gel
last figure 11 is a scanned image of the development would not have been
thickening time chart for slurry 1. The slurry anticipated under accepted ideaology, given
exhibited a thickening time of 3:30 hours. For the right angle set exhibited in
the first 2 1/2 hours of the test the slurry
exhibited a consistency of 10 Bc. Once it began
to set it took approximately 15 minutes to go
9 SPE 90829
Flowmeter
-—
lifgh Pressure 500 psi Transducer
0- Nitrogen
Zone
Supply w
i i a0
Cement
Pore
Pressure
sJ.r,
Control Panel
DataCement
Storage
Graphical
__-11. Display
Slurry
Multi-tasking
Screen
Transducer
300 psi
300 psi Back
Low Pressure
Nitrogen Pressure
Zone Supply
-— Direct to Excel
Spreedsheet
13 SPE 90829
1000______________________________________________________________________________________ 1,1
100— 1000 au
10.0 lloo
Osof
.
1 .----.0
`
14.0170e
I MO Filtrate ------
FiltrUte -
1.0
r t:
·.•
a ' Gas. Flaw
V 'D TO
,
o
v
r
Bo
—I
ZOO
A
0 • O e
. 1 —
• ' 4— Pore Pressure . :
Water . 2
2 ..____
/
Displaced 40 1 At —
— by Filtrate
II, Pore P
-
essure
. . - - - - - - - . of
1911
.
—
SO '
20 s ,
14 SPE 90829
500 lbf/100 sq ft
100 lbf/100
Slurry 3 (Pass)
19 SPE 90829
---1
1 i I1
I 1 I.
4
kC) C
111111111111111
III
l
sq ft
1111111111N
.Mma.
•
111111111 ••
Immo.
111111111111
·
••
MIL