Professional Documents
Culture Documents
I. History: Steel Truss - Made of Individual Members With Equal Counteracting Tensile and Compressive Forces, Its
I. History: Steel Truss - Made of Individual Members With Equal Counteracting Tensile and Compressive Forces, Its
I. HISTORY
The worlds first cast iron bridge was built at Coalbrookdale, Telford in 1779. It is still in use today
carrying occasional light transport and pedestrians. Until 1840, the construction material used was
either cast iron or wrought iron or a combination of both. In the early 1800s cast iron was beginning to
be replaced by wrought iron and many of the early railway bridges were built of riveted wrought iron
construction. It was not until the late 1800s that steel began to replace wrought iron and by the early
1900s wrought iron was no longer available, as worldwide, steel makers had moved to producing carbon
steel, a much more reliable material.
Steel Truss – Made of individual members with equal counteracting tensile and compressive forces, its
purpose is designed to behave as a single object which carries/supports a load over a span. Truss, a
structure of connected elements usually forming triangular units. Within the truss structure itself
interior members further support the loads through axial tension and compression resistance. Trusses
have been used in a similar way to beams in composite decks (Oresund Approach Spans), as arches
(Sydney Harbour Bridge), as cantilevers (Forth Rail Bridge) or as stiffening girders to suspension bridges
(Forth Road Bridge). Today, the truss girder form of construction usually proves expensive to fabricate
because of the large amount of labour-intensive work in building up the members and making the
connections, so they are seldom used for ordinary highway bridges. However, for through or half-
through forms, truss bridges do offer a very stiff, lightweight solutions with minimum structural depth.
Hence, they are widely used in the UK for footbridges, demountable bridges (Bailey bridges), gantries
and longer span railway bridges (over 50m).
Steel Girder – Steel girders are a type of steel beams. Girders are collector beams, they are the main
horizontal supports of a structure which support the smaller beams. So “all girders are beams but all
beams are not girders”. Steel girders and beams differ from each other in various aspects. Essentially, a
beam and a girder have the same function. Girders have an I-shaped cross section or they can be box-
shaped or Z-shaped. The main function of a steel girder is to transfer the load to the columns on which it
rests. A steel beam transfers load to the steel girder. This is another key distinguishing factor between a
steel girder and a steel beam. Girders are often used for constructing bridges.
Steel Bridge – Steel bridges are widely used around the world in different structural forms with different
span length, such as highway bridges, railway bridges, and footbridges. The main advantages of
structural steel over other construction materials are its strength, ductility, easy fabrication, and rapid
construction. It has a much higher strength in both tension and compression than concrete, and
relatively good strength to cost ratio and stiffness to weight ratio. Steel is a versatile and effective
material that provides efficient and sustainable solutions for bridge construction, particularly for long
span bridges or bridges requiring enhanced seismic performance.
Temporary Bridges: As an alternative to costly detours, maintenance of traffic, and increased traffic
volume, prefabricated steel bridges are utilized to divert traffic during bridge repair, rehabilitation,
construction, or replacement. These bridges are installed as a temporary structure during construction
and then disassembled and stored until used again as a temporary structure.
Emergency Bridges: also are needed from a security standpoint, and due to man-made non-terrorist
hazards like ship impact, truck impact, fire, and blast. Natural disasters such as hurricanes, mudslides,
fires, and tornados can destroy a bridge by washout or collapse. Typical prefabricated bridges can be
erected much faster than the time of constructing a cast-in-place structure. Moreover, with the
increased threat to our nation's infrastructure due to terrorism, these systems could be utilized in a time
of national emergency.
Permanent Bridges: A permanent structure requires a design service life of 75 years in accordance with
the AASHTO LRFD Bridge Design Specifications, third edition (2004). A major objective of this study is to
provide recommendations that will increase the use of prefabricated steel bridges as permanent
bridges.
Achieving these objectives will reduce costs, reduce the construction period, enhance quality and
increase the safety of the work.
The activities for the steelwork contractor include planning, ordering, modelling, fabricating,
assembling, coating and erecting.
PLANNING
Two basic approaches to design and construction:
• Traditional approach – the Designer makes the structural choices and the Steelwork Contractor
builds to the drawings
• Early contractor involvement (ECI) – The Designer and Steelwork Contractor liaise at an early
stage to optimize the construction process
Constraints
The site can have a considerable influence on the structural form and how it can be erected. Particular
factors include:
• Location of the structure
• Constraints of the site
• Access
• Phasing of the erection
• Availability and size of erection plant
• Requirements for rapid installation, e.g. during possession
• Working over or adjacent to water
ORDERING
The most economical way to procure plate and section is from the mills in sizes to suit the project.
Stockholders charge much more per tonne and the use of stock sizes will require additional butt welds
and more waste. It is important therefore that the provision of the information for material ordering is
timed to suit the lead times required by the mills. The information that the steelwork contractor needs
to prepare orders is as follows:
Geometry
-Plan layout
-Levels at bearings
-Final profile of top flange
-Haunch definition (if any)
-Dead load precamber – total and breakdown
-Camber tolerance (if any)
-Web to flange weld sizes (for shrinkage and camber)
-Orientation of splices and girder ends
Make-up
-Plate and section dimensions
-bolts – quantity, type, diameter, plating
-Shear stud – quantity, length, diameter
Specification
-Steel grade for different thicknesses of plate and sections
-Restrictions on butt weld positions (if any)
-Options on geometric tolerances (see GN 5.03), surface quality, testing, CEV etc (if any)
Assembly
The ability of a steelwork contractor to use his automated equipment to fabricate steelwork can
greatly reduce fabrication costs and improve the quality of the finished product. This is probably
most important in the assembly of flat plates into fabricated components.
On particularly complex fabrications, a designer is very unlikely to produce the most cost
effective detail without the input of the steelwork contractor who will be carrying out the work.
It is useful to bear in mind that different steelwork contractors have different equipment, and
therefore different capabilities.
Some steelwork contractors have T & I machines which are used to assemble flat plates into ‘T’
sections and then ‘I’ sections. These machines will have limits on girder length, height, width,
weight, curvature (in plan and elevation) and haunching which can be accommodated, which
will differ between steelwork contractors. The larger machines can produce girders up to 4 m
deep and 1.5 m wide. Welds can be built up in multiple passes through the machine but short
lengths of built-up weld have to be done by hand.
As mentioned above, the more suited a structure is to automated assembly, the more cost-
effective its fabrication will be. Designing beams as ‘I’ girders rather than box girders will make
them more suited to automated assembly. Typically, an ‘I’ girder will involve 85% automated
assembly, with only the stiffening being carried out manually (unless robot technology is used).
An open top box will involve 70% automated assembly, with automated welds between the
webs and the top flanges, welding of the stiffeners to the webs and bottom flanges to formed
stiffened plates by robot, and with welding of the bottom flange to the webs being carried out
manually. A closed top box will involve 35% automated profiling and marking of plates only, and
all other fabrication (box assembly and stiffening) being carried out manually.
Welding
Section stiffening
https://youtu.be/HrHjagdZ9Zw
TRANSPORTATION
To maximize the amount of work carried out within the fabrication works, thus achieving the highest
quality, the steel structure is fabricated in pieces as large as can reasonably be transported to site. The
designer should anticipate how the structure will be split into separate components for delivery to site,
particularly in considering member sizes and splice positions.
Access to the site and positioning of the erection plant has to be planned and sequenced to ensure that
disruption to adjacent services / infrastructure is minimized. Access onto site has to be coordinated with
the traffic management scheme to ensure that craneage and steelwork can be brought onto site and
mobilized with minimum disruption.
BRIDGE ERECTION
Methods of erecting steel bridge structures vary considerably from site to site and from project to
project. The subject of erection aspects is therefore a wide and varied subject. This section focuses on
the aspects that should be considered during the initial design and detailed design phases.
- Installation of bearings
The first pieces of steelwork to be erected on site are the bridge bearings. The function
of a bearing is to transfer weight of the superstructure to the substructure. They may
also transfer transverse and longitudinal forces. They carry large forces but can be easily
damaged by inappropriate handling or installation.
Bearings can be supplied attached to the girders but it is more common for them to be
aligned and levelled on the substructure and attached to the girders afterwards. The
designer needs to give clear instructions about line, level and setting of bearings to
ensure that they function as intended in service.
The designer must allow for safe access for precise installation of bearings. The means
of access may need to be retained for maintenance and replacement of bearings.
- Specialist Transport
Where lifting into position is not suitable, for example when there is a lack of space for a
crane or there are overhead cables in the vicinity, one option is to assemble steelwork
at low level away from (but close to) the actual bridge site. The assembled steelwork is
then jacked up to allow specialist transportation units beneath the deck. The units are
then used to transport the deck into position.
Preassembly away from the site also allows the client to continue with the construction
of the bridge piers and abutments for example without disrupting the assembly of the
steel.
- Launching
Launching the steelwork over road or river, involves assembly of steelwork, typically
behind an abutment, on the highway approach. The steelwork is assembled on low
resistance rollers or a sliding system at each pier or temporary support. A haulage and
restraint system is used. The steelwork requires plenty of construction alignment to
ensure adequate fit up prior to launching and needs to have sufficient time in the
programme to allow for this. However, assembly is normally near ground level, with the
use of much smaller and less expensive cranes and minimum work at height.
Working within any form of possession, requires careful and precise planning. Often the
cost penalty of over running can be extreme for both parties. If this is the case, it may be
beneficial for most of the structure to be pre assembled prior to erection. Then the
whole bridge can be lifted into place using a large crane positioned adjacent to the site.
The most common way to improve stability is to assemble girders into braced pairs
which makes them more stable during lifting and when in place compared to a single
girder.
Ideally, designers should make use of any temporary bracing for performance in service
and thus make it permanent. Generally, making bracing permanent is more economic
and avoids hazards of its removal.
DECK CONSTRUCTION
Pre assembly for composite construction can be used to fit critical falsework and formwork, temporary
and permanent walkways and edge protection, before lifting the bridge section into place. The
advantage of this is two-fold. The formwork can be fitted at low level, which is inherently safer, and it
also eliminates this operation from the critical path. The formwork would otherwise be fitted after
completion of the erection.
Falsework systems such as that shown above have been developed such that they can be attached and
removed without any significant risk of damage to protective treatment (or contamination of the
surface of weathering steel). This eliminates the need for subsequent surface treatment, saving time
and costs.
Falsework - defined as any temporary construction used to support vertical loads for a structure until it
becomes self-supporting.
Formwork - temporary structure or mold used to retain plastic or fluid concrete in its designated shape
until it hardens.
https://www.youtube.com/watch?v=sA2vWMOc5Sw
VIII. EXAMPLES