Request For Inspection Yuil

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 6

MARITIME INFRASTRUCTURE ESTABLISHMENT PROJECT 2 (MIEP 2)

REQUEST FOR INSPECTION

RFI Date : 27. 12. 2019


Request Inspection Date : 27. 12. 2019 Onshore Works RFI No. : YUIL/MIEP2/TK 301-001
Work Decipline Civil X Building Mechanical Electrical Instruction Others
Work Area : TK 301
INSPECTION Hold
No. DESCRIPTION DWG/SPEC REF. REMARKS
TIME Point
C-220_rev.B_GASOLINE STORAGE TANK (TK-
1 FOR LEAN CONCRETE 301) FOUNDATION PLAN & SECTION

Engineer Comments :

Date Name Signature

Requested by Contractor

Approved by Consultant
FIELD INTER FACE CLEARANCE
INSPECTION BEFORE PLACING OF CONCRETE

RFI NO. : YUIL/MIEP2/ TK_301_001

PROJECT NAME : MIEP 2 DATE : 20/Nov/2019

DWG NO. : C-220 REV. NO. : B

AREA / LOCATION : ONSHORE TK_301 SUB CONTRACTOR : YUIL

SIGNATURE
Inspection Check(V)
Date Checked REMARKS
Item Approved by Applicable Rating

( ) GOOD
Rebar Work none none
( ) POOR

( ) GOOD
Form Work
( ) POOR

( ) GOOD
Clean Out
( ) POOR

( ) GOOD

( ) POOR

( ) GOOD

( ) POOR

( ) GOOD

( ) POOR

( ) GOOD

( ) POOR

( ) GOOD

( ) POOR

Remarks

WITNESSED BY DATE NAME, SIGNATURE

Requested by Contractor

Approved by Consultant
FIELD TEST / INSPECTION REPORT
CONCRETE POURING PERMIT

RFI NO. : YUIL/MIEP2/TK_301-001

PROJECT NAME : MIEP 2 DATE : 20/Nov/2019

DWG NO. : C-220 REV. NO. : B

AREA / LOCATION : ONSHORE TK_301 LEAN CONCRETE SUB CONTRACTOR YUIL

1 AREA GASOLINE STORAGE TANK (TK-301)

2 LOCATION OF POUR TK_301 LEAN CONCRETE

3 DATE OF POUR 02/Nov/2019

4 VOLUME OF CONCRETE 20,00 ㎥ ( 12,25 by DWG )

5 MIXING PROCESS - SITE MIXING - TRANSIT - OTHERS

6 CONCRETE SPECIFICATION STRENGTH REQUIRED 18 MPA

SLUMP REQUIRED

TEMPERATURE REQ'D

8 COMMENTS

TIME START 12H00mm

GRADE OF CONCRET18MPA

TIME FINISH 19H30mm

Remarks

WITNESSED BY DATE NAME, SIGNATURE

Requested by Contractor

Approved by Consultant
GENERAL CHECK FORMAT

RFI NO. : YUIL/MIEP2/FT_501-001

PROJECT NAME : MIEP 2 DATE : 08/11/2019 & …../….../2019

DWG NO. : MIEP2_C-230_(FT-501) FOUNDATION PLAN & SECTION REV. NO. :

AREA / LOCATION : ONSHORE FT_501 SUB CONTRACTOR YUIL

Remarks

WITNESSED BY DATE NAME, SIGNATURE

Requested by Contractor

Approved by Consultant
SUB-PREPARATION FORMS

PASSED FAILED PASSED FAILED P

SUB-PREPARATION FORMS

PASSED FAILED PASSED


A-BOLT /
FORMS RE-BAR
EMBEDDED STEEL

PASSED FAILED PASSED FAILED PASSED FAILED

FORMS RE-BAR ACCESSORY

FAILED PASSED FAILED PASSED FAILED