Test Questions: Please Describe The DBS3900 Equipment (Hardware Configuration, Board Position, Cable Connections)
Test Questions: Please Describe The DBS3900 Equipment (Hardware Configuration, Board Position, Cable Connections)
CMPT
-FE electric
-FE optic
-E1
HECM
4. Please fill in which can be the power input for one BBU
…….. .?How many amperes we need for one RRU?
Trebuie sa explice ceea ce le-a excplicat alex la training, in legatura cu pozitia RRU-
urilor, pe pilon, la baza pilonului sau pe shelter. Se va preciza si conexiunea pana la RRU,
adica daca se vor pastra feederii existenti sau se vor folosi jumperi pana la combiner si
de la combiner la antene.
220V sau 380V, and the alarms are connected on MON1 and
MON0
Yes, we do have AC power inside APM.
We use DCDU when we install BBU in 19 inch rack and the DCDU
provides -48V.
450Mhz is 450.A and 410Mhz is 450.D or 450.L (este diferentiat prin sub-
banda)
13. How
many external alarms can be provided by one BBU?
Which are the names of the ports?
14. Which
is the role of each RRU RF port? How many inputs
and outputs have one combiner?
TX/RX - main
RX – diversity
4 inputs, 2 outputs
15. TheVSWR alarm appears on transmission or reception
side? What about RSSI value?
16. If
on co-transmission the link from switch to the first BBU
will come on FE0 port, which will be the transmission
port for the second BBU?
FE1
17. If
the transmissions are on E1 we’ll use co-transmission
anymore?
NO
19. Please
specify the user name and password for Telnet or
FTP connection to BBU.
System
System
IP:172.16.16.16
SNM:255.255.255.0
21. OMC
engineer informs you that on sector A you have
VSWR alarm, which are the steps in solving this issue?
Verify the connectors and then verify the jumper.
22. OMCengineer informs you that the second BBU can’t be
reached, which will be your local verifications to clarify
the position of this issue in the network transmissions?
First you need to ping the first BBU and then you should ping the gateway.