Professional Documents
Culture Documents
China Steel Corporation India Private Limited: (CSCI)
China Steel Corporation India Private Limited: (CSCI)
(CSCI)
Technical Specification
For
1 Introduction .............................................................................................. 4
1.1 General .................................................................................................... 4
1.2 Noise ....................................................................................................... 6
1.3 Fire Protection......................................................................................... 6
1.4 Environmental Conditions ...................................................................... 6
1.5 Interfaces ................................................................................................. 7
1.6 Drawings Sheet size and format ............................................................. 7
1.7 Progress Photographs Record................................................................. 8
1.8 List of Responsibilities (L.O.R.) ............................................................. 8
2 Progress of the work................................................................................. 17
3 Scope of work.......................................................................................... 19
3.1 Civil & Structure, Building, Cable Route Design for Main Substation 19
3.2 Main Substation .................................................................................... 20
3.3 Engineering Design............................................................................... 21
3.4 Installation............................................................................................. 24
3.5 Training ................................................................................................. 26
3.6 Temporary site office on Main Substation............................................ 27
4 Specification of Technical Supply ......................................................... 29
4.1 Utility Power Supply............................................................................. 29
4.2 General Equipment Requirements........................................................ 29
4.3 220kV Gas Insulated Switchgear (GIS)............................................... 30
4.4 33kV Gas Insulated Switchgear (GIS)................................................... 84
4.5 11kV Gas Insulated Switchgear (GIS)……………………………..... .105
4.6 11kV Power Factor and Harmonic Improvement Equipment.............. 126
4.7 220kV/33kV 60/80MVA Main Power Transformer ........................... 135
4.8 33kV/11kV 32/40MVA Power Transformer....................................... 162
4.9 11kV/415V 1.6MVA Power Transformer…….. ..................................186
4.10 Distribution Power Transformer ...........................................................210
4.11 RING MAIN UNIT (RMU) .................................................................213
4.12 415 Volt Metal-Enclosed Switchgear ..................................................218
4.13 Charger & Battery & DC Panel ...........................................................228
1.1.6 The general arrangement and all details of the AC power supply to be
supplied for CSCI Engineering Department approval.
1.1.8 The Contractor shall take full responsibility to get certificate and
approval of India Power Company and governmental organization in
India and design to meet the operation of this project.
1.1.17 Safety
This Specification listed is only a general guide. Personal protection
and safety of equipment shall be the first priority in every aspect of
Bidder’s design.
The Contractor shall comply with all India local applicable safety
rules existing at the time of construction of this project.
The import tax and any other essential tax will not be included in the
contract price, but the contractor shall make application of the
abovementioned tax and apply the free of tax for CSCI Engineering
Department.
1.2 Noise
The noise level from any equipment covered by this Specification shall
be tested per ANSI or IEC standards and shall not exceed the desirable
sound levels as defined by the Government organization in India. Other
relevant factors covered by the Government organization in India
requirements, affecting persons exposed to noise from the equipment
covered by this Specification, shall apply.
1.5.1.2 The Contractor shall provide and confirm all necessary E&M input
requirement to the CSD/SEM during package/construction Contractor
design and construction.
1.5.1.3 The Contractor shall provide and confirm all necessary E&M input
requirement to the CSD/SEM during ACL Utility Contractor design and
construct the utility between Main Substation and ACL Secondary
Substation.
1.5.1.4 The Contractor shall provide and confirm all necessary E&M and Civil
designs during Civil Contractor construction.
1.5.2.1 Provide two independent sets of voltage (PT) and current (CT)
transformers for IPC MOF. The PT and CT Specification shall fully
comply with IPC requirements for revenue metering. IPC will
witness testing of the PT and CT before and after they are installed in
the respective switchgears. The Contractor shall also provide
enclosures for the MOF equipment which will be furnished by IPC.
1.7.1 During the period of this contract, the Contractor shall comply with
instruction of CSCI Engineering Department and record the
construction progress in pictures (include slide and color pictures) and
DVD Compact Disc every month. The Contractor shall make the DVD
for construction process of this contract at least 20 minutes cinema.
1.7.2 The Contractor shall make the DVD for record the progress of
manufacture, installation, construction methods, important operation
and detection of major equipments at least one hour cinema.
1.7.4 CSCI Engineering Department has the copyright to possess all of the
pictures and DVD albums (include master films) provided by the
Contractor. Those pictures and DVD shall be made by professional
company and approved by CSCI Engineering Department.
1.7.5 The Contractor shall provide three copies for above mentioned pictures
and DVDs, at least thirty (30) of the pictures shall be enlarged to the
size required by CSCI Engineering Department and provide more
copies if necessary.
The scope of supply shall be shared between the above mentioned parties as
detailed on the table of the LOR (list of responsibilities).
2.3.4 Provide the following information for each drawing in the drawing list
within three (3) months after contract signed:
2.3.5 All preliminary drawings, which are sent back from the site for revision,
shall be returned to the site by the Contractor within fourteen (14) days
after date of issuance from the site. CSCI Engineering Department will
notify the Contractor of the date of issuance from the site.
3.1.2 Design drawings shall show the location of fixed floor plates, anchor
bolts, embedded steel, trenches, opening, access stairs, and the like.
3.1.4 Detail design shall include, but not limited to, the following drawings:
3.1.5 Design drainage, sanitary sewer and industrial waste within the battery
limit.
3.1.6 The Contractor shall design the fence install and furnish around the
Main Substation for safety and security.
3.1.7 Furnish anchor bolt drawings, including bolt location, detail and
projection for all equipment and facilities supplied by the Contractor.
3.2.1 The following summary of the main parts of this project shall serve as
outline of the scope of supplies. Bidder is requested to detail and
complete this Specification as far as possible and to provide
all information such as technical data, weights, sizes, dimensions, etc.
3.2.2 The Contractor shall provide complete design/facilities from the India
Power Company to CSCI Engineering Department Main Substations
(M/S) at 220kV, 3 phases, 50Hz. At the Main substation, it will be
stepped down to nominal 33 KV level and nominal 11 kV level.
3.2.3 The complete design for Main Substation including the electrical,
Mechanical and civil engineering etc. shall be in the supply scope of this
Contract and fully compliance with India Government rules and
regulations.
3.2.3 Design and furnish single line diagram showing the 220kV, 33kV,
11kV and 415V systems. The number of circuit breakers as well as
their ratings provided by the Contractor shall be indicated. A power
system of CSCI Engineering Department shown as appendix one (1) is
for the Contractor to develop the detail drawings.
3.2.5 Design and furnish receptacles of explosion proof (heavy duty) for
welding machines, driller, and general service system.
3.2.6 Design and furnish EOT crane for 220kV GIS maintenance.
3.2.8 Main Substation equipments are listed as, but not limited to, the
following.
3.3.1 The following summary of the main parts of this project shall serve as
outline of the scope of supplies. Bidder is requested to detail and
complete this Specification as far as possible and to provide
all information such as technical data, weights, sizes, dimensions, etc.
3.3.2 The Contractor shall provide complete design from Main Substation to
ACL Secondary Substation at 11kV, 3 phases, 50Hz. The ACL
secondary substation shall convert the 11 kV power to a 415V nominal
level for ACL loads.
3.3.3 The complete design for ACL Secondary Substation including the
electrical, Mechanical etc. shall be in the supply scope of this Contract
and fully compliance with India Government rules and regulations.
3.3.4 The pipe-rack between Main Substation (M/S) and ACL Secondary
Substation (ACL S/S) will be designed and supplied by ACL Utility
Contractor
3.3.5 Design and furnish single line diagram showing the 11kV and 415V
systems. The number of circuit breakers as well as their ratings
provided by the Contractor shall be indicated. A power system of
CSCI Engineering Department shown as appendix one (1) is for the
Contractor to develop the detail drawings.
3.4.2 The Contractor shall take full responsibility for the system, equipment
and construction engineering design. Studies and calculations shall be
performed to substantiate the equipment selection and system
configuration. The Control and Power Cables (Including wires) for all
cubicles or devices shall have wire (cable) marks.
3.4.4 Engineering design and finish listed as, but not limited to, the
following shall be certified by Professional Competent Personnel and
get approval from governmental organization in India.
3.4.7 Detail design for electrical, instrumentation and control works are listed
as, but not limited to, the following. The relative drawings and
documents including the items in Section 3.2.8 and 3.4.4 shall be
submitted.
3.4.10 Furnish with proposal outline drawings of control panels, local panels
and equipment arrangement drawings of electrical equipment.
3.4.11.1 The cable route shall be provided for distribution substation 22kV
power cables and for utility cables (communication, fire fighting,
office/process computer backbone, Utility Dispatched system,
CCTV, guard security and etc.). Additional 50% of in used
quantity shall be provided for spare.
3.4.11.3 The aluminum conduit shall be used for underground and exposed
installation. The PVC conduit can’t be used in exposed area.
3.4.11.6 The most top layer of Cable trays run outdoors shall be protected
with cover.
3.4.11.7 For conduits in cable duct bank, PVC conduits shall be used for
power cables and galvanized steel conduits shall be used for
control cables. The spare quantity shall be 50% of in used
quantity.
3.5 Installation
3.5.1 The Contractor shall furnish all labor, facilities, instruments, materials
and equipment and perform all operations in connection with the
unloading, hauling, storing, handling, installing and testing of all
materials and equipment furnished by the Contractor under these
Specifications.
3.5.2 The Contractor shall submit the detailed method and procedure of
transportation, erection, testing and installation schedule for the
materials and equipment furnished under these Specifications.
Installation work shall be performed according to the approved
schedule and the test work shall not be performed without the presence
of CSCI Engineering Department, all work shall be performed in
strict accordance with these Specifications as well as the
manufacturer's detail design drawings, method and procedure of
erection and testing approved by CSCI Engineering Department. The
Contractor shall be fully responsible for all materials and equipment
furnished and installed by him until final acceptance.
3.5.4 The Contractor may use any special erection equipment, appliance and
test facilities furnished with the equipment for erection purpose, but
shall not use tools furnished for maintenance purpose until specifically
permitted by CSCI Engineering Department. Tools furnished by the
Contractor for maintenance purpose shall be transferred to CSCI
Engineering Department in a brand new and unused condition.
3.5.5 All piping, conduits, cable trays and cable ways shall be installed in
harmony with all other work so that all the piping will be installed in
the most direct and workman like manner, and so that interference
between piping, ducts, equipment and architectural or structural
features will be avoided.
The Contractor shall remove all temporary facilities, tools, etc. and
clean the yards or areas satisfactory to CSCI Engineering Department.
3.5.7 Whole installation shall fulfill the Local Act and Regulation including
the wiring work.
3.5.8 The Contractor shall be responsible for the installation all the way until
it is perfectly finished. Those problems including any accident and
labor safety occurred due to the any related to this Installation and
the new control system should be blamed on and solved by the
Contractor without any extra charge to CSCI Engineering Department.
3.6 Project manager and engineer
3.6.1 The Contractor shall assign a site interface manager with at least 5 years
experiences in AC Power Supply System and a competent site engineer
with English communication ability for each defined interface during
3.7 Training
3.8.3 The Contractor shall be responsible for well-kept and clean site offices
all those items.
3.8.4 Other than item 3.8.2 shall also be prepared by the Contractor, such as
office computer, video/audio facilities with internet (equivalent in
remote design department for communication), furniture, coffee, tea,
refrigerator, telephone, fax, copy and etc.
4.1.1 Utility will be supplied from the India Power Company to Main
Substations (M/S) at 220kV, 3 phases, 50Hz. At the M/S, it will be
stepped down to nominal 33 KV level and nominal 11 kV level then
distributed to ACL Secondary Substations (ACL S/S). The ACL S/S
shall convert the 11 kV power to a 415V nominal level for ACL loads.
The Contractor shall confirm and coordinate with IPC for routing of the
220kV power supply to the overhead tower in the boundary limit of the
Main Substation. The interface of connection point with IPC power line
shall be coordinated and designed.
4.1.2 The Contractor shall file the required applications including finish
documentation and drawings to IPC for permanent power system of
this project.
4.1.3 Two 220kV (Short circuit capacity 3-phase 220kV 50Hz 40kA) main
incoming power feeder shall be supplied to China Steel Corporation
India Private Limited (CSCI Engineering Department ) Plant area.
4.1.5 The low voltage equipment shall be met a single feeder load center.
4.3.1 SCOPE
4.3.1.1 This section specifies the detailed requirements furnished by contractor
for the design, manufacture, assembly, testing, delivery, installation,
commissioning, supervision of the installation and guarantee of whole
220kV gas insulated switchgear equipment, local control cubicle(LCC)
with interlocking circuit,220kV single core, cross-linked polyethylene
insulated (XLPE), PVC jacketed power cable with sealing end and all
necessary accessories and mounting brackets between GIS and main
transformer, and between GIS and outdoor cables termination station
4.3.2 STANDARDS
4.3.2.1 Performance and test of all circuit breaker, disconnecting switch,
earthing switch, potential transformer, current transformer and surge
arrester covered under these specifications shall conform in all respects
to the latest revision of IEC, ANSI Standards (requirement of IPC)
and/or NEMA Standards, ICEA-NEMA S-66-524 "Cross-Linked
Thermosetting Polyethylene" insulated wire and cable for the
220
(2) LPT for 1- phase: KV / 115 − 66.4V See SLD
3
4.3.5.3 The quantities of 220kV cable, sealing ends are listed as follows:
Item Description Quantity
(4) Clearance of live parts to earth, live parts to live parts and isolating
clearances shall be selected taking into consideration the insulation
level of the switchgear specified above and the pressure of the
insulating gas.
4.3.6.2.4 Continuous Current Rating
The rated continuous current rating of all primary components shall be
B. Operation Counter
An operation counter shall be furnished to indicate the total number of
operations of the circuit breaker. The counter shall register on tripping
operation only, and shall remain in operative during the closing stroke
of the breaker.
C. Power Supply Switches
Separate molded case circuit breakers (MCCB) shall be provided in the
control panel for disconnection and protection of the convenience
outlet circuits.
4.3.7.2 Disconnecting Switch
4.3.7.2.1 Disconnecting switches shall be triple pole, single throw, electrically
and manually operated type.
4.3.7.2.2 The disconnecting switches shall be capable of making and breaking
the transformer magnetizing current and charging currents of the
switchgear primary components. They shall be fully interlocked with
the circuit breakers to ensure that they can only be operated when no
4.3.7.2.5 All live metal parts shall be mounted in a gas-tight earthed non-
magnetic metal cylindrical enclosure supported by epoxy resin
insulators and insulated by SF6 gas in a similar manner as other parts
of the system.
4.3.7.2.6 All disconnecting switches shall be of the axial or angular thrust design
with moving and fixed contacts arranged axial with the enclosure.
4.3.7.2.7 Each three-phase disconnecting switch shall be provided with its own
control gear and shall be rated 110V dc, if electrically operated type is
provided.
4.3.7.2.8 Extra auxiliary switches shall be provided for each operating
mechanism, in addition to the indications, controls and interlock
connections used. Each switch shall be provided with at least three (3)
normally open and three (3) normally closed contacts. Switch contacts
shall be rated at 110V dc and 10 A dc.
4.3.7.2.9 The position indicator to indicate the open and close position of the
disconnection switch shall be furnished.
4.3.7.3 Earthing Switches
115
115 − V
(2) Rated secondary voltage 3 115V-66.4V
(3) Rated tertiary voltage: 66.4V -
(4) Accuracy class ANSI 0.3Z ANSI 0.3Z
(5) Rated burden 25,50,150VAx3, 150VAx3 200VAx1
(6) Rated frequency 50Hz 50Hz
(7) Polarity Subtractive Subtractive
4.3.7.4.3 The potential transformers shall be able to withstand the following test
voltages:
(1) Primary side, low frequency (50 Hz), one-minute, dry. 460 kV, rms
(2) Primary side, impulse full wave (4.3.2 x 50 microsecond)1050kV Crest
(3) Secondary side (and tertiary) low frequency (50Hz),
One -minute, dry 2000V
4.3.7.4.4 Temperature rise
The limits of observable temperature rise in potential transformers and
hottest-spot conductor when tested in accordance with their ratings
shall be as follows:
Ambient Winding Temperature Rise Hottest-Spot
Temperature Winding Temperature Rise
30℃ 55℃ 65℃
55℃ 30℃ 40℃
4.3.7.4.5 The potential transformer shall be accommodated in metal enclosures
with SF6 gas insulation. The potential transformer compartments shall
be fully segregated from the primary compartments of the switchgear
by means of epoxy resin insulators. Damping resistor and/or circuit
shall be equipped to prevent any damage from surge voltage.
4.3.7.9.3 The sealing end enclosure directly connected to the switchgear shall be
of the type and size suitable for use with SF6 gas.
4.3.7.9.4 The Contractor shall have full responsibility to coordinate with the
cable manufacturer for effecting the connecting of the cable sealing end
to respective equipment easily and properly.
4.3.7.10 Steel Structure
The Contractor shall furnish all steel structure, which are necessary to
make sure that the equipment will withstand earthquake shocks
specified in this specification
4.3.7.11 Local control cubicle (LCC)
4.3.7.11.1 A metal enclosed floor mounted type control and supervise panel shall
be furnished and mounted adjacent to GIS equipment. Each three-phase
bay shall be controllable at each local control cubicle during emergency.
4.3.7.11.2 The control panel shall contain the necessary valves, pipe-work,
pressure gauges, interlocks and operating devices, mimic diagram,
local/control switches, local/remote control selector switches,
indicating devices and other accessories per each bay to permit opening
and closing the breakers, disconnecting switches and earthing switches
locally. Provisions shall be made for locking the panel doors with
individual key and also provide an extra master key.
4.3.1.11.3 The control panel shall have blank removable floor plates with
sufficient room for conduits to permit entrance of the control circuits.
There shall be 50 cm space above the floor plates to allow all control
wiring to be brought into the panel.
4.3.7.11.4 Each control panel shall be provided with a fluorescent light inside for
interior lighting, and shall be provided with a door switch. Each panel
shall also be provided with an AC 240-volt, 15-ampere, 2-pole, 3-wire
grounding type duplex receptacle. The receptacle shall be wired to
4.3.7.11.5 All control panels shall have to withstand corrosive and epoxy painted;
the finished color shall be RAL7032 or contractor’s standard approved
by CSCI Engineering Department.
4.3.7.11.6 Each control circuit shall be terminated on terminal blocks. All
terminal blocks shall be of the screw on or cage clamp type. At least
fifteen percent (15%) of terminals shall be provided as spare. All
connecting wires from the GIS equipment for remote control shall be
terminated in the control panel. All control wiring shall be 2.0 mm2
except 5.5 mm2 for current transformer or larger with tinned stranded
copper.
4.3.7.11.7 The control panel shall be provided with facilities for connecting with
remote controls and indications. Twenty (20) single-pole
interchangeable normally open and normally close auxiliary switches
or at least ten (10) fixed normally open and ten (10) fixed normally
close dry contacts per each of circuit breakers, disconnecting switches
and earthing switches shall be provided. The auxiliary contact rating
shall be not less than 110V 10 A dc. One (1) set of indicating device,
with audible alarm and manually reset, to supervise the actual operating
or fault condition of the operating mechanism driven system, shall also
be supplied for remote annunciation on main switch board panel as
well as main substation. The device shall be for semi-flush mounting
and suitable for maximum 110V dc and 10A dc. Mimic diagram of the
related circuit including position-indicating lamps (red and green) to
indicate the open and closed positions of the circuit breaker and
operation-indicating lamps of the disconnecting switches and earthing
switches shall be mounted such that they will be plainly visible without
opening the control panel.
4.3.7.11.8 The local control cubicle (LCC) for each line, bus tie and transformer
bays shall accommodate the control devices and instruments of the GIS
including but not limited to the following devices:
4.3.7.15.3 SF6 gas sealing ends/terminations and outdoor type air sealing
ends/terminations.
Bushing and packing etc. for cable sealing end/termination directly
connected to GIS shall be of the type and the size suitable for use with
SF6 gas. The minimum operation pressure of SF6 gas will be
2.5kg/cm2. The Contractor shall fully coordinate with GIS, IPC and
power transformer suppliers for the terminal connection and mounting,
plug-in type is preferable in GIS side. Bushing and packing etc. for
cable sealing end/termination directly connected to the incoming
overhead transmission line shall be of outdoor type air sealing end and
the size suitable for use with 210 mm2 Dual ZTACIR transmission line
conductor. The Contractor shall fully coordinate with IPC for the
terminal connection and mounting.
mm 0.25/0.25
Min. thickness of semi-conducting XLPE
mm 2.0/2.0
9. Thickness of XLPE insulation mm 25.0/25.0
10. Insulation shielding
Min. thickness of semi-conducting mm 0.25/0.25
tape wrapping
Min. thickness of semi-conducting XLPE mm 2.0/2.0
14.3. Metallic shielding:
Min. diameter of wire mm 2.0/2.0
Number of wires - 80/80
12. Nominal thickness of PVC jacket mm 6.0/5.5
13. Max. continuous operating temperature
of conductor ℃ 90
14. Min. partial discharge extinction
level in 5 PC (Pico coulombs) kV 160
15. Guaranteed AC test voltage
on full length of completed cable kV/5 min 240
16. Guaranteed DC test voltage
(On full length of completed cable) kV/15 min 390
17. The min. creepage distance of the
bushing of oil-immersed sealing end mm 920
18. The characteristics of protective device:
(1) Min. operating voltage with
test current 1mA DC kV 4.5
(2) Max. residual voltage at
10kA, 8x20 microsecond wave. kV 11
(3) Min. surge capacity at 8x20
4.3.8.2 One set of SF6 leakage detector shall be furnished and hand over to
CSCI Engineering Department.
4.3.8.3 One set of Gas supply and recovery equipment including the recovery
gas cylinders used for installation and testing.
4.3.12.12 The instruction books shall be provided with complete instructions and
data for shipment, installation, operation, maintenance, and the
ordering of all parts for the circuit breaker, disconnecting switch,
earthing switch, potential transformer, current transformer, surge
arrester, and all accessories. All books shall be identified by he contract
and item numbers and the serial numbers of all circuit breakers,
disconnecting switches, earthing switches, potential transformers,
current transformers and surge arresters to which the books pertain.
Where there is variation between the circuit breaker, disconnecting
switch, earthing switch, potential transformer, current transformer and
surge arrester supplied under this specification, complete information
for each condition shall be provided. This information may be included
4.3.15 INSTALLATION
4.3.15.1 General for GIS
4.3.15.1.1 The Contractor shall furnish all labor, facilities, instruments, materials
and perform all operations in connection with the unloading, hauling,
storing, handling, installing and testing of all materials and equipment
furnished by the Contractor under these specifications.
4.3.15.1.2 The Contractor shall submit the detailed method and procedure of
transportation, erection and testing, and installation schedule, for the
materials and equipment furnished under these specifications.
Installation work shall be performed according to the approved
schedule and the test work shall not be performed without the presence
of CSCI Engineering Department, all work shall be performed in strict
accordance with these specifications as well as the manufacturer's
detail design drawings, method and procedure of erection and testing
approved by CSCI Engineering Department. The Contractor shall be
fully responsible for all materials and equipment furnished and
installed by him until final acceptance.
4.3.15.1.3 To supervise the work covered by these specifications, CSCI
Engineering Department will have field inspector. The Contractor shall
cooperate fully with these inspectors. The inspectors will supervise the
erection, testing, starting and initial operation of equipment. All
temporary bracing, ties, stays, supports and safety provisions for
erection operation, if considered necessary by the inspectors, shall be
4.3.15.1.6 The Contractor shall remove all temporary facilities, tools, etc. and
clean the yards or areas satisfactory to CSCI Engineering Department.
4.3.15.2 Installation of GIS equipment
4.3.15.2.1 The GIS equipment comprise 220kV power circuit breakers, bus-bars,
disconnecting switches, earthing switches, Lightning arrester, potential
transformers, current transformers etc. The Contractor shall assemble
and install the complete set GIS equipment in accordance with the
manufacturer's approval drawings, data and instructions and as directed
by manufacturer's Erection Engineer.
4.3.15.2.2 The installation work shall be done by Contractor or qualified local
electrical subcontractor approved by CSCI Engineering Department.
4.3.15.2.3 The Contractor shall assemble the necessary supporting structures on
the foundation, leveled and anchored, concrete grouting of the anchor
bolts, and then installs the equipment onto the supporting structures.
4.3.15.2.4 Inspection and necessary adjustment shall be made to ensure the
4.4.4.6.3 The enclosures shall be gas tight. In case of enclosure damage, gas
leakage shall not interfere with the adjacent compartment.
4.4.4.6.4 The enclosure shall be designed and constructed that the arc shall not
extend to the adjacent compartment when the internal faults occur.
4.4.4.6.5 The enclosure and seal shall be designed to withstand the gas pressure
4.4.4.8.3 The design of the spacer or insulator shall be such that it can withstand
all overpressures building up in the compartment in case of an internal
fault. No design will be accepted which allows the spacer or insulator
to give way under overpressure, thus communicating the overpressure
to compartments not at fault.
4.4.4.9 Supporting Structure
4.4.5.2 Rating
4.4.5.2.1 Rated frequency, Hertz 50
4.4.5.2.2 Voltage ratings
4.4.5.2.2.1 Rated voltage, kV, rms. 36
4.4.5.2.3 Current ratings
4.4.5.2.3.1 Rated continuous current, Amperes ,rms.as shown on Single Line diagrams
4.4.5.2.3.2 Rated short circuit current (at rated voltage),
Amperes 40,000
4.4.5.2.3.3 3-second short-time current carrying capability,
4.4.8.3 Connection
wye/wye neutral grounded / open delta as shown on Single Line
Diagram
4.4.9.4.3 All secondary tap leads of each current transformer shall be brought out
and connected to the low-voltage cabinet. All connections within the
cubicle shall be made with solderless connectors on suitable short-
circuiting type terminal block. Sufficient terminal shall be provided for
external connection.
4.4.10. Cable Termination
4.4.10.1 The outgoings of G.I.S are connected with power cables, the cable size
will be shown on the attached “Single-Line Diagram.” The cable
termination shall be provided and shall be of plug-in type, similar to
PFISTERER CONNEX CABLE PLUG-IN SYSTEM.
4.4.10.1.1 Ratings
4.4.10.1.1.1Rated voltage, kV 36
4.5.1 STANDARDS
4.5.1.1 Performance and test of all circuit breaker, disconnecting switch,
earthing switch, potential transformer, current transformer covered
4.5.5.2 Rating
4.5.5.2.1 Rated frequency, Hertz 50
4.5.5.2.2 Voltage ratings
4.5.5.2.2.1 Rated voltage, kV, rms. 12
4.5.5.2.3 Current ratings
4.5.5.2.3.1 Rated continuous current, Amperes ,rms.as shown on Single Line diagrams
4.5.5.2.3.2 Rated short circuit current (at rated voltage),
Amperes 40,000
4.5.5.2.3.3 3-second short-time current carrying capability,
Amperes, rms. 40,000
4.5.5.2.4 Interrupting ratings
4.5.5.2.4.1 Maximum symmetrical Interrupting capability for standard
duty cycle of CO+15 sec.+CO, Amperes, rms. 40,000
4.5.5.2.4.2 Maximum symmetrical Interrupting capability for reclosing
duty cycle of O+0.3 sec.+CO+3min.+CO, Amperes, rms. 40,000
4.5.5.2.5 Rated interrupting time, cycle (Based on 50 Hertz) 5
4.5.5.7 Construction
4.5.5.7.1 Circuit breakers
4.5.5.7.1.1 Live parts shall be mounted within a gas-tight and earthed metal
enclosure, SF6 gas shall be used as the insulation medium between live
parts and earthed enclosure. A homogeneous uniform electric field
shall be maintained within the insulation gas. Supports shall be epoxy
resin insulators.
4.5.5.7.2 Operating mechanisms:
The operating mechanism shall be of spring operated type. The other
types will not be accepted.
4.5.5.7.2.1 The operating mechanism shall operate to open and close all three
poles of the breaker essentially and simultaneously for three-phase
operation. The echanism shall be installed in dust-proof housing.
4.5.5.8 Accessories
4.5.5.8.1 Each circuit breaker shall be furnished with all necessary accessories,
but not be limited to the following:
4.5.5.8.1.1 Position indicator:
A mechanical position indicator shall be provided in the operating
mechanism housing to indicate the open and closed positions of circuit
breaker.
4.5.5.8.1.2 Operation counter :
An operation counter shall be furnished to indicate the total number of
operations of the circuit breaker. The counter shall register on tripping
operation only, and shall remain in operative during the closing stroke
of the breaker.
4.5.5.8.1.3 Exposed runs of control cable through the G.I.S structure shall be
protected by suitable covers.
4.5.5.8.1.4 Other accessories in accordance with manufacturer‘s standard.
4.5.6. Disconnecting Switch
4.5.6.1 General requirement
4.5.6.1.1 Disconnecting switches shall be of single-break, triple-pole, single
4.5.6.2 Rating
4.5.6.2.1 Rated frequency, Hertz 50
4.5.6.2.2 Rated voltage, kV, rms. (line to line) 12
4.5.6.2.3 Current ratings
4.5.6.2.3.1 Rated current, Amperes, rms. as shown on Single Line Diagram
4.5.6.2.3.2 Rated short circuit current (at maximum voltage) Amperes,rms. 40,000
4.5.6.2.3.2 3-second short-time current carrying capability Amperes,rms. 40,000
4.5.6.3 Insulation Level
4.5.6.3.1 The disconnecting switches shall withstand the following test voltage at
the normal operation gas pressure.
4.5.6.3.1.1 Low-frequency withstand voltage, one minute, kV, rms. 28
4.5.6.3.1.2 Impulse withstand voltage, 1.2x50 microsecond,
full wave, kV, crest 75
4.5.6.4 Operating Mechanism of Disconnecting Switch
4.5.6.4.1 The disconnecting switches shall be operated electrically and manually.
The control and service voltage of operating mechanism shall be
suitable for the power supply specified in Section 4.5.4.14. The
operating mechanism shall be enclosed in a metal housing. A heater
shall be provided in the housing and controlled by a humidity controller
in the low-voltage cabinet.
4.5.6.4.2 Each bay shall be provided with a "ON/OFF/EARTH" three position
disconnecting switch between circuit breaker and busbar. If a bus side
DS and a line side DS are used, instead of the three position DS, they
will also be accepted.
4.5.6.4.3 By putting the disconnecting switch into "EARTH" position, the circuit
4.6.1.3.2 Special equipment and tools for adjustment, testing, installation and
4.6.7.2 The total price for the recommended spare parts shall not be included in
the Bid evaluation price. The itemized prices for the spare parts shall be
quoted separately. CSCI Engineering Department reserves the right to
adjust the quantities of these spare parts to be purchased before the
contract award. The spare parts list shall be attached to the Bid and shall
4.6.8.2 Contractor shall submit twelve (12) paper copies and three (3) CDROM
of instruction book in Chinese and English before shipment. The
instruction book shall contain details of construction, installation,
maintenance and CT, relays instruments and all other devices in the
assemblies.
4.6.8.3 The contractor shall furnish the following information and drawings to
send to CSCI Engineering Department, No later than the date that the
contract delivery from the Contractor's works:
(1) Five (5) sets of certified drawings of equipment, including outline,
arrangement, construction, and wiring details.
(2) Three (3) sets of shop test report.
4.6.8.4 The contractor shall provide the training course for CSCI Engineering
Department’s engineer by 2 persons 1 week in factory and 6 persons 1
week at site in CSCI Engineering Department. The contractor shall have
obligation to let CSCI Engineering Department’s engineer familiar to
operation and maintenance.
4.6.10 Guarantee
4.6.10.1 Any damage of equipment, which delivered to local switch board
manufacturer’s factory site, shall be contractor’s responsibility.
4.6.10.2 If within two (2) years after delivery from the Contractor's factory, any
part of the material or equipment is found defective because of design,
workmanship or quality of materials, the Contractor shall furnish, at his
own expense, to CSCI Engineering Department for replacement part of
4.7.1 Scope
4.7.1.2 The Contractor shall offer design, size, type and foundations
which has been built previously and proven to meet the required
performance during satisfactory operating. No proto-type design
will be considered.
4.7.2.1 Standards
4.7.3.3 Special tools which for site assembly and installation.(If required)
4.7.5 Performance
The taps specified in Section 4.7.5.1.2 shall be full capacity taps and
shall be connected as described therein. The taps, upon which all
ratings are based, shall be 220kV for the high voltage winding and
22kV for the low voltage winding.
4.7.5.9 Losses
The ratio of copper loss to iron loss at base MVA for each
transformer shall be the practical minimum (Refer to Table "A").
4.7.5.10 Impedance
4.7.6 Construction
4.7.6.1 Core
The core shall be of cold rolled, grain oriented silicon steel of low
hysteresis loss and high permeability. The core legs shall be securely
held by appropriate means, insulated with Class B insulation. The
use of organic tape or pressed board wrapping to hold the
laminations will not be acceptable. All clamping structures shall
have adequate mechanical strength and shall be so constructed as to
minimize eddy currents. The core laminations shall have an
insulating coating resistant to the action of hot oil. The core and
coils shall be so fixed in the tank that shifting will not occur when
the transformer is being moved.
4.7.6.2 Windings
The windings shall consist of copper conductors and be of surge-
proof design to provide best protection against impulse stress. Coil
and core assembly shall be vacuum dried at the factory. All
permanent current carrying joints, except threaded connections,
shall be welded or silver soldered. Bolted clamp-type connections
shall be used at bushings, tap changers, and terminal boards. Bolts
shall be furnished with suitable locking devices to prevent
loosening of connections.
4.7.6.3 Bushings
The design of the bushings and the transformer shall permit the
removal and replacement of the bushings without removing the top
cover of the transformer tank and without lowering the oil to a
level which will uncover the windings.
4.7.6.5.2. The tap-changer shall regulate the voltage of all three phases
simultaneously and shall be suitable for remote manual operation.
Provision shall also be made for direct manual operation at the
- The tap selector switches shall not open or close under conditions,
which would require them to make or break load current.
4.7.6.9 Gas sampling valve shall be provided for the gas preservation
system.
4.7.6.13.1. The insulating oil shall be Naphthene series distillated pale oil
refined from natural crude petroleum, suitable for cooling and
insulating the transformers being supplied. It shall contain no
corrosive impurities which might affect insulating materials,
varnishes, metals and other parts of the transformer. It shall not
form sludge, chemical reaction or any other adverse condition,
even during a long period. The Contractor shall be provided "Shell
DD" oil. The Contractor shall give a survey of transformer oils
approved for filling or topping-up. All transformer oil shall be the
same sort.
4.7.6.13.2. The insulating oil will be tested before and after filling into the
transformers. If the tests indicate that the oil from any drum fails
to meet requirements of this Specification, the entire quantity of
supplied insulating oil will not be accepted and shall be replaced
at Contractor's expense.
4.7.6.14.2. For Atmoseal type, the equipment shall include a separate oil
expansion chamber with a synthetic rubber bag, which is of high
quality, high strength, moisture and oil resistant, suitable for
durable operation under variable temperature, and shall be airtight
and easily replaceable. No oil shall be blown off on replacement
of the bag. All necessary accessories shall also be included in the
equipment. The construction, mechanical strength and painting of
oil expansion chamber shall conform to Section 4.7.6.6 and
4.7.7.2.
4.7.6.16 Motors
4.7.6.17.2. All control and secondary wiring shall consist of not less than 2
mm2 stranded copper switchboard wire, having 600-volt heat and
moisture resistant insulation, with fireproof covering, if the
insulation alone is not fire retardant. Neoprene shall not be used.
Wiring shall be treated with antifungal agent to provide
satisfactory performance. All switchboard wiring shall be attached
to terminals with crimp-type lugs or approved equal.
4.7.6.17.3. Terminal blocks for all control wiring shall be stainless type. Ten
percent of the terminal positions shall be provided as spares.
4.7.6.18 All trip, alarm and other auxiliary contacts for thermo-meters,
thermostats, Buchholz relay, pressure relief device, oil gauge…
etc., shall be ungrounded and rated for use with CSCI
Engineering Department 's ungrounded 110 V DC system.
4.7.7 Accessories
The Buchholz relay shall be provided with one alarm contact and
one trip contact (for operation and leakage indication). All leads for
these contacts shall be brought to the control cabinet.
A suitable device for internal fault gas collection should be provided.
The fault gas shall be easily collected for analysis whiles the
transformer in operation.
4.7.7.1.3. Magnetic liquid-level oil gauge with low level alarm contacts, by
the Contractor.
4.7.7.1.5. Each transformer shall be provided with a dial type hot spot
winding temperature indicator for LV winding, to be located in a
well which is sealed off from the main tank. Indicator shall be
AKM type or approved equivalent, with 4 sets of microswitch
contacts adjustable in a range of 50℃ to 150℃ and provision for
field testing. Leads shall be brought out and tagged for control
cabinet termination. The dial type thermometer shall be
weatherproof and submersible.
The dial type thermometers shall be equipped with maximum
temperature indication pointer.
4.7.7.1.6. The dial type hot spot winding temperature indicator shall
perform the following functions at specified successive values of
hot spot temperature rise:
4.7.7.1.9. Current transformer for use with this indicator shall be located
under oil in transformer tank, in the center phase of the
low-voltage winding. Ratio of this CT, and indicator contact
settings, shall be indicated on a metal nameplate located near the
indicator and on transformer nameplate.
4.7.7.1.11. Insulating oil sufficient to fill the transformer to the normal oil
level.
4.7.7.1.16. All insulations that are not fungus-resistant shall have a fungus
resisting coating applied. Where such coatings would interfere
with proper operation of apparatus, the coating shall not be
applied. In such cases, the part
shall be inherently fungus-resistant.
4.7.7.2.1. Standard finish shall consist of three coats. The first coat shall be a
rust inhibitor, and the second and third coat shall be painted
according to the manufacturer's standard practice. The paint shall be
selected for superior quality with respect to both pigment and vehicle.
The color of the third coat shall be RAL 7033 (cement gray). The
second coat shall be of different color to insure that each coat is
continuous and of sufficient thickness. Sufficient quantity of RAL
7033 (cement gray) paint for a final field coat shall be furnished.
4.7.7.2.3. The Contractor shall provide 4 liters of finish paint for touch-up
purposes at China Steel Corporation site.
4.7.8.1 General
4.7.8.2 Ratings
System voltage 33 kV
Rated voltage 33/kV
Rated current (10 seconds) 800 amps
Resistance (Approximate) at 20 ℃ 15.9 ohms
Temperature rise limit at 30 ℃ ambient for stainless steel 760 ℃
4.7.8.4 Construction
4.7.8.4.1. All resistor grids shall be made of stainless steel and shall be
insulated from mounting supports and framework.
4.7.8.4.6. Each assembly shall be furnished with lugs for terminating the
cable from the transformer neutral and for connection of the
assembly to ground.
4.7.9.1 The Contractor shall submit, in both the Chinese and English
languages, five (5) copies of drawings of all equipment, including
dimensions, arrangement, electrical connections, name plate and
similar pertinent drawings, to CSCI Engineering Department
for approval. Detailed dimensions in metric units shall be clearly
marked on all drawings. CSCI Engineering Department will return
4.7.9.4 Five (5) sets of finally corrected and certified drawings of the
equipment, including outline, arrangement, construction and
wiring details. Five(5) sets of installation, operation and
maintenance instructions. (Including test r e p o r t , name p l a t e ,
outline, wiring details)
4.7.11.1.2. Tests for resistances of each tap, phases for both HV and LV
winding.
4.7.11.1.6. Tests for polarity and checking of the type of winding connection
as well as phase sequence.
4.7.11.1.7. Test for insulating oil and test report from the insulating oil’s
manufacturer.
4.7.11.2.1. Impulse voltage tests, both full wave and chopped wave, on the
complete transformer, with all bushings mounted.
4.7.11.5 Three (3) copies of suitable bound certified test report and
inspection data in Chinese and English shall be furnished after
these have been approved by CSCI Engineering Department.
4.7.12 Inspection
4.7.12.2 The Contractor shall afford without charge, all necessary and
reasonable facilities required by CSCI Engineering Department or
his consignee for the performance of inspection required.
4.7.13 Installation
The Bidder shall clearly state all exceptions, if any, to any part of this
Specification. Any statement on the Bidder's proposal (including
drawings) which differs from the requirements of this Specification shall
be specifically referred to by a definite citation in a "Statement of
Exceptions" to be considered by CSCI Engineering Department as
constituting an Exception to the Specification. Justification for such
exceptions shall be included in the "Statement of Exceptions".
2. Quantity 2
4. Percent Impedance at 75 ℃, 13 %
60 MVA base
5. LV neutral grounding resistor
Resistance at 20 ℃ 15.9 ohms
Rated current (10 seconds, at 24.2 KV) 800 amps
6. Bushing current transformer
6.1 HV terminal 600/1A CT per
Terminal with an accuracy class of 15VA, 5P20A. (Two cores CT,
each core CT include above ment-ioned rating.)
7. Characteristic value:
(guaranteed losses, at 75 ℃, at rated voltage, PF=1.0, 50Hz)
7.1 No-load losses ≦ 39 KW
7.2 Full load, Load Losses, at 75 MVA ≦ 372 KW
7.3 Total losses, at 75 MVA ≦ 411 KW
4.8.1 SCOPE
4.8.1.2 Bidder shall offer design, size and type which has been built previously
and proven to meet the required performance during satisfactory
operating. No proto-type design will be considered.
4.8.2.1 Standards
4.8.2.2.1 The Contractor shall make himself aware of the related weather,
earthquake and environmental conditions… etc in Dahej-2 Industrial
estate of Gujurat province in India.
4.8.2.2.2 In order to insure reliable service of equipment and wiring under these
adverse atmospheric conditions, the equipment shall be tropicalized
and the control cabinet shall be provided with space heaters and
gasketed doors.
4.8.2.2.5 The screw/washer below M10 (including M10) for allfitting device in
transformer shall be stainless steel and the screw/washer above M10
shall be hot-dip galvanized .
4.8.3.2 All transformers shall be complete with, but not necessarily limited to,
no load-tap-changing equipment, neutral grounding resistors, cooling
equipment, all controls and accessories, including bushing current
transformers, as specified herein.
4.8.3.4 Complete assembly and test of each transformer, at the factory, prior to
shipment. (See Section 4.8.12)
4.8.3.5 Complete installation and commissioning test of each transformer at
field.
4.8.4.3 Foundations.
4.8.4.5 Power cable for phase and neutral grounding resistor connection.
4.8.5.1.5 Basic insulation level (BIL) of all HV windings and bushings shall be
200 kV.
4.8.6. PERFORMANCE
4.8.6.4.1 The transformers covered by this specification shall meet the Short
Circuit Qualification Requirements given in the Short Circuit Test
Code prepared by IEEE Transformer Committee as an amplification of
ANSI Standard C57.12.00, Section 10, entitled Short Circuit
Characteristics.
4.8.6.4.2 The Bidder shall include, as an option, a quotation for the performance
of such tests, including the system conditions under which the tests
will be performed, and the test procedures to be followed.
4.8.6.4.3 CSCI Engineering Department will advise the Contractor at any time
during the engineering and manufacturing cycle whether such tests will
be required, but not later than four (4) weeks prior to delivery.
4.8.6.6.1 The transformer shall not produce radio influence voltage in excess of
650 micro-volts measured in accordance with NEMA Standard TR-
1(latest revision).
4.8.6.7.1 The transformer shall be so designed that the average audible sound
level will not exceed the standard values of NEMA Standard TR-
1(latest revision), when measured at the factory according to
conditions outlined in TR 1-9.04. Noise Level 71 db(A) + 3 db(A)
tolerance.
4.8.6.9 Losses
4.8.6.9.1 Core iron losses at 50 Hertz and flux density of 15000 gausses shall
preferably be less than 1.52 watts/kg.
4.8.6.9.2 The ratio of copper loss to iron loss at base MVA for each transformer
shall be the practical minimum, relevant information shall be included
in Bidder's proposal.
4.8.6.10 Impedance
4.8.7.0 CONSTRUCTION
4.8.7.1.1 The core shall be of cold rolled, grain oriented silicon steel of low
hysteresis loss and high permeability. The core legs shall be securely
held by appropriate means, insulated with Class B insulation.
The use of organic tape or pressed board wrapping to hold the
laminations will not be acceptable. All clamping structures shall have
adequate mechanical strength and shall be so constructed as to
minimize eddy currents.
The core laminations shall have an insulating coating resistant to the
action of hot oil.
The core and coils shall be so fixed in the tank that shifting will not
occur when the transformer is being moved.
4.8.7.2 Windings
4.8.7.3 Bushings
4.8.7.3.1 All bushings shall have current ratings to match the transformer
capacity and shall not crack due to uneven tightening in assembly or
from stresses of normal operation. All contact surfaces shall be silver
plated.
4.8.7.3.5 The main and neutral low voltage bushings shall be of 15 kV class, 110
kV BIL, according to ANSI Standard.
4.8.7.3.8 External clearances between energized parts and ground, and spacing
between adjacent phases, shall be coordinated with the internal
transformer insulation class.
4.8.7.3.9 The design of the bushings and the transformer shall permit the
removal and replacement of the bushings without removing the top
cover of the transformer tank and without lowering the oil to a level
which will uncover the windings.
4.8.7.6.2 The base shall be sufficiently strong and properly constructed to skid
the transformer forward, backward or sidewise.
The points of support of the skid base shall be so located that the
center of gravity of support for a tilt of the base of 15 degrees or less
from the horizontal, with or without oil in the transformer.
Provision shall be made on, or adjacent to, the base, for pulling the
transformer parallel to both center lines.
Lifting eyes for lifting the cover and jack lugs for jacking the
completely assembled transformer shall be provided, in accordance
with ANSI C57.12.10, Section B.17.
4.8.7.7.1 51mm minimum size, located at lowest point on tank for complete
drainage of tank. Valves to have valve body offset below outlet,
flanged inlet, threaded outlet with pipe plug; and sampling valve to
drain only when main valve is open. Flanged end to be bolted to
mating flange welded to tank with gasket between flanges.
4.8.7.8 Filter Press Valves
4.8.7.8.1 31.75 millimeters minimum size, located on opposite side of tank from
drain valves. Valves to have flanged inlet, threaded outlet with pipe
plug.
4.8.7.9 Gas sampling valve shall be provided for the gas preservation system.
4.8.7.10 Ground pads shall be furnished as specified in ANSI C57-12-10,
Section B,17. Each ground pad shall be furnished with a crimp type
connector for 250 mm2 copper cable.
4.8.7.11 Gasketed surfaces shall be provided with gasket compression-limit stop.
Gasketed surfaces which must be opened for untanking the transformer
shall have gaskets so installed as to minimize damage to the gaskets
when untanking the transformer.
Gaskets shall be Nitrile rubber, Corprene Neoprene, or approved equal.
One spare set of gaskets shall be quoted for all bushings and openings.
4.8.7.13.1 The insulating oil shall be Naphthene series distillated pale oil refined
from natural crude petroleum, suitable for cooling and insulating the
transformers being supplied. It shall contain no corrosive impurities
which might affect insulating materials, varnishes, metals and other
parts of the transformer. It shall not form sludge, chemical reaction or
any other adverse condition, even during a long period. "Shell DD"
oil is preferable.
Contractor shall give a survey of transformer oils approved for filling
or topping-up.
All transformer oil shall be the same sort.
4.8.7.13.3 The insulating oil will be tested before and after filling into the
transformers. If the tests indicate that the oil from any drum fails to
meet requirements of this specification, the entire quantity of
supplied insulating oil will not be accepted and shall be replaced at
Contractor's expense.
4.8.7.14.2 For Atmoseal type, the equipment shall include a separate oil
expansion chamber with a synthetic separate oil expansion chamber
with a synthetic rubber bag, which is of high quality, high strength,
moisture and oil resistant, suitable for durable operation under
variable temperature, and shall be airtight and easily replaceable. No
oil shall be blown off on replacement of the bag. All necessary
accessories shall also be included in the equipment. The construction,
mechanical strength and painting of oil expansion chamber shall
4.8.7.15.4 The OA/FA cooling system shall consist of necessary fans, motors,
temperature control and alarm devices. The system shall be capable
of operation by either manual or automatic control.
4.8. 7.15.5 Two 415-volt, 3-phase,50Hertz feeders each with a fault current
capability of 25000 amperes symmetrical will be furnished by CSC
for auxiliary power. Contractor shall provide circuit breakers and
equipment for automatic transfer to the standby source with remote
annunciation, in case of failure of the selected operating source.
If Contractor's equipment operates at voltages other than 415, two
suitable full capacity dry type transformers shall be furnished by
Contractor.
4.8.7.15.7 Fan guards shall be provided to prevent direct human contact with
blades.
4.8.7.16.2 Motors shall be 415 volt, 3-phase, 50Hertz, within dividual overload
protection. Motor less than one-quarter horse-power may be 240
volt, 1-phase,50 Hertz.
4.8.7.17.2 All control and secondary wiring shall consist of not less than 2 mm2
stranded copper switchboard wire, having 600-volt heat and moisture
resistant insulation, with fireproof covering, if the insulation alone is
not fire retardant. Neoprene shall not be used. Wiring shall be treated
with antifungal agent to provide satisfactory performance. All
switchboard wiring shall be attached to terminals with crimp-type
lugs or approved equal.
4.8.7.17.3 Terminal blocks for all control wiring shall be stainless type . Ten
percent of the terminal positions shall be provided as spares.
4.8.7.18 All trip, alarm and other auxiliary contacts for thermo- meters,
thermostats, buchholz relay, pressure relief device, oil gauge… etc.,
shall be ungrounded and rated for use with CSCI Engineering
Department 's ungrounded 110V DC system.
4.8.8 ACCESSORIES
4.8.8.1 Accessories shall be provided, including, but not limited to,as following:
4.8.8.1.1 A mechanical type pressure relief device shall bemounted on the cover
of each transformer to prevent the buildup of dangerous pressure in the
transformer tank. The device shall trip at 10 psi, concurrently actuating
a semaphore and an alarm contact. When the internal pressure is
reduced, the device shall automatically close to keep out rain or other
foreign matter.
4.8.8.1.3 Magnetic liquid-level oil gauge with low level alarm contacts, by
Contractor.
4.8.8.1.5 Each transformer shall be provided with a dial type hot spot winding
temperature indicator for LV winding, to be located in a well which is
sealed off from the main tank. Indicator shall be AKM type or
approved equivalent, with 4 sets of microswitch contacts adjustable in
a range of 50℃ to 150℃ and provision for field testing. Leads shall be
brought out and tagged for control cabinet termination. The dial type
4.8.8.1.6 The dial type hot spot winding temperature indicator shall perform the
following functions at specified successive values of hot spot
temperature rise:
a. Turn on cooling equipment.
b. Operate CSCI's alarm.
c. Trip breakers.
4.8.8.1.7 One dial type thermometer direct mounted for measuring the top
liquid temperature complete with 4 sets of micros witch contacts
adjustable temperature alarm/trip contacts and with maximum
temperature indication pointer. The indicating part shall be of air tight
construction and submersible; that there is no possibility of the glass
interior collecting moisture resulting in difficulty to observe the
indicator.
Indicator shall be AKM type approved equivalent.
All the indicator dials, with alarm/trip contact adjustments, shall be
mounted as a group in a position conveniently visible and accessible to
a man standing at floor level.
4.8.8.1.9 Current transformer for use with this indicator shall be located under
oil in transformer tank, in the center phase of the low-voltage winding.
Ratio of this CT, and indicator contact settings, shall be indicated on a
metal nameplate located near the indicator and on transformer
nameplate.
4.8.8.1.12 The transformer shall be furnished with all standard accessories and
fittings for transformer oil filling or removal to include oil sampling
connections top and bottom, oil filtering connections, and draining
extreme bottom of tank. All accessories shall be rustproof.
4.8.8.1.16 All insulations that are not fungus-resistant shall have a fungus
resisting coating applied. Where such coatings would interfere with
proper operation of apparatus, the coating shall not be applied. In
such cases, the part shall be inherently fungus-resistant.
4.8.8.1.18 Each transformer shall be furnished with stainless steel fence, located
on the cover of the transform main tank, to protect workers from
falling.
4.8.8.2 Painting
4.8.8.2.1 Standard finish shall consist of three coats. The first coat shall be a
rust inhibitor, and the second and third coat shall be painted according
to the manufacturer's standard practice. The paint shall be selected for
superior quality with respect to both pigment and vehicle. The color of
4.8.8.2.2 Before painting, all surfaces shall be thoroughly cleaned of oil, rust
and detritus. All edges and rough spots shall be smoothed. The
surfaces shall be kept thoroughly dry and clean before and during
painting.
4.8.8.2.3 Contractor shall provide 4 liters of finish paint for touch-up purposes
at CSCI Engineering Department site.
4.8.9.1 General
4.8.9.1.2 The resistor assembly shall be floor mounted and screened in cubicle
for personnel protection, self-supporting and of the stainless steel, open
grid, dry, stack type.
4.8.9.2 Ratings
4.8.9.2.1 System voltage 11.5 KV
4.8.9.2.2 Rated voltage 11.5/(root 3) KV
4.8.9.2.3 Rated current (10 seconds) 600 amps
4.8.9.2.4 Resistance (Approximate) at 20 ℃ 11.1 ohms
4.8.9.2.5 Temperature rise limit at 30 ℃ ambient
For stainless steel 760 ℃
4.8.9.4 Construction
4.8.9.4.1 All resistor grids shall be made of stainless steel and shall be insulated
from mounting supports and framework.
4.8.9.4.6 Each assembly shall be furnished with lugs for terminating the cable
from the transformer neutral and for connection of the assembly to
ground.
4.8.10.1 The Contractor shall submit, in both the Chinese and English
languages, within the period given in Section 4.8.19.5.27, five (5)
copies of drawings of all equipment, including dimensions,
arrangement, electrical connections, name plate and similar pertinent
drawings, to CSC for approval.
Detailed dimensions in metric units shall be clearly marked on all
drawings. CSC will return one copy to the Contractor marked
"Approved", or commented for correction. The
Contractor shall then make all necessary corrections and revisions.
Correction of drawings shall be not entitled to any extension of the
delivery time. Any work done or materials ordered by the Contractor,
prior to receipt by the Contractor of drawings marked Approved, shall
be at the Contractor's own risk.
4.8.11.1 Itemized prices for following parts shall be quoted separately; CSCI
reserves the right to adjust the quantities of these spare parts (as
section 6.1 spare part list) within 24 months after contract signed:
4.8.12.1.1 All tests shall be made by and at the expense of the Contractor in
accordance with the latest revision of ANSI Standard C57-12, unless
otherwise specified, or to standards that equipment is built to.
4.8.12.1.2 CSCI reserves the right to witness the tests. Contractor shall notify
CSCI four weeks in advance of scheduled tests.
4.8.12.2.2 Tests for resistances of each tap, phases for both HV and LV winding.
4.8.12.2.5 Tests for polarity and checking of the type of winding connection as
well as phase sequence.
4.8.12.3.1 Impulse voltage tests, both full wave and chopped wave, on the
complete transformer, with all bushings mounted.
4.8.12.5 All tests shall be conducted at the Contractor's works, by and at the
expense of the Contractor. The test items of Sections 4.8.12.2.3,
4.8.12.2.4, 4.8.12.2.5, 4.8.12.2.6, 4.8.12.2.7, 4.8.12.2.8, 4.8.12.2.9,
4.8.12.3.1 for completed transformers shall be conducted in the
presence of CSCI's inspector, shall in no way relieve the contractor of
his responsibility for testing the equipment in strict accordance with
the relevant standard.
4.8.12.6 Three (3) copies of suitable bound certified test report and inspection
data in Chinese and English shall be furnished after these have been
approved by CSCI Engineering Department.
4.8.12.7 Oil used in the transformer during tests conducted at the Contractor's
works shall be the same as applied and specified in Section 4.8.7.13.
4.8.13.2 The Contractor shall afford without charge, all necessary and
reasonable facilities required by CSCI Engineering Department or his
consignee for the performance of inspection required.
4.8.13.3 CSCI Engineering Department or his consignee shall have full access
to all fabricating or manufacturing plants at all times, to inspect all
materials and fabrication, as well as witness all tests.
4.8. 13.4 No material or equipment shall be delivered before it has been cleared
by CSCI V, and the material or equipment so marked.
4.8.14.3 All packing enclosures shall be such that slings for handling may be
readily attached during transport. Where it is unsafe to attach slings to
boxes or crates, boxed or crated parts shall be packed with slings
attached to the contents. The slings shall project through the box or
crate so that other lifting attachments can be readily made.
4.8.14.4 All projecting parts such as valves, gauges, and similar equipment shall
be removed wherever possible, and transported separately; where
removal is not possible, protective steel plate or boxes shall be welded
for protection.
4.8.14.6 All finished nonferrous metal work and devices liable to be damaged
shall be suitably wrapped or otherwise protected.
All finished ferrous surfaces shall be coated with a readily removable
rust preventive compound.
4.8.14.8 All parts shall be adequately marked to facilitate field erection, and all
packages shall have two (2) copies of the package list, one attached to
the package, the other to be sent to CSCI Engineering Department, if
requested.
4.8.14.9 The transformer with its accessories and spare parts shall be
transported to CSCI Engineering Department erection site in India at
Contractor's cost, with the transformer taps connected at 33 KV to
11KV position.
4.8.15.1 For the purpose of comparing bids, the Bidder shall guarantee the
transformers to meet the characteristic value as specified in Table“A”,
and propose relevant information as per Section 4.8.19.5.11. If the
characteristic value in Bidder’s proposal exceed the guaranteed value
as specified in Table “A”, CSCI Engineering Department will reject
the proposal.
4.8.15.2 Liquidated damage shall be one hundred twenty five thousand New
Taiwan dollars (NT$125,000) for each KW or part thereof, by which
the actual total no-load losses of each transformer, operating on 33 KV
/ 11 KV taps excited at rated voltage and frequency exceed the
guaranteed value.
4.8.16.0 GUARANTEE
4.8.16.1 If within four (4) years after delivery from the Contractor's factory, any
part of the material or equipment is found defective because of design,
workmanship, or quality of material, the Contractor shall, at his own
expense, furnish to CSCI Engineering Department site replacement
parts of such design, workmanship and material as approved by CSCI
Engineering Department.
4.8.17.1 The Bidder shall clearly state all exceptions, if any, to any part of this
specification. Any statement on the Bidder's proposal (including
drawings) which differs from the requirements of this specification
shall be specifically referred to by a definite citation in a "Statement of
Exceptions" to be considered by CSCI Engineering Department as
constituting an Exception to the specification. Justification for such
exceptions shall be included in the "Statement of Exceptions".
2. Quantity 2
4. Percent Impedance at 75 ℃, 9%
32 MVA base
7. Characteristic value:
(guaranteed losses, at 75 ℃, at rated voltage, PF=1.0, 60Hz)
7.1 No-load losses <= 27.0 KW
7.2 Full load, Load Losses, at 40 MVA <= 182.1 KW
7.3 Auxiliary power loss, at 40 MVA <= 1.2 KW
7.4 Total losses, at 40 MVA <= 210.3 KW
9 Efficiency in percent at
100% load (40 MVA) <= 99.48%
75% load <= 99.57%
50% load <= 99.63%
4.9.1.2 Bidder shall offer design, size and type, which has been built
previously and proven to meet the required performance during
satisfactory operating. No proto-type design will be considered.
4.9.1.3 The transformers shall be cables connected to the bus of the main
incoming breakers.
4.9.1.4 Each power transformer is rated to carry the total load of the bus
section of each switchgear assembly. The impedance of each power
transformer has been selected to allow parallel operation of the two
sources without exceeding the interrupting rating of the associated
switchgear. (Transformer kVA and impedance values are as shown on
the attached list).
4.9.1.6 Base bids shall be for equipment outlined in Section 4.9.1.3 including,
but not necessarily limited to, all controls and accessories further
specified herein, including transformers filled with non-inhibited oil
4.9.3.2 All transformers shall be complete with, but not necessarily limited to,
no-voltage tap-changer equipment, cooling equipment, all controls and
accessories, including bushing current transformers, as specified herein.
4.9.3.4 Complete assembly and test of each transformer, at the factory, prior to
shipment. (See Section 4.9.11)
4.9.4.3 Foundations.
4.9.6.1.2 The above specified temperature rise shall apply when the transformer
is operated continuously at full load rating, with the primary voltage
tap set at each one of the five positions. The kVA rating is based on
rated low voltage, which is maintained by impressing on the HV
winding a voltage higher than its rated voltage for compensation of the
transformer voltage regulation. The transformer shall deliver rated
kVA continuously at 105 percent rated voltage and operate
continuously at 10 percent above rated voltage at no load without
exceeding the above specified temperature rise.
4.9.7.6.2 The base shall be sufficiently strong and properly constructed to permit
the transformer skidding forward, backward or sidewise. The points of
support of the skid base hall be so located that the center of gravity of
support for a tilt of the base of 15 degrees or less from the horizontal,
with or without oil in the transformer. Provision shall be made on, or
adjacent to, the base, for pulling the transformer parallel to both central
lines. Lifting eyes for lifting the cover and jack lugs for jacking the
completely assembled transformer shall be provided, in accordance
with ANSI C57.12.10, Section B.17.
4.9.7.11.2 The Buchholz relay shall be complete with separate contacts for alarm
and trip (for operation and leakage indication).
4.9.7.11.3 All leads for these contacts shall be brought to the common terminal
box described in Section 4.9.7.13.1. The system will be operated from
a 110V DC control source.
4.9.7.13.6 All alarm and relay contacts shall be ungrounded and rated for use
with CSCI Engineering Department 's ungrounded 110V DC system.
4.9.7.14 Painting
4.9.7.14.1 Standard finish shall consist of three coats. The first coat shall be a rust
inhibitor, and the Second and third coat shall be painted according to
the manufacturer's standard practice. The paint shall be selected for
superior quality with respect to both pigment and vehicle. The color of
the third coat shall be RAL 7033 (cement gray). The Second coat shall
be of different color to insure that each coat is continuous and of
sufficient thickness. Paints such as alkyd enamels having a fungus
resistant property shall be used on all inside surfaces and shall be
sprayed. The paint has to withstand chemically aggressive atmospheres
prevailing in steel mills.
4.9.7.14.2 Before painting, all surfaces shall be thoroughly cleaned of oil, rust
and detritus. All edges and rough spots shall be smoothed. The
surfaces shall be kept thoroughly dry and clean before and during
painting.
4.9.7.14.3 All insulation that is not fungus-resistant shall have a fungus resisting
coating applied. Where such coatings would interfere with proper
operation of apparatus, the coating shall not be applied. In such cases,
the part shall be inherently fungus-resistant.
4.9.8.3 Stainless steel nameplate and connection diagram plate, in accord with
ANSI standards, by Contractor.
4.9.8.4 Each transformer shall be provided with a dial type hot spot winding
temperature indicator for LV winding, to be located in a well which is
sealed off from the main tank. Indicator shall be FUKUDA type or
equal, with 4 sets of contacts adjustable in a range of 0℃ to 120℃ and
provision for field-testing. Leads shall be brought out and tagged for
control cabinet termination. The dial type thermometer shall be
weatherproof and submersible.
4.9.8.5 The dial type hot spot winding temperature indicator shall perform the
following functions at specified successive values of hot spot
temperature rise:
The equipment will be used to measure the top-oil temperature and the
winding temperatures of the transformer components. Installation and
wiring of the equipment shall be done by Contractor. All of the remote
ndicating temperature as mentioned above shall also be provided with
RTD PT100 ohms 0℃ and 4-20 mA signal terminal (DC transducer
will be HSIANG CHENG type) for connection to UDC for remote
monitor by others.
4.9.8.6 The dial type thermometer direct mounted for measuring the top liquid
temperature complete with adjustable temperature alarm/trip contacts.
The indicating part shall be of airtight construction and submersible;
that there is no possibility of the glass interior collecting moisture
resulting in difficulty to observe the indicator.
4.9.8.13 The control cabinet shall be weatherproof, dust tight and shall include
space heaters and thermostat.
4.9.8.14 The Contractor without additional cost shall provide any equipment
which is normally furnished with this size transformer, or which is
necessary for satisfactory operation and maintenance to CSCI
Engineering Department.
4.9.9.3 The Contractor shall furnish the following information and drawings,
in Chinese and English languages, to reach CSCI Engineering
Department not later than the date that the equipment contracted is
ready for delivery from Contractor's works:
4.9.9.3.1 Fifteen (15) sets of finally corrected and certified drawings of the
equipment, including outline, arrangement, construction and wiring
details.
4.9.9.3.2 Fifteen (15) sets of installation, operation and maintenance instructions.
(including test report, name plate, outline, wiring details)
4.9.9.3.3 Five (5) sets of replacement parts list.
4.9.10.2 The Bidder shall provide with his proposal a separate list of
recommended spare parts suitable for two years operation complete
with unit price. Cost of spare parts shall not be included in the bid
price. Purchase of these additional spare parts will be at CSCI
Engineering Department 's option.
4.9.11 Test and Reports
4.9.11.1 All tests shall be made by and at the expense of the Contractor in
accordance with the latest revision of ANSI Standard C57-12, unless
4.0 Cooling OA
4.10.2.3 The transformer shall be provided with two 2.5 percent full
capacity taps above and two 2.5 percent full capacity taps below
rated primary voltage. Taps shall be accessible from front or rear
of unit.
4.10.2.6 Each high voltage winding and each low voltage winding of each
phase shall be separately cast as a rigid tubular coil. High voltage
and low voltage windings shall be coaxial with no mechanical
connection. The windings shall not absorb moisture and shall be
suitable for both storage and operation in adverse environments,
including prolonged storage in 100% humidity at temperature
ranging from 0 to 40 deg C. and shall be capable of being
energized immediately after such storage without pre drying.
4.10.2.8 The core shall be visibly grounded to the base and the base
provided with a grounding connection pad.
4.10.2.12 Internally connected no-load taps, two 2.5 percent above the rated
voltage and two 2.5 percent below the rated voltage, externally
operated tap changer for de-energized operation, lifting eyes,
diagrammatic nameplates, and accessories for forced air cooling
(if required) shall be provided.
- Kind of transformer
- Standard
- Manufacture’s name and serial number
- Year of manufacture
- Number of phases
- Rated power and frequency
- Rated voltages and tapping range
- Rated currents
- Insulation class and temperature rise
- Connection symbol
- Short-circuit impedance voltage
- Type of cooling
- Total weight
4.10.3 Tests
Unless as specially stated, the following routine tests will be made on all
transformers in accordance with corresponding codes and standards.
4.11.1.2 Similarly rated equipment shall have been built previously and proven
to meet the required performance during satisfactory operation. No
prototype design will be considered.
4.11.2.1.2 In the event that any part of the offer is not covered by other
authoritative standards, the appropriate American National Standard or
codes shall be complied with.
The metal sheet of ring main unit switchgear shall be made by stainless
steel.
With cable fitation flange (40mm diameter) and cover on each bay
The outdoor chassis shall be made by hot-dipping Zinc steel (GI), and
provide the dimensions of chassis and design document for technical
review.
4.11.7.2 Contractor shall submit fifteen (15) paper copies and three (3)
CDROM of instruction book in Chinese and English before
shipment. The instruction book shall contain details of construction,
installation, maintenance and operation of RMU and all other devices
in the assemblies.
4.11.7.3 The contractor shall furnish the following information and drawings to
send to CSCI Engineering Department, No later than the date that the
contract delivery from the Contractor's works:
(1) Three sets of certified drawings of equipment, including outline,
arrangement, construction, and wiring details.
(2) Shop test report.
4.11.7.4 The contractor shall provide the training course for CSCI Engineering
Department’s engineer by 2 persons 2 week in factory and 6 persons 1
week at site in CSCI Engineering Department. The contractor shall
have obligation to let CSCI Engineering Department’s engineer
familiar to operation and maintenance of RMU.
4.11.8 Packing and Delivery
4.11.8.1 The RMU, with its accessories and spare parts, shall be suitably
packed as seaworthy packing at Contractor's expense. The breaker
shall be boxed in crates, with upper and lower polyethylene sheets
welded together, with desiccant bags and sealed wooden floor.
4.11.8.2 The contractor shall deliver all RMU with packing list to CSCI
Engineering Department’s specified manufacturer. All spare parts and
special tools shall be packed in a suitable steel cabinet with lock and
deliver to CSCI Engineering Department directly.
4.12.1.2 Similarly rated equipment shall have been built previously and proven to
meet the required performance during satisfactory operation. No
prototype design will be considered.
4.12.1.3 Quantity
See Single Line Diagram of Appendix one.
4.12.1.3.1 The total quantity of ACB for metal-enclosed switchgears :
4.12.1.4 Each switchgear unit consists of 2 bus sections, double sections are
electrically connected by bus tie breaker.
The arrangements as shown on the appendix one.
4.12.2.1 STANDARDS
4.12.2.1.2 In the event that any part of the offer is not covered by other
authoritative standards, the appropriate American National Standard or
codes shall be complied with.
4.12.2.2.1 The Contractor shall make himself aware of the related weather,
earthquake and environmental conditions… etc in Dahej-2 Industrial
estate of Gujurat province in India
4.12.3.1.1 The air circuit breaker shall be equipped with primary and secondary
contacts, drawout rails and mechanical interlocks to prevent insertion
or drawout of the breaker when the breaker is in the closed position.
Each breaker shall be provided with a breaker drawout mechanism,
which permits a tripped breaker to be moved from the connected
position to the test and disconnect positions. The drawout mechanism
allows the breaker to take any of the following positions:
"CONNECTED","TEST","DISCONNECTED" or "FULLY DRAWN
OUT". The breaker in any position or somewhere between them is
earthed through any adequate method. In the connected, test,
disconnected position, the switchboard front panel can be shut.
The air circuit breakers can be locked in the open position by means of
a padlock,to prevent the breaker from being accidentally closed. When
the breaker is locked by this device, it cannot be closed mechanically
or electrically.
4.12.3.1.4 Each breaker shall be equipped with a device for fixing a pad-lock in
"Disconnected" position.
4.12.3.1.5 Air circuit breakers shall be three-pole, rated insulation voltage AC 660V,
drawout type, supported on a frame, and designed to be rigidly connected
to the housing in the operating position. There shall be provision for
easily moving the circuit breaker to a test position by means of a hand-
operated device at each breaker, with the main disconnecting devices
open, but with the control and operating circuits operable. The breakers
shall be removable from the front of the compartment. The breakers
should be stored-energy-closing operation, the energy is stored in springs,
and release of this stored energy causes the air circuit breaker to close.
The energy is stored by means of an electric motor or by hand. For
manual closing, the closing spring are charged by any number of handle
strokes from one to five or several inching strokes. When the charging
indicator shows "charged", depressing a mechanical CLOSE button on
the escutcheon can close the breaker.
For electrically operated breakers, utilize a motor to automatically keep
the closing spring in a charged state; upon receipt of a closing signal, a
control solenoid release the springs, closing the breaker's contacts.
All breakers, manual and electrical, are equipped with a mechanical trip
button located on the breaker escutcheon, an external trip switch can be
used for shunt trip since the circuit is already connected to the control
source of solid state over current trip relay unit. Electrically operated
breakers can be opened from a remote control switch or relay.
The breaker cannot be closed electrically or manually while the open
button or command is locked in the off position.
4.12.3.1.9 All circuit breaker operating electrically mechanisms shall be trip free.
Shunt trip operated mechanisms shall be designed for remote trip.
4.12.3.1.10 Air circuit breakers shall have "stored energy" type tripping
mechanisms.
4.12.3.1.1.13 Each breaker shall be equipped with 4NO, 4NC and one alarm
switch.
4.12.3.2 Switchgear
4.12.3.2.1 The switchgear section shall be cable-connected to a transformer and
shall consist of a completely metal-enclosed structure. Switchgear bus
shall be three phases, three wires, for operation at 415 volts 1600A
continuously.
4.12.3.2.3 Removable panels with hinge shall enclose back site of cubicles.
4.12.3.2.5 All power cable will enter the switchgear from the bottom
All external connected power cables will be PVC jackets.
Control cables will enter the switchgear from side bottom of rear panel.
Suitable supports shall be provided within the switchgear housing for
purchaser's power and control cables. The cable bending space meets
the requirements of the latest National Electrical Code. Power and
conductors will be copper. Terminal connectors and terminal blocks
shall be suitable for copper conductors.
4.12.3.2.8 The switchgear front panel is attached with adhesive colored mimic
synoptic of circuit diagram.
4.12.3.2.9 The cable and terminal compartment is located behind the bus
compartment and provided adequate room for easy cable installation.
Copper bars extend the load size of the stationary disconnecting
contacts into the cable compartment. Current transformers can be
4.12.3.2.11 Compartment designated " spare " are to be completed in all respects
including breaker element.
4.12.3.2.12 Not more than three (3) breakers shall be installed in any vertical row.
4.12.3.4 Buses
4.12.3.4.1 Buses shall be copper, suitably supported and braced for 50,000
amperes symmetrical short circuit current.
4.12.3.4.2 Load terminal location shall be arranged to provide for the changeout
of load cables, and without de-energizing the switchgear assembly
proper attachable isolated sheets shall be provided.
4.12.3.4.3 Copper ground bus shall be provided across the full length of the
switchgear in the rear compartments. Ground bus shall have two
4.12.3.5.1 Control cable will be copper and will enter the switchgear from the
side bottom of rear panel. Terminal conductors and terminal blocks
shall be suitable for copper conductors.
4.12.3.5.2 Minimum size conductors for switchgear control wiring shall be 2.0
mm square stranded copper switchboard wire type PVC rated 600 volt,
90 deg. C.
4.12.3.5.5 All control wiring shall be brought out to terminal blocks for remote
controls. All auxiliary switch spare contacts, current transformer
secondary leads, potential transformer secondary leads and auxiliary
relay contacts shall be wired to terminal blocks. Wireways within
switchgear for Purchaser's control cables shall be arranged to provide
safe installation of such cables without de-energizing the switchgear.
4.12.3.6.1 Under normal operating conditions the bus tiebreakers will be open so
as not to exceed the interrupting rating of the switchgear and
downstream equipment due to short circuit contribution from the two
sources. It may be necessary to monetarily tie the 480 volt buses
together during periods of load transfer until the auxiliary load is
transferred the proper unit.
4.12.3.6.2 A time relay will trip the tiebreaker, in case the parallel operation is
continue for a contained time period (adjustable range from 1 sec. to
30 sec.).
4.12.3.6.3 All necessary protective relay, inter compartment wiring and interlocks
shall be furnished by Contractor. Bell alarm mounted on switchgear
will operate during paralleling.
4.12.3.7.1 Current transformers shall be the window types with rations suitable to
associated breaker. All current transformers shall have thermal and
mechanical ratings equal to or greater than that of the associated circuit
breaker.
4.12.3.7.2 The manufacturer shall state the accuracy class and shall furnish
typical ratios, correction factor, and phase angle, saturation curves for
each current transformer supplied before shipment.
4.12.3.7.3 There are two potential transformers for each incoming feeder, one is
used for measurement, the other supplies for the control circuit.
4.12.3.7.4 The primaries and secondary shall be protected with built-in current
limiting fuses and primary connections shall be made with 600 volt-
insulated cable. Potential transformer shall have 1 metering accuracy
class. The manufacturer will specify accuracy class and burden and
shall furnish typical ratios, correction factor and phase angle curves for
each potential transformer supplied before shipments. The primaries of
potential transformers will be connected to the primary side of
incoming breakers.
4.12.3.7.6 All instruments and relays shall be for operation on 5-ampere current
transformer secondary circuits and/or 120-volt potential transformer
secondary circuits. Relays shall be furnished with integral, or
separately mounted, test switches as required.
4.12.3.7.8 Suitable current shorting switch shall be provided in the current leads
to each instrument to facilitate maintenance and calibration.
4.12.3.7.9 Suitable test switches shall be provided in the potential leads to each
instrument, in the secondary circuit from each set of potential
transformers and in the potential leads to each voltmeter switch.
4.12.3.7.11 Control switches for switchgear control bus and meters shall be
mounted on the front of the appropriate switchgear cubicle.
4.12.4 TESTS
4.12.4.1 For each type air circuit breaker and rating of a fault current interrupting
device, a certified test report shall be submitted showing the interrupting
capacity of the device tested in accordance with the standard to which the
device was built.
4.12.4.2 Contractor should perform the factory and site test for switchgear with
ACB. Including meter, CB operation and relay trip function. Authorized
engineering consultant should perform site test.
4.12.5 Painting
4.12.5.2 All insulation that is not fungus resistant shall have a fungus resistant
coating applied. Where such coatings would interfere with proper
operation of apparatus, the coating shall not be applied. In such cases, the
part shall be inherently fungus resistant.
4.12.5.3 Contractor shall provide one liters of finish paint for touch-up purposes
at CSCI Engineering Department site.
The Bidder shall provide spare parts for two years as section 6.1 spare
part list of normal continuous operation.
4.12.7.1 Contractor shall submit the following drawings and data in accordance
with the contract terms and conditions:
(a) Within 30 days after receipt of Letter of Intent of award the contract:
Layout and arrangement drawings showing front and rear views,
weights, sections, bus arrangements, dimensions, floor plan,
anchoring detailed and so forth All dimensions shall be in the metric
systems.
4.12.7.2 Contractor shall submit six (12) copies of instruction book in Chinese
before shipment. The instruction book shall contain details of
construction, installation, maintenance and operation of switchgear,
breakers, relays instruments and all other devices in the assemblies.
4.12.7.3 The contractor shall furnish the following information and drawing, to
reach CSCI Engineering Department, No later than the date that the
contract delivery from the Contractor's works:
4.12.7.4 Any construction work done prior to the approval of drawing will be at
the Contractor's risk. The Contractor shall make any change in the design,
which are necessary to make the equipment conform to the provisions
and intent of the contract documents without additional cost.
Approval of Contractor's drawing shall not be held to relieve the
Contractor of any part of Contractor's obligation to meet all of the
requirements of the contract documents nor of the responsibility for the
correctness of the contract's drawings.
If within two (2) years after delivery from the Contractor's factory, any
part of the
material or equipment is found defective because of design,
workmanship or quality of materials, the Contractor shall furnish, at his
own expense, to CSCI Engineering Department for replacement part of
such design, workmanship and material as approved by CSCI
Engineering Department.
4.12.11EXCEPTION TO SPECIFICATION
4.13.1 General
4.13.1.1 The DC 110V power system shall include the following facilities:
4.13.1.1.1. Battery:
Quantity: Two (2)sets for main substation and one(1) set for ACL S/S.
batteries capacity (at ten (10) hours rate): 400 AH/set.
Quantity: Two (2)sets for main substation and one(1) set for ACL S/S.
Battery Chargers capacity 50A (Minimum rated output at DC 110V).
Quantity: Two (2)sets for main substation and one(1) set for ACL S/S.
4.13.1.2.4. Description and lists of software (if any), spare parts, standard
and/or special tools and test equipment.
4.13.1.3 Standards
The listed below shows the standard that shall be used to comply and
confirm manufacture quality of Batteries and battery chargers.
IEC61000, EN50121, CEM 89/336/CEE, IEC60896-2, IEC 60146-1,
ANSI, NEMA and IEEE.
4.13.2 Charger
The charger shall be suitable for charging at the appropriate float and
boost values together with the supply of the standing load. The charger
shall have one incoming breaker to receive 240V source and four DC
output breakers (two loading and two battery set breakers).
4.13.2.2.2. If the AC input power to the charger is interrupted, the load shall
be supplied with power from the battery without a momentary
interruption. After the interruption of AC is recovered, the
supplementary charge shall be carried out as promptly as possible.
Further, a manual operation device shall be provided for boosting
charge, initial charge and supplementary charge.
4.13.2.2.3. The charger shall be capable of float charging the battery at 2.10 ~
2.25V per cell (115.5~123.75V in total) and boosting charge at
2.20 ~ 2.35V per cell (121~129.25V in total), these voltages shall
be obtained by continuous adjustment, and the range of
adjustment shall be sufficient to permit setting of the output
voltage to any value within the range specified above with AC
voltage variation of +10%. DC output current is automatically
limited to within a tolerance of ±2%, while also supplying the
standing load, over an input voltage variation of ±10%.
4.13.2.2.5. The charging circuit shall be arranged that the failure of any
component will not cause permanent damage to the battery by
overcharging. The battery charge current should be pre-set, and
that will be limited.
4.13.2.2.6. The charger shall be provided whereby the on line battery set
capacity test function. When the test button is pushed, the charger
output voltage reduced to pre-set value which is the same as “Test
Ending Voltage”, the battery set begin discharge and a timer count
the discharge time. Until the voltage of battery set was dropped
4.13.2.2.7. A high rate (0-24 hour) manual timer shall be provided for
switching from normal float charge to boosting charge, after
manually set boosting recharge time, the charge function shall
automatically return to float charge.
One (1) selector switch for floating and boosting charge at front
mounted.
A 0-24 hour manual high-rate timer for time setting of boost
charge. An AC input "ON-OFF" and dc output "ON-OFF" molded
case
breaker.
One (1) AC-Voltmeter, class
1.0. One (1) AC-Ammeter,
class 1.0. One (1) DC-
Voltmeter, class 1.0. One (1)
DC-Ammeter, class 1.0.
One (1) DC Volt Selector switch (Charger output, Loading,
Battery). One (1) DC Amp Selector switch (Charger output,
Loading, Battery). One (1) pilot lamp to show that charger input
4.13.2.4.1. The battery charger shall be housed in heavy gauge sheet metal
enclosure of modern design with finish approved by CSCI
Engineering Department.
4.13.2.4.2. The battery charger panel shall be arranged for floor mounting
and shall be of dustproof construction. The front panel of cabinet
shall be provided with hinged swing door on which shall be
mounted meters, relays, selector switches, change over switches,
pilot lamps and other instruments.
4.13.3 Battery
The battery shall be made in a manner to seal out dust and dirt.
4.13.3.2.1. The voltage of battery cell at the end of discharge period shall not
be less than 1.8V at 25℃, including the resistance drop of one
inter-cell connector in series with the cell.
4.13.3.2.2. The positive (Clad type) and negative (lead alloy Grid) straps
shall be extra heavies to assure good conductivity and shall have a
sturdy terminal post with copper insert for extra conductivity. The
cells shall be equipped with a perfect and lasting seal, where the
post is fitted through the cover.
4.13.3.3.2. The cells shall be located on the rack to two or three step within
easy reach and at a convenient height. Racks will be accessible
from one side.
4.13.3.3.3. The racks shall be steel seal type and resistant to the chemical
attack of the electrolyte, and it shall be capable of withstanding
earthquake. Shock and they shall permit easy maintenance and
cleaning of the battery and the battery room floor.
4.13.3.3.5. The racks shall be painted with two coatings of acid resisting
paint and shall be easy to assemble. Contractor shall submit for
CSCI Engineering Department approval the type of paint he
proposes to use.
4.13.3.3.6. The Contractor shall also supply bolts, nuts and washers plated
with acid resisting material to fasten the rack to the floor.
When UPS has trouble, the automatic transfer switch shall automatically
shift from inverter supply to by-pass supply within four (4) milliseconds.
The transfer time from by-pass supply to inverter supply shall also be
within four (4) milliseconds.
The battery charger shall supply the full-load input to the inverter, and
"float" recharge the batteries as required.
The system output capacity shall be 1.25 times of maximum load at 0.8
power factor.
Battery reserve capacity shall be for not less than 60 minutes after
sustained 415V AC power failure.
The input power supply will be three phase 415V ±10% voltage
variation and 50 Hz ±5% frequency variation.
The output for the inverter of UPS system shall be 240V ±2% voltage
regulation and 50 Hz ±1% frequency regulation.
The charger shall be operated between no load and full load within AC
input voltage variation of 10%, and frequency variation of 5%.
The charger shall have the functions of float charge and equalizing
The charger shall consist of but not less than the following components:
4.15.3 Batteries
When the input 415V AC power fails, the battery will supply the critical
load via the inverter. The battery shall have a capacity to deliver full
current at inverter rated output for 1 hour.
Solid state inverter section convert the rectifier DC output to 240V AC,
single phase, 50 Hz, 2 wire output with a separated protection earth wire.
The inverter shall be composed of IGBT power transistors controlled
utilizing a pulse-width modulation (PWM) design. Inverter shall be
equipped with internal starting control, current limit control, voltage and
frequency control, circuits for synchronizing inverter output frequency
with AC line frequency and DC input circuit breaker.
(1) Capacity:
1.25 times of maximum load at 0.8 P.F. continuous and capable of
switching or starting into any loads without improper balance or
operation within the specified rating.
(2) AC output:
Shall be maintained within ±2% over the range of battery voltage
from equalizing level under any load conditions.
(6) Overload:
Automatic current limit shall be furnished to protect the inverter
against overloads or short circuits at the output.
(7) Starting:
The inverter shall be capable of starting into any load to obtain
full output voltage within 1/4 cycle.
(10) Efficiency:
The inverter efficiency shall be 80% Min. at full load 75% Min.
at half load
(11) The inverter shall include but not less than the following
accessories:
a. DC input breaker
b. AC output breaker
c. AC output voltmeter d. AC output ammeter
e. AC output under voltage relay to provide local indication and
remote alarm in case of inverter malfunction.
The system shall include automatic AC load transfer switch and manual
by-pass switch with overlapping contacts. The by-pass circuit is provided
to allow the critical load to be transferred from the inverter to the 380V
AC power system. This transfer operation shall be performed
automatically by means of static switching by-pass feature. Automatic
breaker cross-interlocking performed electrically, to prevent paralleling
of non-synchronized lines.
4.15.7 The 240V 50Hz, UPS system shall cover the following equipments:
4.16.2.1 The Contractor shall take full responsibility for the system design,
and equipment and construction engineering design. Studies and
calculations shall be performed to substantiate the equipment
selection and system configuration.
4.16.3.1 The fire fighting pump shall be furnished and installed for the
work. The pump power source shall be fed from other commercial
power system or Diesel Engine Generator power supply system.
4.16.3.2 The alarm system shall consist of control panels and detectors.
4.17.1.1 The site shall be forced air ventilation with filter as following:
The Contractor shall take full responsibility for the system design, and
equipment and construction engineering design. Studies and calculations
shall be performed to substantiate the equipment selection and system
configuration.
The quantity of air conditioner for 33kV/11kV GIS room and control
room shall be two (2) sets respectively. The temperature shall be under
30℃ when only one (1) set is in service and under 25℃ when two (2)
sets
are in service. The cooling tower systems or water chilling systems shall
be of two (2) sets as well.
4.17.2 Drawings
4.18.1 The Contractor shall furnish an overhead crane including the design,
manufacture, assembly, testing, delivery, installation, commissioning,
supervision and guarantee for 220kV GIS maintenance.
4.18.2 The Contractor shall take full responsibility to get certificate and
approval of governmental organization in India, if required.
4.18.4 EOT crane specification shall comply with the standards of CNS, JIS,
ANSI, IEC or DIN.
4.19.1 Grounding
The ground bus shall be soft drawn or medium hard drawn copper wire
or copper bar, not smaller than 100 mm2 in cross sectional area.
Design and furnish lightning protection system. The protection area shall
cover all the battery limit of Main Substation.
The power rating shall be 240V 50Hz single phase for daily use.
High pressure sodium lamps shall be designed and furnished for open
area as required.
5.2.1 Conductor
5.2.3 Insulation
Extruded black PVC compound shall be applied over the binder. The
minimum thickness shall be not less than 80% of the specified value.
5.2.9 SF6 gas sealing ends/terminations and outdoor type air sealing ends /
terminations.
Bushing and packing etc. for cable sealing end/termination directly
connected to GIS shall be of the type and the size suitable for use with
SF6 gas. The minimum operation pressure of SF6 gas will be
2.5kg/cm2. The Contractor shall fully coordinate with GIS and power
transformer suppliers for the terminal connection and mounting, plug-
in type is preferable in GIS side. Bushing and packing etc. for cable
sealing end/termination directly connected to the incoming
overhead transmission line shall be of outdoor type air sealing end and
the size suitable for use with transmission line conductor. The
Contractor shall fully coordinate with IPC for the terminal
connection and mounting.
(1) The Bidder shall state in his proposal the reasons for selection
of the type, which the Bidder recommends, and the induced
voltage calculations to justify one-end, or both-ends are to be
grounded with the device. If the Bidder provides one-end
grounded system then each open end of the cable shield shall
be grounded through protective device.
(2) The Bidder shall provide a suitable type of
protective/grounding device such as arrester or means, if
necessary.
(3) The protective/grounding devices shall be properly mounted to
the support structures and placed under the oil-immersed
sealing ends, SF6 gas sealing ends and outdoor air sealing ends.
(4) The device and the exposed metallic shielding of the cable shall
be adequately protected with suitable covers to keep operators
and other people from touching.
(5) The valve elements of protective device shall be of the
non-linear resistor type and shall be made of zinc oxide
compound. Its characteristics shall be stated in Section
5.2.1.6.16. The non-linear resistors must be protected
from moisture in a suitable case or encapsulation, and
shall be enclosed in watertight link box. The link box
shall be gantry-mounted type. All link bars shall be designed
removable to facilitate cable jacket integrity test.
One (1) set of each completed cable shall be made the following tests at
the factory in accordance with ASTM, IEC, ICEA-NEMA S-66-524 and
AEIC CS-7 Standards unless otherwise specified herein.
5.3.1.2 Bid shall include all data requested in attached proposal data sheets.
5.3.1.3 Whenever material proposed by the bidder cannot satisfactorily meet the
intent of the Specifications, in any respect, such exceptions must be
clearly stated in the Proposal. No exceptions are allowed unless
specifically granted by the Purchaser in writing.
5.3.2.1 Standards
5.3.2.1.1 All design, materials, tests and fabrication, as well as electrical and
physical characteristics of the cable shall conform to IEC Pub. 60502-
2/1997, But Partial discharge equal or less 2 piko coulomb at 2.0 Uo
according to VDE 0276-620.
5.3.2.2.1 The Contractor shall make himself aware of the related weather,
earthquake and environmental conditions… etc in Dahej-2 Industrial
estate of Gujurat province in India.
5.3.2.3.1 The external surface of the cable shall be in red color and shall be
durably marked throughout its length with the manufacturer's
identification, type of the cable insulation (e.g. XLPE), conductor
material and size of the conductor, rated voltage, year of manufacturer
and Purchaser's identification (i.e. CSCI Engineering Department).
5.3.2.3.2 The cable identification shall be repeated along the cable at regular
interval of one meter. For identification of the remaining cable length in
cable drum. Length of the cable from the inner end of the drum shall be
exactly marked at each one meter together with the identification with 4
or 5 digits. The inner end digits shall be clearly marked on the cable
drum. The digits shall be continuous for the same conductor size in one
drum.
5.3.2.4 Guarantee
5.3.2.4.1 The manufacturer shall guarantee that, the cable furnished under this
specification is of first-class material and workmanship throughout, that
it has been tested in accordance with the specification, and that the
results of the tests comply with the requirements of this specification. In
5.3.2.4.4 Except as otherwise agreed, length of cable which has been replaced
under provision of this specification, shall become the property of
the manufacturer and shall be returned by the purchaser to the
manufacturer at CSCI Engineering Department's installation site.
5.3.2.5 Inspection
5.3.2.5.2 The manufacturer shall afford, without charge, all necessary and
reasonable facilities required by the inspector for the performance of
inspection required.
5.3.2.6 Packing
5.3.2.6.1 The cable shall be packed on standard non-returnable wooden reels with
the cable ends properly sealed to prevent entering of moisture.
Maximum cable length per reel shall be 1,400 meters. Plywood reels are
not acceptable. Individual cable lengths are valid with +/- 2% tolerance.
5.3.2.6.1 Cable reels, shall be properly constructed to protect the cable assembly
from damage during transport and subsequent handling.
The stranded conductor shall be clean, uniform in size and shape, and its
surface shall be free from sharp edges.
5.4.1.4 Insulation
Cables shall have a PVC outer sheath and its average thickness shall be
not less than the specified standard value.
6.1 The following list Spare Parts items shall be supplied by the Contractor.
The Contractor shall provide to CSCI Engineering Department before
system commissioning.
Item
Description and Function Unit Quantity Remark
NO.
2.6. Fuse PC 10
MCCB
2.7. PC 2
3.6 Fuse PC 10
3.7 MCCB PC 2
7. SCADA System
8.1. Hydrometer PC 2
11. UPS
6.2 The Contractor shall provide special tools and test equipment required
to service CSCI Engineering Department (including PC and extender
boards, special plugs, adapters, sockets and cable connection tool, etc).
The Contractor shall furnish a list of special tools and test equipment
and submit to CSCI Engineering Department for approval before the
system commissioning.
Any damage of all equipment, material, test equipment and any other
which are supplied by contractor shall be contractor’s responsibility.
8.2 Exceptions
Bidder shall clearly state all exceptions, if any, to any part of this
Specification. Any statement on the Bidder's proposal (including
drawings) which differs from the requirements of this Specification shall
be specifically referred to by a definite citation in a "Statement of
Exceptions" to be considered by CSCI 220kV Main Substation First
Floor Plan Layout Diagram
Appendix two Dwg No. Q100306-37-EN-0001 Rev. A
Appendix two 220kV Main Substation BF & 2F & 3F PLAN Layout
Diagram Dwg No. Q100306-37-EN-0002 Rev. A
as constituting an exceptions shall be included in the "Statement of
Exception".
Western Europe
2 33kV Gas insulated switchgear(GIS) Siemens,ABB,Schneider North America ,Japan
Western Europe
3 11kV Gas insulated switchgear(GIS) Siemens,ABB,Schneider North America ,Japan
Western Europe
11kV power factor and harmonic
4 Siemens,ABB,Schneider North America ,Japan
improvement equipment
Western Europe
6 415V Switchgear Panel Siemens,ABB,Schneider North America ,Japan
Western Europe
Shihlin,Tatung, Siemens,
7 220kV/33kV power transformers North America ,Japan
ABB, Schneider
Taiwan
Western Europe
Shihlin,Tatung, Siemens,
8 33kV/11kV power transformers North America ,Japan
ABB, Schneider
Taiwan
Western Europe
Shihlin,Tatung, Siemens,
9 11kV/415V power transformers North America ,Japan
ABB, Schneider
Taiwan
Western Europe
10 Protection relay Siemens, ABB, Alstom North America ,Japan
Western Europe
Siemens, ABB, Alstom,
11 Batteries and battery chargers North America ,Japan
福峰工業
Taiwan
Western Europe
12 SCADA system equipment Siemens, ABB, Alstom North America ,Japan