Professional Documents
Culture Documents
8.50 Lacks Pipeline Corrected
8.50 Lacks Pipeline Corrected
Sl.N M.A @
Item Unit Rate Total
o 20%
1 Mason 1st class Each 350.00 70.00 420.00
2 Mason 2nd Class Each 320.00 64.00 384.00
3 Mazdoor (Unskilled) Each 280.00 56.00 336.00
4 Mate Each 280.00 56.00 336.00
5 Bar Bender Each 370.00 74.00 444.00
6 Painter Cl.1 Each 400.00 80.00 480.00
7 Painter CL.2 Each 320.00 64.00 384.00
HIRE CHARGES
Sl. Rate of
Name of the Minor Mineral Unit
No. Seigniorage Fee
1 Building Stone M³ 50.00
2 Rough Stone/Boulders M³ 50.00
3 Road Metal & Ballast M³ 50.00
4 Muram/Gravel & Ordinary earth M³ 22.00
Ordinary sand / Sand manufactured
5 from Boulders useful for Civil M³ 40.00
construction
CONVEYANCE CHARGES
(Lead)
(Lead) (Lead)
(Lead) charges
charges charges
charges for
for for
for trucks trucks
trucks trucks
and and (Lead)
and and (Lead)
tippers tippers charges
tippers tippers charges
for per for trucks
for for for
Cement/ cu.meter and
Sl Earth / Rubble/S trucks
Distance Steel/ for PCC tippers
No. Sand ize per
RCC slabs/ per
/Gravel / stones/ 1000
poles/ AC Shahaba cu.meter
Murrum/ Cut nos. of
& GI d slabs/ water/
Lime/ Stones/ bricks
sheets/ CC & 1000 litres
Surki/ Coarse
Packed Laterite
per aggrega
materials blocks/
cu.mete te per
/tonne Wood/
r cu.meter
cum
1 2 3 4 5 6 7 8
1 Lead up to 1 km 30.00 28.90 18.00 42.40 17.80 48.10
2 Lead up to 2 km 42.00 40.40 25.30 59.40 24.90 67.30
3 Lead up to 3 km 56.00 56.00 35.00 82.40 33.20 89.80
4 Lead up to 4 km 68.00 68.00 42.50 100.00 40.30 109.00
5 Lead up to 5 km 80.00 80.00 50.00 117.70 47.40 128.30
6 for Every km beyond 5 km up to 30 km 12.00 12.00 7.50 17.60 7.10 19.20
7 for Every km beyond 30 km 10.00 10.00 6.30 14.70 5.90 16.00
DATA4
DATA
Common Standard Schedule of Rates For The Year:2013-14
BLD-CSTN-2-2 10 Plain Cement concrete Grade M10 - Nominal Mix upto Plinth level
using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement Kg 220.00 #REF! #REF!
Coarse aggregate 40mm cum 0.90 #REF! #REF!
Fine aggregate (Sand) cum 0.45 #REF! #REF!
Water (including for curing) kl 1.20 100.00 120.00
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00 303.10 303.10
capacity sl no.18 of hire charges of common ssr
C. LABOUR:
Mason 1st class day 0.10 350.00 35.00
Mazdoor (unskilled) day 1.39 280.00 389.20
Add for labour allowance 20% on Rs. 424.20 84.84
#REF!
Over heads and conractor profit 14% #REF!
Seigniorage charges for C.A Cum 0.90 50.00 45.00
Seigniorage charges for F.A Cum 0.45 40.00 18.00
Grand Total #REF!
BLD-CSTN-2-5 13 Plain Cement concrete (1:4:8) using 40 mm metal with concrete mixture. All work
upto plinth level.
Unit = 1cum
A. MATERIALS:
Cement kg 162.00 #REF! #REF!
Coarse aggregate 40 mm cum 0.90 #REF! #REF!
Fine aggregate (Sand) cum 0.45 #REF! #REF!
Water (including for curing) kl 1.20 100.00 120.00
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00 303.10 303.10
capacity
C. LABOUR:
Mason 1st class day 0.10 350.00 35.00
Mazdoor (unskilled) day 1.39 280.00 389.20
Add for labour allowance 20% on Rs. 424.20 84.84
#REF!
Water Charges 1% 1.00 % #REF!
#REF!
Over heads and conractor profit 14% #REF!
Seigniorage charges for C.A Cum 0.90 50.00 45.00
Seigniorage charges for F.A Cum 0.45 40.00 18.00
Total per 1Cum #REF!
BLD-CSTN-2-7 15 Plain Cement concrete (1:5:10) using 40 mm metal with Concrete mixture. All work upto
plinth level.
Unit = 1cum
A. MATERIALS:
Cement kg 129.60 #REF! #REF!
Coarse aggregate 40 mm cum 0.90 #REF! #REF!
Fine aggregate (Sand) cum 0.45 #REF! #REF!
Water (including for curing) kl 1.20 100.00 120.00
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00 303.10 303.10
capacity
C. LABOUR:
Mason 1st class day 0.10 350.00 35.00
Mazdoor (unskilled) day 1.39 280.00 389.20
Add for labour allowance 20% on Rs. 424.20 84.84
Grand Total #REF!
Over heads and conractor profit 14% #REF!
Seigniorage charges for C.A Cum 0.90 50.00 45.00
Seigniorage charges for F.A Cum 0.45 40.00 18.00
DATA7
BLD-CSTN-2-10 17 Plain Cement concrete (1:2:4) using 20 mm metal with Concrete mixture
Unit = 1cum
A. MATERIALS:
Cement kg 330.00 #REF! #REF!
Coarse aggregate 20 mm cum 0.90 #REF! #REF!
Fine aggregate (Sand) cum 0.54 #REF! #REF!
Water (including for curing) kl 1.20 100.00 120.00
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00 303.10 303.10
capacity
C. LABOUR:
Mason 1st class day 0.10 350.00 35.00
Mazdoor (unskilled) day 1.39 280.00 389.20
Add for labour allowance 20% on Rs. 424.20 84.84
Grand Total #REF!
Over heads and conractor profit 14% #REF!
Seigniorage charges for C.A Cum 0.90 50.00 45.00
Seigniorage charges for F.A Cum 0.54 40.00 21.60
Total per 1Cum #REF!
BLD-CSTN-2-11 19 Plain Cement concrete (M 20) Nominal Mix using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement Kg 330.00 #REF! #REF!
Coarse aggregate 40mm graded cum 0.90 #REF! #REF!
Fine aggregate (Sand) cum 0.45 #REF! #REF!
Water (including for curing) kl 1.20 100.00 120.00
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 1.00 303.10 303.10
capacity
C. LABOUR:
Mason 1st class day 0.10 350.00 35.00
Mazdoor (unskilled) day 1.39 280.00 389.20
Grand Total #REF!
Over heads and conractor profit 0.14 #REF!
Seigniorage charges for C.A Cum 0.90 50.00 45.00
Seigniorage charges for F.A Cum 0.45 40.00 18.00
Total per 1Cum #REF!
Plain Cement Concrete corresponding to M7.5 grade as per IS 456 equivalent to (1:4:8)
proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm size Hard
Blasted Granite (IS383, 1970) graded metal from approved quarry including cost and
conveyance of all materials like cement, sand, coarse aggregate, water etc. to site,
including seigniorage charges, sales & other taxes on all materials, all operational,
incidental, and labour charges such as mixing, laying and ramming concrete in layers in
position not exceeding 15cm, finishing top surface, curing concrete, etc., complete for
finished item of work for )Foundations (APSS No. 402
Unit-1 cum
Taking out put =
A. MATERIALS:
Cement kg 162.00 #REF! #REF!
Coarse aggregate 40mm graded cum 0.90 #REF! #REF!
DATA8
C. LABOUR:
Mason 1st class day 0.10 350.00 35.00
Mason 2nd class day 0.28 320.00 89.60
Mazdoor (un skilled) day 1.39 280.00 389.20
Add 20% MA 102.76
Total #REF!
Add @ 4% for framed work #REF!
#REF!
Add overheads and contractors profit @14% #REF!
Plain Cement Concrete corresponding to M10 grade as per IS 456 equivalent to (1:3:6)
proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 20mm size Hard
Blasted Granite (IS383, 1970) Machine Crushed graded metal from from approved quarry
including cost and conveyance of all materials like cement, sand, coarse aggregate, water
etc. to site, including seigniorage charges, sales & other taxes on all materials, all
operational, incidental and labour charges such as mixing, laying, curing concrete, etc.,
complete for finished item of work for Bed Blocks and Hold Fasts (APSS No. 402)
Unit-1 cum
Taking out put =
A. MATERIALS:
Cement kg 220.00 #REF! #REF!
Coarse aggregate 40mm graded cum 0.90 #REF! #REF!
Fine aggregate (sand) cum 0.45 #REF! #REF!
Water (incluidng for curing) Kl 1.20 100.00 120.00
B. MACHINERY
Concrete Mixer 10/7 cft (0.2/0.8 cum) capacity hour 0.40 303.10 121.24
C. LABOUR:
Mason 1st class day 0.10 350.00 35.00
Mazdoor (un skilled) day 1.39 280.00 389.20
Add 20% MA 84.84
Total #REF!
Add @ 4% for framed work #REF!
#REF!
Add overheads and contractors profit @14% #REF!
BLD-CSTN-2-14 22 Vibrated Reinforced Cement Concrete M25 grade using 20 mm GRADED HBG crushed
stone aggregate(Coarse aggregate conforming to table 1000-1 and fine aggregated
confirming to table 1000-2 including cost , seigniorage conveyance of all materials to
site and labour charges ,centring ,Machine mixing ,laying ,vibrating , curing etc.,
including other incidental hire and operational charges of all T&P as per approved
drawings and as directed during execution but excluding cost of steel and its fabrication
charges for finished item as per MORT&H specification 1500,1600,1700,&2200 (4th
revision) and as directed by the Engineer-in-Charge for cover slabs over side drains
B. LABOUR:
1st Class Mason day 0.100 350.00 35.00
2nd Class Mason day 0.280 320.00 89.60
Mazdoor (Both Men and Women) day 1.390 280.00 389.20
Add for labour allowance 20% on Rs. 513.80 102.76
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 0.400 303.10 121.24
capacity sl no.18 p/130
Water (including for curing) kl 1.200 100.00 120.00
Centering hire charges cum 1.000 62.00 62.00
Labour charges for centering cum 1.000 372.00 372.00
Add for labour allowance 20% on Rs. 372.00 74.40
#REF!
Over heads and conractor profit 14% #REF!
Seigniorage charges for C.A Cum 0.82 50.00 41.00
Seigniorage charges for F.A Cum 0.39 40.00 15.60
Total per 1Cum #REF! /Cum
Basic rate
A. MATERIALS:
20mm HBG graded metal cum 0.820 #REF! #REF!
Sand cum 0.390 #REF! #REF!
Cement Kgs 380.000 #REF! #REF!
#REF!
B. LABOUR:
1st Class Mason day 0.167 350.00 58.45
2nd Class Mason day 0.167 320.00 53.44
Mazdoor (Both Men and Women) day 5.600 280.00 1568.00
Add for labour allowance 20% on Rs. 1679.89 335.98
2015.87
C. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 0.400 303.10 121.24
capacity
Water (including for curing) kl 1.200 100.00 120.00
241.24
Seigniorage charges for C.A Cum 0.82 50.00 41.00
Seigniorage charges for F.A Cum 0.39 40.00 15.60
Total : A+B+C Rs. #REF!
a) Ground floor columns
Basic Rate cum 1.00 #REF! #REF!
Centering hire charges page no.76 cum 1.00 134.00 134.00
Labour charges for centering cum 1.00 1070.00 1070.00
Add for labour allowance 20% on Rs. 1070.00 214.00
#REF! Cum
Over heads and conractor profit 14% #REF!
Total per 1Cum #REF! /1Cum
b) 1st floor columns
Basic rate cum 1.00 #REF! #REF!
Lift charges on labour 10.00 % on 1679.89 167.99
Centering hire charges cum 1.000 134.00 134.00
Labour charges for centering cum 1.000 1070.00 1070.00
Add for labour allowance 20% on Rs. 1070.00 214.00
Rate per 1 Cum #REF!
Over heads and conractor profit 14% #REF!
Total per 1Cum #REF! /Cum
c) 2nd floor columns
Basic rate of ground floor Cum 1.00 #REF! #REF!
Lift charges on labour 20.00 % on 1679.89 335.98
Lift charges for lifting concrete by hiring lift @ Hrs 1.33 200.00 266.00
Rs.1600/day ( 8 hours)
Centering hire charges cum 1.000 134.00 134.00
Labour charges for centering cum 1.000 1865.00 1865.00
Add for labour allowance 20% on Rs. 1865.00 373.00
Rate per 1 Cum #REF!
Over heads and conractor profit 14% #REF!
Total per 1Cum Rs. #REF! /Cum
c) 3rd floor columns
Basic rate of ground floor Cum 1.00 #REF! #REF!
Lift charges on labour 30.00 % on 1679.89 503.97
Lift charges for lifting concrete by hiring lift @ Hrs 1.33 200.00 266.00
Rs.1600/day ( 8 hours)
Centering hire charges cum 1.000 134.00 134.00
Labour charges for centering cum 1.000 2034.00 2034.00
Add for labour allowance 20% on Rs. 2034.00 406.80
Rate per 1 Cum #REF!
Over heads and conractor profit 14% #REF!
Total per 1Cum Rs. #REF! /Cum
d) 4th floor columns
Basic rate of ground floor Cum 1.00 #REF! #REF!
Lift charges on labour 40.00 % on 1679.89 671.96
Lift charges for lifting concrete by hiring lift @ Hrs 1.33 200.00 266.00
Rs.1600/day ( 8 hours)
Centering hire charges cum 1.000 134.00 134.00
DATA11
a Ground floor
Basic rate cum 1.00 #REF! #REF!
Centering hire charges page no.76 cum 1.000 890.00 890.00
Labour charges for centering cum 1.000 762.00 762.00
Add for labour allowance 20% on Rs. 762.00 152.40
A+B+C #REF!
Over heads and conractor profit 14% #REF!
Total per 1Cum #REF!
b) 1st floor lintels
Basic rate of ground floor 1.00 Cum #REF! #REF!
Lift charges on labour 10.00 % on 2015.87 201.59
Centering hire charges cum 1.000 890.00 890.00
Labour charges for centering cum 1.000 762.00 762.00
Add for labour allowance 20% on Rs. 762.00 152.40
Rate per 1 Cum #REF!
Over heads and conractor profit 14% #REF!
Total per 1Cum #REF! /Cum
c) 2nd floor lintels
Basic rate of ground floor 1.00 Cum #REF! #REF!
Lift charges on labour 20.00 % on 2015.87 403.17
Lift charges for lifting concrete by hiring lift @ Hrs 1.33 200.00 266.00
Rs.1600/day ( 8 hours)
Centering hire charges cum 1.000 890.00 890.00
Labour charges for centering cum 1.000 1328.00 1328.00
Add for labour allowance 20% on Rs. 1328.00 265.60
Rate per 1 Cum #REF!
Over heads and conractor profit 14% #REF!
DATA12
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) hour 0.31 303.10 93.35
capacity
Water (including for curing) kl 1.20 100.00 120.00
213.35
A+B+C Rs. #REF! /1Cum
Slab rate per 10Sqm
I) Slab thickness 125.00 mm
a) Ground floor slabs
1.25 Cum Basic rate of slab 1.00 Cum #REF! #REF!
10 Sqm cetering hire charges 1.00 sqm 151.00 1510.00
10 Sqm labour charges for centering charges 1.00 sqm 101.00 1010.00
Add for labour allowance 20% on Rs. 1010.00 202.00
#REF!
Over heads and conractor profit 14% #REF!
Total per 1Cum Rs. #REF! /10sqm
10 Sqm labour charges for centering charges 1.00 sqm 101.00 1010.00
Add for labour allowance 20% on Rs. 1010.00 202.00
#REF!
Over heads and conractor profit 14% #REF!
Total per 1Cum Rs. #REF! /10sqm
10 Sqm labour charges for centering charges 1.00 sqm 105.00 1050.00
Add for labour allowance 20% on Rs. 1050.00 210.00
#REF!
Over heads and conractor profit 14% #REF!
Total per 1Cum Rs. #REF! /10sqm
c) 2nd floor slabs
2.5 Cum Basic rate of slab 1.00 Cum #REF! #REF!
2.5 Cum Lift charges for lifting materials 20.00 % on 1113.08 556.54
10 Sqm cetering hire charges 1.00 sqm 157.00 1570.00
10 Sqm labour charges for centering charges 1.00 sqm 183.00 1830.00
Add for labour allowance 20% on Rs. 1830.00 366.00
#REF!
Over heads and conractor profit 14% #REF!
Total per 1Cum Rs. #REF! /10sqm
d) 3rd floor slabs
2.5 Cum Basic rate of slab 1.00 Cum #REF! #REF!
2.5 Cum Lift charges for lifting materials 30.00 % on 1113.08 834.81
10 Sqm cetering hire charges 1.00 sqm 157.00 1570.00
10 Sqm labour charges for centering charges 1.00 sqm 199.00 1990.00
Add for labour allowance 20% on Rs. 1990.00 398.00
#REF!
Over heads and conractor profit 14% #REF!
Total per 1Cum Rs. #REF! /10sqm
e) 4th floor slabs
2.5 Cum Basic rate of slab 1.00 Cum #REF! #REF!
2.5 Cum Lift charges for lifting materials 40.00 % on 1113.08 1113.08
10 Sqm cetering hire charges 1.00 sqm 157.00 1570.00
10 Sqm labour charges for centering charges 1.00 sqm 216.00 2160.00
Add for labour allowance 20% on Rs. 2160.00 432.00
#REF!
Over heads and conractor profit 14% #REF!
Total per 1Cum Rs. #REF! /10sqm
f) 5th floor slabs
2.5 Cum Basic rate of slab 1 Cum #REF! #REF!
2.5 Cum Lift charges for lifting materials 50 % on 1113.08 1391.35
10 Sqm cetering hire charges 1 sqm 157.00 1570.00
10 Sqm labour charges for centering charges 1 sqm 232.00 2320.00
Add for labour allowance 20% on Rs. 2320.00 464.00
#REF!
Over heads and conractor profit 14% #REF!
Total per 1Cum Rs. #REF! /10sqm
III) Slab thickness 175 mm
a) Ground floor slabs
1.75 Cum Basic rate of slab 1.00 Cum #REF! #REF!
10 Sqm cetering hire charges 1.00 sqm 157.00 1570.00
10 Sqm labour charges for centering charges 1.00 sqm 105.00 1050.00
Add for labour allowance 20% on Rs. 1050.00 210.00
#REF!
Over heads and conractor profit 14% #REF!
Total per 1Cum Rs. #REF! /10sqm
1000 Unit = t
& (a) Material
1200 HYSD bars including 5 per cent for overlaps and t 1.05 #REF! #REF!
wastage
Binding wire sl no.3 p/12 kg 6.00 70.00 420.00
(b) Labour for cutting, bending, shifting to site,
tying and placing in position
Blacksmith / Bar bender sl no.2 day 10.00 350.00 3500.00
Mazdoor (Unskilled) day 10.00 280.00 2800.00
Add for labour allowance 20% on Rs. 6300.00 1260.00
Sundries on Material 20.00
#REF!
Over heads and conractor profit 14% #REF!
Total per 1Cum #REF! /1kg
1000 Unit = t
& (a) Material
1200 Tubular truss including 5 per cent for overlaps t 1.05 32000.00 33600.00
and wastage
Add VAT @ 12.5 % 4200.00
(b) Labour for fabrication , welding etc sl no.824 T 1.00 12000.00 12000.00
p/68
Add 20% on labour charges 20 % on Rs. 12000.00 2400.00
Total for 1 M.Tonne 52200.00
BLD-CSTN-3-4 32 Reinforced Brick Masonary walls of 11.5cm in CM(1:4) using Modular bricks having a
crushing strength of not less than 35.00kg/cm2 and using two mild steel bars of 6m dia
in every third layer of brick masory, with free joints of the main block work including
cost and seignorage charges and conveyance of all materials and water from approved
sources to work site and all operational, incidental, labour charges such as scaffolding
mixing mortor constructing masonary lift charges, curing etc. complete but excluding
the cost of steel and its fabrication charges for finished item of work as per SS 509
Basic rate
A. MATERIALS:
II Class Bricks cum 512.000 #REF! #REF!
C.M.(1:4) cum 0.200 #REF! #REF!
DATA20
B. LABOUR:
Mason 1st class day 0.600 350.00 210.00
Mason 2nd class day 0.600 320.00 192.00
Mazdoor (unskilled) day 2.750 280.00 770.00
Add for labour allowance 20% 1172.00 234.40
Total #REF! 1cum
I) Wall thickness 115 mm
Area of scaffolding in sqm 8.7
a Ground floor
1 Cum Basic rate cum 1.00 #REF! #REF!
8.70 sqm scaffolding hire charges Sqm 1.00 5.46 47.50
8.70 sqm scaffolding hire charges Sqm 1.00 40.43 351.74
Add for labour allowance 20% 351.74 70.35
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /1Cum
Rs. #REF!
b 1st floor
1 Cum Basic rate cum 1.00 #REF! #REF!
lift charges 10.00 % 351.74 35.17
8.70 sqm scaffolding hire charges Sqm 1.00 5.46 47.50
8.70 sqm scaffolding hire charges Sqm 1.00 40.43 351.74
Add for labour allowance 20% 351.74 70.35
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /1Cum
Rs. #REF!
c 2nd floor
1 Cum Basic rate cum 1.00 #REF! #REF!
lift charges 20.00 % 351.74 70.35
8.7 sqm scaffolding hire charges Sqm 1.00 5.46 47.50
8.70 sqm scaffolding hire charges Sqm 1.00 60.65 527.66
Add for labour allowance 20% 527.66 105.53
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /1Cum
Rs. #REF!
d 3rd floor
1 Cum Basic rate cum 1.00 #REF! #REF!
lift charges 30.00 % 351.74 105.52
8.7 sqm scaffolding hire charges Sqm 1.00 5.46 47.50
8.70 sqm scaffolding hire charges Sqm 1.00 80.86 703.48
Add for labour allowance 20% 703.48 140.70
997.20
Over heads and conractor profit 14% 139.61
Grand Total Rs. #REF! /1Cum
Rs. #REF!
e 4th floor
1 Cum Basic rate cum 1.00 #REF! #REF!
lift charges 40.00 % 351.74 140.70
8.7 sqm scaffolding hire charges Sqm 1.00 5.46 47.50
8.70 sqm scaffolding hire charges Sqm 1.00 101.08 879.40
Add for labour allowance 20% 879.40 175.88
1243.48
Over heads and conractor profit 14% 174.09
Grand Total Rs. #REF! /1Cum
Rs. #REF!
f 5th floor
1 Cum Basic rate cum 1.00 #REF! #REF!
lift charges 50.00 % 351.74 175.87
8.7 sqm scaffolding hire charges Sqm 1.00 5.46 47.50
8.70 sqm scaffolding hire charges Sqm 1.00 121.29 1055.22
Add for labour allowance 20% 1055.22 211.04
1489.64
Over heads and conractor profit 14% 208.55
DATA21
a Unit = 1cum
i A. MATERIALS:
Cement kg 72.00 #REF! #REF!
Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 #REF! #REF!
iv Brick Masonry in CM (1:6) with 23 x 11 x 7cms size Bricks in CM(1:4) having a crushing
strength of not less than 35.00kg/cm2 including cost and seignorage charges and conveyance of
all materials and water from approved sources to work site and all operational, incidental, labour
charges such as scaffolding mixing mortor constructing masonary lift charges, curing etc.
complete for finished item of work as per SS 509
Unit = 1cum
Basic rate
A. MATERIALS:
Cement kg 48.00 #REF! #REF!
Bricks traditional size 23 x 11 x 7 cms 2nd class Nos 512.00 #REF! #REF!
Rs. #REF!
c 2nd floor
1 Cum Basic rate cum 1.00 #REF! #REF!
lift charges 20.00 % 792.40 158.48
4.35 sqm scaffolding hire charges Sqm 1.00 5.46 23.75
4.35 sqm scaffolding hire charges Sqm 1.00 60.65 263.83
Add for labour allowance 20% 263.83 52.77
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /1Cum
Rs. #REF!
d 3rd floor
1 Cum Basic rate cum 1.00 #REF! #REF!
lift charges 30.00 % 792.40 237.72
4.35 sqm scaffolding hire charges Sqm 1.00 5.46 23.75
4.35 sqm scaffolding hire charges Sqm 1.00 80.86 351.74
Add for labour allowance 20% 351.74 70.35
683.56
Over heads and conractor profit 14% 95.70
Grand Total Rs. #REF! /1Cum
Rs. #REF!
e 4th floor
1 Cum Basic rate cum 1.00 #REF! #REF!
lift charges 40.00 % 792.40 316.96
4.35 sqm scaffolding hire charges Sqm 1.00 5.46 23.75
4.35 sqm scaffolding hire charges Sqm 1.00 101.08 439.70
Add for labour allowance 20% 439.70 87.94
868.35
Over heads and conractor profit 14% 121.57
Grand Total Rs. #REF! /1Cum
Rs. #REF!
f 5th floor
1 Cum Basic rate cum 1.00 #REF! #REF!
lift charges 50.00 % 792.40 396.20
4.35 sqm scaffolding hire charges Sqm 1.00 5.46 23.75
4.35 sqm scaffolding hire charges Sqm 1.00 121.29 527.61
Add for labour allowance 20% 527.61 105.52
1053.08
Over heads and conractor profit 14% 147.43
Grand Total Rs. #REF! /1Cum
Rs. #REF!
BLD-CSTN-3-4 32 Reinforced Brick Masonary walls of 11.5cm in CM(1:4) using FlyAsh bricks having a
crushing strength of not less than 35.00kg/cm2 and using two mild steel bars of 6m dia
in every third layer of brick masory, with free joints of the main block work including
cost and seignorage charges and conveyance of all materials and water from approved
sources to work site and all operational, incidental, labour charges such as scaffolding
mixing mortor constructing masonary lift charges, curing etc. complete but excluding
the cost of steel and its fabrication charges for finished item of work as per SS 509
Basic rate
A. MATERIALS:
II Class Bricks cum 512.000 0.00 0.00
C.M.(1:4) cum 0.200 #REF! #REF!
B. LABOUR:
Mason 1st class day 0.600 350.00 210.00
Mason 2 nd
class day 0.600 320.00 192.00
Mazdoor (unskilled) day 2.750 280.00 770.00
Add 40% on labour charges 20% % 1172.00 2.34
Total #REF! 1cum
I) Wall thickness 230 mm
Area of scaffolding in sqm 4.35
a Ground floor
1 Cum Basic rate cum 1.00 #REF! #REF!
4.35 sqm scaffolding hire charges Sqm 1.00 5.46 23.75
DATA23
unit:10sqm
A. MATERIALS:
DATA24
Country bricks, second class traditional size nos 565.000 #REF! #REF!
23x11x7cm
Cement kg. 106.000 #REF! #REF!
Sand cum 0.220 #REF! #REF!
B. LABOUR:
Mason 1st class day 0.600 350.00 210.00
Mason 2 nd
class day 0.600 320.00 192.00
Mazdoor (unskilled) day 2.750 280.00 770.00
Add 40% on labour charges 40 % 1172.00 468.80
#REF!
Add water charges 1% 1.00% #REF!
Total #REF!
a Ground Floor :
Basic rate cum 1.000 #REF! #REF!
Over heads and conractor profit 0.14 #REF!
Grand Total #REF! 10sqm
b) 1st floor
Basic rate #REF!
lift charges 10.00 % 1172.00 117.20
centering Hire charges 5.29
labour charges 35.99
Add 40% on labour charges 40 % 35.99 14.40
Grand Total #REF!
Over heads and conractor profit 0.14 #REF!
Grand Total #REF! 10sqm
c) 2nd floor
Basic rate #REF!
lift charges 20.00 % 1172.00 234.40
centering Hire charges 5.29
labour charges 53.99
Add 40% on labour charges 40 % 53.99 21.60
Grand Total #REF!
Over heads and conractor profit 0.14 #REF!
Grand Total #REF! 10sqm
BLD-CSTN-3-4 32 Reinforced Brick Masonary walls of 11.5cm in CM(1:4) using FlyAsh bricks having a
crushing strength of not less than 35.00kg/cm2 and using two mild steel bars of 6m dia
in every third layer of brick masory, with free joints of the main block work including
cost and seignorage charges and conveyance of all materials and water from approved
sources to work site and all operational, incidental, labour charges such as scaffolding
mixing mortor constructing masonary lift charges, curing etc. complete but excluding
the cost of steel and its fabrication charges for finished item of work as per SS 509
Ground Floor :
A. MATERIALS:
II Class Bricks cum 512.000 #REF! #REF!
C.M.(1:4) cum 0.200 #REF! #REF!
B. LABOUR: 0.00
Mason 1st class day 0.600 350.00 210.00
Mason 2nd class day 0.600 320.00 192.00
Mazdoor (unskilled) day 2.750 280.00 770.00
Add 40% on labour charges 40 % 1172.00 468.80
Total #REF! 1cum
Over heads and conractor profit 0.14 #REF!
Grand Total #REF! cum
BLD-CSTN-4-3 39 Construction of in CRS Masonary using 2nd Sort granite stone in Cement Mortor 1:6
Prop using hard granite stone including cost & Conveyance of all materials like Cement,
Sand , Water, Granite Stones, Etc., including Cost of Seigniorage Charges on all
Materials, all taxes including Labour for cutting Stones to required size and shape mixing
of Cement Mortor Construction, Scaffolding Charges curing Etc., Complete for Finished
item of Work . (As per SS 611).P
Unit = 1cum
A. MATERIALS:
Cement kg 76.80 #REF! #REF!
Coursed Rubble Stone cum 0.94 906.92 852.50
DATA25
Unit = 1cum
A. MATERIALS:
Cement kg 79.20 #REF! #REF!
CR Stone cum 0.44 906.92 399.04
Rough Stone cum 0.50 719.92 359.96
Bond Stones cum 0.16 3060.92 489.75
Fine aggregate (Sand) cum 0.33 #REF! #REF!
B. LABOUR:
Mason 1st class day 1.20 350.00 420.00
Mazdoor (unskilled) day 2.00 280.00 560.00
Add 20% on labour charges 20% 980.00 196.00
Grand Total #REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! cum
BLD-CSTN-5 POINTING
BLD-CSTN-5-1 49 Flush Pointing with CM (1:3) to Brick / CRS Masonry
Unit = 10 sqm
A. MATERIALS:
Cement kg 14.40 #REF! #REF!
Fine aggregate (Sand) cum 0.03 #REF! #REF!
B. LABOUR:
Mason 2nd class day 0.50 320.00 160.00
Mazdoor (unskilled) day 0.74 280.00 207.20
Add 40% on labour charges 20% 367.20 73.44
Grand Total #REF! /10sqm
Over heads and conractor profit 0.14 #REF!
Grand Total #REF! /10sqm
BLD-CSTN-5-2 50 Flush Pointing with CM (1:3) to CRS Masonry including cost & Conveyance of all
materials like Cement, Sand , Water etc including Cost of Seigniorage Charges on all
Materials, all taxes including Labour for mixing of Cement Mortor curing etc., Complete
for Finished item of Work .
Unit = 10 sqm
A. MATERIALS:
Cement kg 14.40 #REF! #REF!
Fine aggregate (Sand) cum 0.03 #REF! #REF!
B. LABOUR:
Mason 2nd class day 0.50 350.00 175.00
Mazdoor (unskilled) day 0.74 280.00 207.20
Add 40% on labour charges 20% 382.20 76.44
Grand Total #REF! /10sqm
Over heads and conractor profit 0.14 #REF!
Grand Total #REF! /10sqm
BLD-CSTN-5-3 51 Raised Pointing with CM (1:3) to RR Masonry
Unit = 10 sqm
A. MATERIALS:
Cement kg 28.80 #REF! #REF!
Fine aggregate (Sand) cum 0.06 #REF! #REF!
DATA26
B. LABOUR:
Mason 2nd class day 0.50 320.00 160.00
Mazdoor (unskilled) day 0.74 280.00 207.20
Add 20% on labour charges 20% 367.20 73.44
Grand Total #REF! /10sqm
Over heads and conractor profit 14% #REF!
Grand Total #REF! /10sqm
BLD-CSTN-6 PLASTERING
BLD-CSTN-6-1 53 Plastering with CM (1:1), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:1) cum 0.15 #REF! #REF!
B. LABOUR:
Mason 1st class day 0.60 320.00 192.00
Mazdoor (unskilled) day 0.96 280.00 268.80
Add 40% on labour charges 20% 460.80 92.16
Grand Total #REF! 10sqm
BLD-CSTN-6-1 53 Plastering with CM (1:2), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3) cum 0.15 #REF! #REF!
B. LABOUR:
Mason 1st class day 0.60 350.00 210.00
Mazdoor (unskilled) day 0.96 280.00 268.80
Add 40% on labour charges 20% 478.80 95.76
Grand Total #REF! 10sqm
BLD-CSTN-6-2 54 Ceiling Plastering with CM (1:4), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4) cum 0.15 #REF! #REF!
B. LABOUR:
Mason 1st class day 0.60 350.00 210.00
Mazdoor (unskilled) day 0.96 280.00 268.80
Add 25% on labour charges 20% 478.80 95.76
Grand Total #REF!
Over heads and conractor profit 14% #REF!
#REF! 10sqm
a Ground floor
10 Sqm Basic rate sqm 10.00 #REF! #REF!
10 Sqm Scoffolding hire charges Sqm 1.00 1.28 12.80
10 sqm scaffolding labour charges Sqm 1.00 8.00 80.00
Add for labour allowance 20% 80.00 16.00
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
b 1st floor
10 Sqm Basic rate sqm 10.00 #REF! #REF!
lift charges 10 % 0.00 0.00
10 Sqm Scoffolding hire charges Sqm 1.00 1.28 12.80
10 sqm scaffolding labour charges Sqm 1.00 8.00 80.00
Add for labour allowance 20% 80.00 16.00
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
c 2nd floor
10 Sqm Basic rate cum 10.00 #REF! #REF!
lift charges 20 % 0.00 0.00
10 Sqm Scoffolding hire charges Sqm 1.00 1.28 12.80
10 sqm scaffolding labour charges Sqm 1.00 12.00 120.00
Add for labour allowance 20% 120.00 24.00
DATA27
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
d 3rd floor
10 Sqm Basic rate cum 10.00 #REF! #REF!
lift charges 30 % 0.00 0.00
10 Sqm Scoffolding hire charges Sqm 1.00 1.28 12.80
10 sqm scaffolding labour charges Sqm 1.00 16.00 160.00
Add for labour allowance 20% 160.00 32.00
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
e 4th floor
10 Sqm Basic rate cum 10.00 #REF! #REF!
lift charges 40 % 0.00 0.00
10 Sqm Scoffolding hire charges Sqm 1.00 1.28 12.80
10 sqm scaffolding labour charges Sqm 1.00 20.00 200.00
Add for labour allowance 20% 200.00 40.00
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
f 5th floor
10 Sqm Basic rate cum 10.00 #REF! #REF!
lift charges 50 % 0.00 0.00
10 Sqm Scoffolding hire charges Sqm 1.00 1.28 12.80
10 sqm scaffolding labour charges Sqm 1.00 24.00 240.00
Add for labour allowance 20% 240.00 48.00
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
Grand Total #REF! 10sqm
BLD-CSTN-6-6 58 Plastering with CM (1:4), 15 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4) cum 0.19
Seigniorage charges for F.A cum 0.19
B. LABOUR:
Mason 2nd class day 0.60
Mazdoor (unskilled) day 0.96
Grand Total
BLD-CSTN-6-7 59 Plastering with CM (1:4), 20 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4) cum 0.210 #REF! #REF!
B. LABOUR:
Mason 2nd class day 0.94 350.00 329.00
Mazdoor (unskilled) day 1.60 280.00 448.00
Add labour charges allowance 20% 777.00 155.40
Grand Total #REF!
BLD-CSTN-6-8 60 Plastering with CM (1:3), 20 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3) cum 0.210 #REF! #REF!
B. LABOUR:
Mason 2nd class day 0.94 350.00 329.00
Mazdoor (unskilled) day 1.60 280.00 448.00
Add labour charges allowance 20% 777.00 155.40
Grand Total #REF!
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted
DATA28
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:6), 16 mm thick
Cement kg 43.00 #REF! #REF!
Fine aggregate (Sand) cum 0.18 #REF! #REF!
Top Coat in CM(1:3), 4 mm thick
Cement kg 14.50 #REF! #REF!
Fine aggregate (Sand) cum 0.04 #REF! #REF!
B. LABOUR:
Mason 1st class day 0.63 350.00 220.50
Mason 2nd class day 1.47 320.00 470.40
Mazdoor (unskilled) day 3.90 280.00 1092.00
Add 25% on labour charges 20% 1782.90 356.58
Grand Total #REF! /10sqm
a Ground floor
10 Sqm Basic rate sqm 10.00 #REF! #REF!
10 Sqm Scoffolding hire charges Sqm 1.00 0.55 5.50
10 sqm scaffolding labour charges Sqm 1.00 4.04 40.40
Add for labour allowance 20% 40.40 8.08
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
b 1st floor
10 Sqm Basic rate sqm 10.00 #REF! #REF!
lift charges 10 % 1782.90 178.29
10 Sqm Scoffolding hire charges Sqm 1.00 0.55 5.50
10 sqm scaffolding labour charges Sqm 1.00 4.04 40.40
Add for labour allowance 20% 40.40 8.08
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
c 2nd floor
10 Sqm Basic rate cum 10.00 #REF! #REF!
lift charges 20 % 1782.90 356.58
10 Sqm Scoffolding hire charges Sqm 1.00 0.55 5.50
10 sqm scaffolding labour charges Sqm 1.00 6.06 60.60
Add for labour allowance 20% 60.60 12.12
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
d 3rd floor
10 Sqm Basic rate cum 10.00 #REF! #REF!
lift charges 30 % 1782.90 534.87
10 Sqm Scoffolding hire charges Sqm 1.00 0.55 5.50
10 sqm scaffolding labour charges Sqm 1.00 8.09 80.90
Add for labour allowance 20% 80.90 16.18
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
e 4th floor
10 Sqm Basic rate cum 10.00 #REF! #REF!
lift charges 40 % 1782.90 713.16
10 Sqm Scoffolding hire charges Sqm 1.00 0.55 5.50
10 sqm scaffolding labour charges Sqm 1.00 10.11 101.10
Add for labour allowance 20% 101.10 20.22
#REF!
Over heads and conractor profit 14% #REF!
DATA29
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:6), 12 mm thick
Cement kg 31.70 #REF! #REF!
Fine aggregate (Sand) cum 0.11 #REF! #REF!
Top Coat in CM(1:4), 4 mm thick
Cement kg 19.20 #REF! #REF!
Fine aggregate (Sand) cum 0.04 #REF! #REF!
B. LABOUR:
Mason 1st class day 0.63 350.00 220.50
Mason 2nd class day 1.47 320.00 470.40
Mazdoor (unskilled) day 3.90 280.00 1092.00
Add 25% on labour charges 20% 1782.90 356.58
Grand Total #REF! 10sqm
a Ground floor
10 Sqm Basic rate sqm 10.00 #REF! #REF!
10 Sqm Scoffolding hire charges Sqm 1.00 0.55 5.50
10 sqm scaffolding labour charges Sqm 1.00 4.04 40.40
Add for labour allowance 20% 40.40 8.08
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
b 1st floor
10 Sqm Basic rate sqm 10.00 #REF! #REF!
lift charges 10 % 1782.90 178.29
10 Sqm Scoffolding hire charges Sqm 1.00 0.55 5.50
10 sqm scaffolding labour charges Sqm 1.00 4.04 40.40
Add for labour allowance 20% 40.40 8.08
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
c 2nd floor
10 Sqm Basic rate cum 10.00 #REF! #REF!
lift charges 20 % 1782.90 356.58
10 Sqm Scoffolding hire charges Sqm 1.00 0.55 5.50
10 sqm scaffolding labour charges Sqm 1.00 6.06 60.60
Add for labour allowance 20% 60.60 12.12
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
d 3rd floor
10 Sqm Basic rate cum 10.00 #REF! #REF!
lift charges 30 % 1782.90 534.87
10 Sqm Scoffolding hire charges Sqm 1.00 0.55 5.50
10 sqm scaffolding labour charges Sqm 1.00 8.09 80.90
Add for labour allowance 20% 80.90 16.18
DATA30
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
e 4th floor
10 Sqm Basic rate cum 10.00 #REF! #REF!
lift charges 40 % 1782.90 713.16
10 Sqm Scoffolding hire charges Sqm 1.00 0.53 5.30
10 sqm scaffolding labour charges Sqm 1.00 10.11 101.10
Add for labour allowance 20% 101.10 20.22
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
f 5th floor
10 Sqm Basic rate cum 10.00 #REF! #REF!
lift charges 50 % 1782.90 891.45
10 Sqm Scoffolding hire charges Sqm 1.00 0.55 5.50
10 sqm scaffolding labour charges Sqm 1.00 12.13 121.30
Add for labour allowance 20% 121.30 24.26
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
RCM FACIA WORKS
BLD-CSTN-6-11 63 RCM facia 5cm thick in CM (1:1) for drop walls, fins with rabbit wire mesh & nominal
reinforcement as directed by Engineer-in-charge with dubara sponge finishing, including cost &
conveyance of all materials to site, seigniorage charges, sales & other taxes on all materials,
operational & incidental, cost and conveyance of cement, wire mesh, water to work site, centering,
scaffolding and form work, lift charges etc., complete for finished items of work but excluding cost
of steel & its fabrication charges, for finished item of work. (APSS No.403 & 903)
Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M drop) sqm 13.30 150.00 1995.00
sl no.83
Cement Mortar 1:1 for 25 mm thick cum 0.25 #REF! #REF!
Dry Cement for making Lumps kg 50.00 #REF! #REF!
12 mm Plastering 2 coats in 1:4 & 1:2 cm both sqm 21.80 #REF! #REF!
sides
Excluding HYSD Steel/ Mild steel & Binding
wire
B) LABOUR CHARGES
1st Class Mason day 8.00 350.00 2800.00
Miller Operator day 1.00 320.00 320.00
Mazdoor (unskilled) day 10.00 280.00 2800.00
Add for labour allowance 20% 5920.00 1184.00
c) Machinery
Machine Mixing Mortar with Miller - Hire Hrs 2.00 66.00 132.00
charges
Basic cost #REF! 10sqm
a Ground floor
10 Sqm Basic rate sqm 10.00 #REF! #REF!
10 Sqm Scoffolding hire charges Sqm 1.00 0.55 5.50
10 sqm scaffolding labour charges Sqm 1.00 4.04 40.40
Add for labour allowance 20% 40.40 8.08
#REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! /10sqm
Rs. #REF!
b 1st floor
10 Sqm Basic rate sqm 10.00 #REF! #REF!
lift charges 10 % 5920.00 592.00
10 Sqm Scoffolding hire charges Sqm 1.00 0.55 5.50
DATA31
Unit = 10 sqm
a Ground floor
A. MATERIALS:
Polished Bethamcherla pure (marble type) white sqm 11.00 3374.00 3711.40
stone minimum 25 mm thick (0.254Mx0.254M)
sl no.28 p/4
Cement for CM (1:8) proportion for base coat kg. 21.60 #REF! #REF!
B. LABOUR:
Mason 1st class day 3.10 350.00 1085.00
Mason 2nd class day 1.10 320.00 352.00
Mazdoor (unskilled) day 0.86 280.00 240.80
Add for labour allowance 20% 1677.80 335.56
#REF!
Add water charges 1% 1% #REF!
0.03
Grand Total #REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! 10sqm
Rs. #REF!
b 1st floor
Basic rate sqm 10.00 #REF!
Lift charges 10 % 1677.80 167.78
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
c 2nd floor
Basic rate Sqm 10.00 #REF!
lift charges 20.00 % 1677.80 335.56
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
d 3rd floor
Basic rate Sqm 10.00 #REF!
lift charges 30.00 % 1677.80 503.34
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
BLD-CSTN-7-2 72 Flooring with 40 mm thick Rough Cuddapah/Shabad stones, set over base coat of cement mortar
(1 : 8) 12 mm thick over CC bed already laid or RCC roof slab, including pointing with cement
mortar 1:3 duly filling joints nearly, including cost of all materials like flooring stone, cement,
sand, and water etc., complete, including seigniorage charges, labour charges for dressing of
flooring stones etc., complete for finished item of work, but excluding the cost of conveyance of all
materials.
Unit = 10 sqm
A. MATERIALS:
Rough Cuddapah/Shabad stones (40 mm thick) sqm 10.50 1084.00 1138.20
(0.457 x 0.457 m) sl no.24
Cement for CM (1:8) proportion for base coat kg. 21.60 #REF! #REF!
Cement for CM 1:3 proportion for pointing kg. 9.60 #REF! #REF!
Sand for CM (1:8) proportion cum 0.12 #REF! #REF!
Sand for CM (1:3) proportion cum 0.02 #REF! #REF!
B. LABOUR: 0.00
Mason 1st class day 0.960 350.00 336.00
Mason 2nd class day 2.240 320.00 716.80
Mazdoor (unskilled) day 3.30 280.00 924.00
Add 25% on labour charges 20% 1976.80 395.36
#REF!
Add water charges 1% #REF!
Grand Total #REF!
BLD-CSTN-7-3 73 Flooring with polished marble slab 20 mm thick set over base coat of cement mortar (1:6) 20 mm
thick (joints of stone must be flushed) over CC bed already laid or RCC roof slab, including near
cement slurry of honey like consistency spread @ 3.30 kgs per sqm. Jointed with neat cement to
full depth mixed with pigment of matching shade, including cost of all materials like flooring slab,
cement, sand, and water etc., complete, including seigniorage charges, labour charges for dressing,
rubbing and polishing of flooring stones etc., complete for finished item of work, but excluding the
cost of conveyance of all materials.
DATA33
Unit = 10 sqm
A. MATERIALS:
Marble slab of size 0.305 M x 0.305 M sl no.34 sqm 10.10 874.00 8827.40
Cement for CM (1:6) proportion for base coat kg. 48.00 #REF! #REF!
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles of 1st quality of size sl no.53 BMT- sqm 10.10 810.00 8181.00
C-16
Cement for CM (1:8) for base coat kg. 21.60 #REF! #REF!
Cement for slurry kg. 33.00 #REF! #REF!
Cement for Pointing with CM (1:3) kg. 6.000 #REF! #REF!
Sand for CM (1:8) cum 0.12 #REF! #REF!
Sand for pointing cum 0.020 #REF! #REF!
B. LABOUR 0.00
Mason 1st class day 0.96 350.00 336.00
Mason 2nd class day 2.24 320.00 716.80
Mazdoor (unskiled) day 3.30 280.00 924.00
Add 25% on labour charges 20% 1976.80 395.36
#REF!
Add water charges 1% 1.00% #REF!
#REF!
0.02
Grand Total #REF!
Rs. #REF!
e 4th floor
Basic rate Sqm 10.00 #REF!
lift charges 40% 1677.80 671.12
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
f 5th floor
Basic rate Sqm 10.00 #REF!
lift charges 50% 1677.80 838.90
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
DATA34
BLD-CSTN-7-22 92 Providing skirting to internal walls to 15 cm height/risers of steps with 25 mm thick polished
Cuddapah stone length equal to flooring stones, set over base coat of CM (1:3) 12 mm thick with
cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointed with
white cement paste mixed with pigment of matching shade to full depth, including cost of all
materials like Cuddapah stone, cement, sand and water etc., complete including seigniorage
charges, etc., complete for finished item of work, in cluding the cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
25 mm thick polished Cuddapah stone sqm 10.10 3012.80 3042.93
Sand for cm 1:3 base coat cum 0.12 #REF! #REF!
Cement for cm 1:3 base coat kgs 57.60 #REF! #REF!
Cement for slurry kgs 33.00 #REF! #REF!
B. LABOUR
Mason Ist class day 0.96 315.00 302.40
Mason 2nd class day 2.24 285.00 638.40
Mazdoor (unskiled) day 3.10 250.00 775.00
Add water charges 1% 1.00% 850.00 8.50
Grand Total #REF!
Grand Total #REF!
Over heads and conractor profit 14% #REF!
Grand Total Rs. #REF! 10sqm
b 1st floor
Basic rate sqm 10.00 #REF!
Lift charges 10 % 850.00 85.00
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
c 2nd floor
Basic rate Sqm 10.00 #REF!
lift charges 20.00 % 850.00 170.00
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
d 3rd floor
Basic rate Sqm 10.00 #REF!
lift charges 30.00 % 850.00 255.00
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
BLD-CSTN-7-2 72 Flooring with 40 mm thick Rough Cuddapah/Shabad stones, set over base coat of cement mortar
(1 : 8) 12 mm thick over CC bed already laid or RCC roof slab, including pointing with cement
mortar 1:3 duly filling joints nearly, including cost of all materials like flooring stone, cement,
sand, and water etc., complete, including seigniorage charges, labour charges for dressing of
flooring stones etc., complete for finished item of work, but including the cost of conveyance of all
materials.
Unit = 10 sqm
A. MATERIALS:
Rough Cuddapah/Shabad stones (40 mm thick) sqm 10.50 968.00 1016.40
(0.457 x 0.457 m) sl no.24
Cement for CM (1:8) proportion for base coat kg. 21.60 0.00 0.00
Cement for CM 1:3 proportion for pointing kg. 9.60 #REF! #REF!
Sand for CM (1:8) proportion cum 0.12 #REF! #REF!
Sand for CM (1:3) proportion cum 0.02 #REF! #REF!
B. LABOUR: 0.00
Mason 1st class day 0.960 350.00 336.00
Mason 2nd class day 2.240 320.00 716.80
Mazdoor (unskilled) day 3.30 280.00 924.00
Add 40% on labour charges 20 % 1976.80 39536.00
DATA35
#REF!
Add water charges 1% #REF!
0.02
Grand Total #REF!
BLD-CSTN-7-3 73 Flooring with polished marble slab 20 mm thick set over base coat of cement mortar (1:6) 20 mm
thick (joints of stone must be flushed) over CC bed already laid or RCC roof slab, including near
cement slurry of honey like consistency spread @ 3.30 kgs per sqm. Jointed with neat cement to
full depth mixed with pigment of matching shade, including cost of all materials like flooring slab,
cement, sand, and water etc., complete, including seigniorage charges, labour charges for dressing,
rubbing and polishing of flooring stones etc., complete for finished item of work, but excluding the
cost of conveyance of all materials.
Unit = 10 sqm
A. MATERIALS:
Marble slab of size 0.305 M x 0.305 M sl no.34 sqm 10.10 780.00 7878.00
Cement for CM (1:6) proportion for base coat kg. 48.00 0.00 0.00
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles of 1st quality of size sl no.49 sqm 10.10 1290.00 13029.00
Cement for CM (1:8) for base coat kg. 21.60 0.00 0.00
Cement for slurry kg. 33.00 0.00 0.00
Cement for Pointing with CM (1:3) kg. 6.000 0.00 0.00
Sand for CM (1:8) cum 0.12 #REF! #REF!
Sand for pointing cum 0.020 #REF! #REF!
B. LABOUR 0.00
Mason 1st class day 0.96 350.00 336.00
Mason 2 nd
class day 2.24 280.00 627.20
Mazdoor (unskiled) day 3.30 100.00 330.00
Add 40% on labour charges 20% 1293.20 2.59
#REF!
Add water charges 1% 1.00% #REF!
#REF!
0.04
Grand Total #REF!
Rs. #REF!
e 4th floor
Basic rate Sqm 10.00 #REF!
lift charges 20% 850.00 1.70
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
DATA36
BLD-CSTN-7-5 75 Flooring with vitrified tiles of 1 st quality, set over base coat of cement mortar (1:8), 12 mm thick
over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly with white cement paste to full depth mixed with
pigment of matching shade, including cost of all materials like cement, sand water and tiles etc.,
complete, including seigniorage charges, etc., complete for finished item of work, but excluding
the cost of conveyance of all materials.
Unit = 10 sqm
a Ground floor
A. MATERIALS:
Vitrified tiles of 1st quality of size BMT C-16 sno sqm 10.10 810.00 8181.00
53 p/5
Cement for CM (1:8) proportion for base coat kg. 21.60 4.40 95.04
BLD-CSTN-7-2 72 Flooring with 40 mm thick Rough Cuddapah/Shabad stones, set over base coat of cement mortar
(1 : 8) 12 mm thick over CC bed already laid or RCC roof slab, including pointing with cement
mortar 1:3 duly filling joints nearly, including cost of all materials like flooring stone, cement,
sand, and water etc., complete, including seigniorage charges, labour charges for dressing of
flooring stones etc., complete for finished item of work, but excluding the cost of conveyance of all
materials.
Unit = 10 sqm
A. MATERIALS:
Rough Cuddapah/Shabad stones (40 mm thick) sqm 10.50 968.00 1016.40
(0.457 x 0.457 m) sl no.24
Cement for CM (1:8) proportion for base coat kg. 21.60 4.40 95.04
Cement for CM 1:3 proportion for pointing kg. 9.60 4.40 42.24
Sand for CM (1:8) proportion cum 0.12 439.16 52.70
Sand for CM (1:3) proportion cum 0.02 439.16 8.78
B. LABOUR: 0.00
Mason 1st class day 0.960 350.00 336.00
Mason 2nd class day 2.240 320.00 716.80
Mazdoor (unskilled) day 3.30 280.00 924.00
Add 40% on labour charges 20% 1976.80 184.80
3376.76
Add water charges 1% 33.77
0.02
Grand Total 3410.55
BLD-CSTN-7-3 73 Flooring with polished marble slab 20 mm thick set over base coat of cement mortar (1:6) 20 mm
thick (joints of stone must be flushed) over CC bed already laid or RCC roof slab, including near
cement slurry of honey like consistency spread @ 3.30 kgs per sqm. Jointed with neat cement to
full depth mixed with pigment of matching shade, including cost of all materials like flooring slab,
cement, sand, and water etc., complete, including seigniorage charges, labour charges for dressing,
rubbing and polishing of flooring stones etc., complete for finished item of work, but excluding the
cost of conveyance of all materials.
Unit = 10 sqm
A. MATERIALS:
Marble slab BMT-B.14 sqm 10.10 780.00 7878.00
Cement for CM (1:6) proportion for base coat kg. 48.00 4.40 211.20
Unit = 10 sqm
A. MATERIALS:
High polished granite 16 to 18 mm thick slab sqm 10.10 2300.00 23230.00
other than black No. BMT-B.09
Cement for CM (1:8) prop for base coat kg. 36.00 4.40 158.40
Cement for slurry for bedding kg. 33.00 4.40 145.20
White Cement for pointing kg. 6.00 20.00 120.00
Sand for CM (1:8) cum 0.20 439.16 87.83
B. LABOUR:
Mason 1st class day 3.00 350.00 1050.00
Mason 2nd class day 1.00 320.00 320.00
Mazdoor (unskilled) day 8.00 280.00 2240.00
Add for labour allowance 20% 3610.00 722.00
28073.43
Add water charges 1% 1% 280.73
Grand Total 28354.16
Over heads and conractor profit 14% 3969.58
Grand Total 32604.47 10sqm
Rs. 32604.47
b 1st floor
Basic rate sqm 10.00 28354.16 28354.16
Lift charges 10 % 3610.00 361.00
28715.16
Over heads and conractor profit 14% 4020.12
Grand Total 33096.28 10sqm
Rs. 33096.28
c 2nd floor
Basic rate Sqm 10.00 28354.16 28354.16
lift charges 20.00 % 3610.00 722.00
29076.16
DATA39
Unit = 10 sqm
A. MATERIALS:
Cement Concrete 1:3:6 using concrete mixer cum 1.00 #REF!
Unit = 10 sqm
a Ground floor
A. MATERIALS:
Edge cut Ceramic tiles sl no.39 p/5 BMT-C 02 sqm 10.10 504.00 5090.40
Cement for CM (1:8) for base coat kg. 21.60 #REF! #REF!
Cement for slurry kg. 33.00 #REF! #REF!
White cement kg. 2.00 20.00 40.00
Sand for CM (1:8) cum 0.12 #REF! #REF!
B. LABOUR
Mason 1st class day 0.96 350.00 336.00
Mason 2nd class day 2.24 320.00 716.80
Mazdoor (unskiled) day 3.30 280.00 924.00
Add for labour allowance 20% 1976.80 395.36
#REF!
Add water charges 1% 1.00% #REF!
#REF!
Grand Total #REF!
Over heads and conractor profit 14% #REF!
#REF! /10sqm
Rs. #REF!
b 1st floor
Basic rate sqm 10.00 #REF! #REF!
Lift charges 10 % 1976.80 197.68
#REF!
DATA40
Unit = 10 sqm
a Ground floor
A. MATERIALS:
Edge cut Ceramic tiles sl no.38 sqm 10.10 504.00 5090.40
Cement for CM (1:6) for base coat kg. 28.80 #REF! #REF!
Cement for slurry kg. 33.00 #REF! #REF!
White cement kg. 6.00 20.00 120.00
Sand for CM (1:6) cum 0.12 #REF! #REF!
B. LABOUR
Mason 1st class day 0.96 350.00 336.00
Mason 2nd class day 2.24 320.00 716.80
Mazdoor (unskiled) day 3.30 280.00 924.00
Add for labour allowance 20% 1976.80 395.36
#REF!
Add water charges 1% 1.00% #REF!
Grand Total #REF!
Over heads and conractor profit 14% #REF!
#REF! /10sqm
Rs. #REF!
b 1st floor
Basic rate sqm 10.00 #REF! #REF!
Lift charges 10 % 1976.80 197.68
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
DATA41
c 2nd floor
Basic rate Sqm 10.00 #REF! #REF!
lift charges 20.00 % 1976.80 395.36
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
d 3rd floor
Basic rate Sqm 10.00 #REF! #REF!
lift charges 30.00 % 1976.80 593.04
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
e 4th floor
Basic rate Sqm 10.00 #REF! #REF!
lift charges 40.00 % 1976.80 790.72
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
f 5th floor
Basic rate Sqm 10.00 #REF! #REF!
lift charges 50.00 % 1976.80 988.40
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
BLD-CSTN-7-20 90 Providing skirting to internal walls to 15 cm height/risers of steps with vitrified tiles length equal
to flooring stones, set over base coat of CM (1:5) 12 mm thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with
pigment of matching shade to full depth, including cost of all materials like tiles, cement, sand
and water etc., complete including seigniorage charges, etc., complete for finished item of work,
but excluding the cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Vetrified tiles Ceramic tiles 7.30 mm thick sqm 10.10 810.00 8181.00
Sand for cm 1:5 base coat cum 0.12 439.16 52.70
Cement for cm 1:5 base coat kgs 34.56 #REF! #REF!
Cement for slurry kgs 33.00 #REF! #REF!
White cement for jointing & pointing kgs 2.00 20.00 40.00
B. LABOUR
Mason 1st class day 0.96 350.00 336.00
Mason 2nd class day 2.24 320.00 716.80
Mazdoor (unskiled) day 3.30 280.00 924.00
Add for labour allowance 20% 1260.00 252.00
Grand Total #REF!
Add water charges 1% 1% #REF!
#REF!
Over heads and conractor profit 14% #REF!
#REF! /10sqm
Rs. #REF!
b 1st floor
Basic rate sqm 10.00 #REF! #REF!
Lift charges 10 % 1260.00 126.00
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
c 2nd floor
Basic rate Sqm 10.00 #REF! #REF!
lift charges 20.00 % 1260.00 252.00
#REF!
Over heads and conractor profit 14% #REF!
DATA42
Unit = 10 sqm
A. MATERIALS:
Ceramic tiles 7.30 mm thick Sno 39 p/5 sqm 10.00 504.00 5040.00
Sand for cm 1:3 base coat cum 0.12 #REF! #REF!
Cement for cm 1:3 base coat kgs 57.60 #REF! #REF!
Cement for slurry kgs 33.00 #REF! #REF!
White cement for jointing & pointing kgs 6.00 20.00 120.00
B. LABOUR
Mason 1st class day 0.77 350.00 269.50
Mazdoor (unskiled) day 0.80 280.00 224.00
Add for labour allowance 20% 493.50 98.70
Grand Total #REF!
Add water charges 1% 1% #REF!
#REF!
Over heads and conractor profit 14% #REF!
#REF! /10sqm
Rs. #REF!
b 1st floor
Basic rate sqm 10.00 #REF! #REF!
Lift charges 10 % 493.50 49.35
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
c 2nd floor
Basic rate Sqm 10.00 #REF! #REF!
lift charges 20.00 % 493.50 98.70
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
d 3rd floor
Basic rate Sqm 10.00 #REF! #REF!
lift charges 30.00 % 493.50 148.05
DATA43
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
e 4th floor
Basic rate Sqm 10.00 #REF! #REF!
lift charges 40.00 % 493.50 197.40
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
f 5th floor
Basic rate Sqm 10.00 #REF! #REF!
lift charges 50.00 % 493.50 246.75
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
Grand Total #REF! #REF!
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884 sl nos 47.91 5.00 239.57
no.894
G.I bolts & nuts 20 x 6 sl no.895 nos 6.50 5.00 32.50
G.I ‘J’ bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos = nos 43.90 8.00 351.22
810 nos. with washers or srews, if wooden
battens used. sl no.896
Limpet washers (for scam & ‘J’ bolts) 884 + nos 91.82 0.25 22.95
810 = 1694 sl no.898
Bitumen washers sl no.899 p/97 nos 91.82 0.20 18.36
Zinc cromate yellow paint sl no.84 p/15 litre 0.14 80.00 10.97
Ready mixed paint litre 0.20 80.00 16.26
B. LABOUR
For roofing
Carpenter II class day 0.84 320.00 268.83
Man mazdoor (beldar) day 0.91 280.00 254.96
Add 20% on labour charges 20 % 523.79 104.76
For premier painting one coat
Painter day 0.06 350.00 21.44
Mazdoor (coolie) day 0.06 280.00 17.15
Add 40% on labour charges 40 % 38.59 15.44
BLD-CSTN-8-4 99 Roofing with 6 mm thick corrugated asbestos cement sheets, fixing with G.I ‘J’ bolts &
nuts 8 mm dia G.I plain washers complete including seigniorage charges etc., complete
for finished item of work, but excluding the cost of purlins, rafters, trusses & cost of
conveyance of all materials – upto 60 0 pitch.
8 mm dia G.I ‘J’ bolts & nuts sl no.896 p/97 nos 22.03 8.00 176.21
Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3 cum 0.210 #REF! #REF!
Water proof compound sl no.237 p/15 kg 2.000 24.00 48.00
B. LABOUR
Mason 1st class day 0.660 350.00 231.00
Mason 2 nd
class day 1.540 320.00 492.80
Mazdoor (unskiled) day 3.70 280.00 1036.00
Add for labour allowance 20% 1759.80 351.96
Grand Total #REF! 10sqm
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
b 1st floor
Basic rate sqm 10.00 #REF! #REF!
Lift charges 10 % 320.00 32.00
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
c 2nd floor
Basic rate Sqm 10.00 #REF! #REF!
lift charges 20.00 % 320.00 64.00
#REF!
Over heads and conractor profit 14% #REF!
Grand Total #REF! 10sqm
Rs. #REF!
d 3rd floor
Basic rate Sqm 10.00 #REF! #REF!
lift charges 30.00 % 320.00 96.00
#REF!
Over heads and conractor profit 14% #REF!
DATA46
BLD-CSTN-8-30 125 Providing 10 mm thick plaster of paris (Gypsum anhydrous) ceiling upto a height of 5 m
above floor level over first class BT wood strips 25 x 6 mm with 10 mm gap in between
and reinforced with rabbit wire mesh fixed to wooden frame excluding cost of wooden
frame for base & cost of conveyance of all materials.
Unit = 10 sqm
A. MATERIALS:
Wooden strips 1st class BT wood 25 x 6 mm size cum 0.05 77693.00 3690.42
sl no.
Nails sl no. kg 0.75 150.00 112.50
Rabbit wire mesh sl no.155 sqm 10.20 12.00 122.40
Plaster of paris sl no. kg 219.76 25.00 5494.00
B. LABOUR
for Jointing the wooden strips including fixing
the rabbit mesh
Carpenter Ist class day 2.60 350.00 910.00
Man mazdoor (beldar) day 1.60 280.00 448.00
Add for labour allowance 20% 1358.00 271.60
UNIT -1 sqm
A) Material requirement as per India Gypsum
DATA47
12.5 mm Gypboard
1219 mm x 1829 mm size Boards sqm 1.03 220.00 225.63
Ceiling Angle 0.00
25 mm x 10 mm x 0.55 mm RM 0.64 65.00 41.60
Connecting Clips Nos 1.84 2.00 3.68
Ceiling Section
51.5 mm x 26 mm x 10.5 mm x 0.55 mm thick RM 2.30 74.00 170.20
Intermediate Channel
45 mmx 15 mm x 15 mm x 0.9 mm RM 0.84 73.00 61.32
Perimeter Channel
20 mm x 27 mm x 30 mm(web) of 0.55 mm RM 0.40 65.00 26.00
thick
Rawl Plug Nos 0.64 1.50 0.96
Soffit Cleats Nos 0.64 1.50 0.96
Drywall Screws - 25 mm Nos 18.00 1.50 27.00
Jointing Compound Kgs 0.55 25.00 13.75
Jointing Paper Tape RM 1.46 5.00 7.30
Drywall Top Coat Lits 0.15 125.00 18.75
B) LABOUR CHARGES
1st Class Carpenter day 0.40 350.00 140.00
2nd Class Carpenter day 0.40 320.00 128.00
1st Class Painter day 0.08 350.00 28.00
2nd Class Painter day 0.08 320.00 25.60
Power Saw Cutter - Hand Operated - Operator day 0.04 280.00 11.20
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 0.32 105.00 33.60
charges
Power Drill - Hand Operated - Hire Charges Hrs 0.64 97.00 62.08
Add for labour allowance 20% 95.68 19.14
1199.71
Scaffolding charges 1% 12.00
BASIC COST per 1 sqm 1211.71
Over heads and conractor profit 14% 169.64
Grand Total 1393.35 1sqm
Rs. 1393.35
Gyp Board Fine Line Grid false ceiling
BLD-CSTN-8-32 127 Supplying and fixing Gyp Board Fine Line Grid false ceiling (GS-FLC-4.6 as per India
Gypsum) in size 600 mm x 600 mm using 12.5 mm thick/ 9.5 mm thick Gyp Board sheet
tiles of size 595 mm x 595 mm or 595 mm x 1195 mm conforming to IS 2095 - 1982
fixing to Gyp steel precoated GI wall angle of size 25 mm x 25 mm x of 0.70 mm thick
along the perimeter of ceiling screw fixed to brick work/ partition at 610 mm c/c and
suspending the frame work using precoated GI Tee section (24 mm x 38 mm x 0.7 mm)
from soffit at 1220 mm c/c fixed with GI Soffit Cleat, rawl plugs and steel expansion
fasteners & connecting clip to the GI T section with 4 mm dia GI Rod with galvanised
spring steel level clip of PVC unversal holding clips system at 1200 mm c/c and fixing
the 12.5 mm / 9.5 mm Gypboard Sheet tiles of size 595 mm x 595 mm or 595 mm x
1195 mm and finishing two coats of drywall topcoat complete for finished item of work
as per Idia Gypsum Ltd specification.
UNIT -1 sqm
A) Material requirement as per India Gypsum
UNIT 1 sqm
A) Material requirement
15 mm/ 19 mm Thermocole sheet 600 x 600 sqm 1.00 40.00 40.08
Alumninium Angle
24 mm x 24 mm RM 0.40 23.00 9.20
Anodised Aluminium T Section
(1) 24 x 24.5 x 2.4 mm mm RM 3.20 30.00 96.00
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod Nos 1.28 2.00 2.56
Rawl Plugs Nos 1.28 1.50 1.92
B) LABOUR CHARGES
1st Class Carpenter day 0.36 350.00 126.00
2nd Class Carpenter day 0.36 320.00 115.20
1st Class Painter day 0.00 350.00
2nd Class Painter day 0.00 320.00
Power Saw Cutter - Hand Operated - Operator day 0.02 350.00 7.00
C) Machinery
Power Saw Cutter - Hand Operated - Hire Hrs 0.16 105.00 16.80
charges
Power Drill - Hand Operated - Hire Charges Hrs 0.32 97.00 31.04
579.44
Scaffolding charges 1% 5.79
BASIC COST per 1 sqm 585.23
Over heads and conractor profit 14% 81.93
Grand Total 672.95 1sqm
Rs. 672.95
Unit: 10 sqm
A. MATERIALS :
Distemper sl no.369 p/34 kg 1.700 70.00 119.00
B. LABOUR
Painter day 1.200 400.00 480.00
Add 20% on labour charges 20% 480.00 96.00
695.00
Sundries including brushes, ladders, etc., 1% 6.95
Total cost for 10 sqm 701.95 10sqm
Over heads and conractor profit 14% 98.27
Grand Total 800.22 10sqm
Rs. 800.22
b 1st floor
Basic rate sqm 10.00 701.95 701.95
Lift charges 10 % 480.00 48.00
749.95
Over heads and conractor profit 14% 104.99
Grand Total 902.94 10sqm
Rs. 902.94
c 2nd floor
Basic rate Sqm 10.00 701.95 701.95
lift charges 20.00 % 480.00 96.00
797.95
Over heads and conractor profit 14% 111.71
Grand Total 1005.66 10sqm
Rs. 1005.66
d 3rd floor
Basic rate Sqm 10.00 701.95 701.95
lift charges 30.00 % 480.00 144.00
845.95
Over heads and conractor profit 14% 118.43
Grand Total 1108.38 10sqm
Rs. 1108.38
e 4th floor
Basic rate Sqm 10.00 701.95 701.95
lift charges 40.00 % 480.00 192.00
893.95
Over heads and conractor profit 14% 125.15
Grand Total 1211.10 10sqm
Rs. 1211.10
f 5th floor
Basic rate Sqm 10.00 701.95 701.95
lift charges 50.00 % 480.00 240.00
941.95
Over heads and conractor profit 14% 131.87
Grand Total 1313.82 10sqm
Rs. 1313.82
DATA50
BLD-CSTN-10-1 140 Painting to new walls with 2 coats of ready mixed oil bound wahsable distemper of
approved brand and shade over a base coat of appropriate primer of approved brand,
making 3 coats in all to give an even shade after thourughly brushing the surface to
remove all dirt and remains of loose powdered materials, including cost and conveyance
of all materials to work site and all operational, incidental, labour charges etc. complete
for finished item of work as per SS 911 for internal walls
PRIMARY COAT:
Cost of Primer Lts 0.50 117.00 58.50
Painter I st class Nos 0.08 400.00 32.00
Pianter Iind class Nos 0.19 320.00 60.80
Add for labour allowance 20% 92.80 18.56
PRIMARY COAT:
Rate as per SSR item no.391 p/24 sqm 1.00 110.00 110.00
Total cost 110.00
Over heads and conractor profit 14% 15.40
Grand Total 125.40 1sqm
BLD-CSTN-10-5 144 Painting to new walls with 2 coats of water proof cement paint of apporved brand and
shade over a base coat of approved cement primer grade I making making 3 coats in all
to give an even shade after thourughly brushing the surface to remove all dirt and
remains of loose powdered materials, including cost and conveyance of all materials to
work site and all operational, incidental, labour charges etc. complete for finished item
of work as per SS 912 for external walls
Unit: 10 sqm
Cost of Cement Primer sl no.353 in p/23 kg 1.00 117.00 117.00
Ist class painter day 0.21 400.00 84.00
2nd class painter day 0.49 320.00 156.80
Add 25% on labour charges 20% % 240.80 48.16
Cost of water proof cement Paint of approved kg 3.50 41.00 143.50
quality sl no.376 p/23
1st class painter day 0.15 400.00 60.00
2nd class painter day 0.35 320.00 112.00
Mazdoor (unskilled) day 1.50 280.00 420.00
DATA51
B. LABOUR
Painter day 1.500 350.00 525.00
Add 20% on labour charges 20% 525.00 105.00
948.40
Sundries including brushes, soap, putty etc., 0.07
1 BMT-N.55 Supply and Fixing of of Main entrance door with Double leaf shutter, Door with Teak wood Frame of sections size
150mm x 150mm with Door Shutter 50mm thick teak including cost of fixtures such as Brass Tower Bolts 250mm
long 2 Nos, Brass Handles 150mm long 2 Nos, 300mm long Brass Aldrops 1No, 125mm long Brass butt hinges 6Nos,
300 mm long Brass Flat latch 1No, Door stopper 2 Nos, Brass Hold fasts 4Nos 230mm long , Sales and Other Taxes
cost and convenyance of all materials to site all Labour charges such as Fixing of Door Frame and shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed item of work. Size : 2.4*2.40mts
89441.52 Each
2 BMT-N.55 Supply and Fixing of Door with Double leaf shutter, Door with Teak wood Frame of sections size 75mm x 125mm
with Door Shutter 50mm thick teak including cost of fixtures such as Brass Tower Bolts 300mm long 2 Nos, Brass
Handles 150mm long 2 Nos, 300mm long Brass Aldrops 2No, 125mm long Brass butt hinges 6Nos, Door stopper 2
Nos, Brass Hold fasts 4Nos 230mm long , Sales and Other Taxes cost and convenyance of all materials to site all
Labour charges such as Fixing of Door Frame and shutter Fixing in position , with Hardware fixtures etc., complete
for finsihed item of work.
6 no's Brass butt hinges 150mm long s.no178/p 14 179 1 no's 1074.00
30426.38 Each
54
3 BMT-N.55 Supply and Fixing of single leaf shutter, Door Size 1.20x2.10 mtrs with teakwood Frame of sections size 75mm x
100mm with Flush Door Shutter Solid Bond Wood block board type with commercial ply on both faces of 35mm thick
including cost of fixtures such as MS Powder coated Tower Bolts 250mm long 2 Nos, MS Powder coated Handles
150mm long 2 Nos, 300mm long MS Powder coated Aldrops 1No, 125mm long M.S.Powder Coated butt hinges 6Nos,
300 mm long MS Powder coated Flat latch 1No, Door stopper 2 Nos, MS Hold fasts 4Nos 230mm long , Sales and
Other Taxes cost and convenyance of all materials to site all Labour charges such as Fixing of Door Frame and shutter
Fixing in position , with Hardware fixtures etc., complete for finsihed item of work.
BMT-N.15 Flush door shutters, solid bond wood block board type with commercial ply on both
faces.: 25 mm thick conforming to IS:2202 of
ANAND/RAAVILA/KUTTY/STANDARD/SHUBHDWAR/ITP
2.52 Cum Area of Door 595.0 1.00 Cum 1499.40
2 no's M.S power coated tower bolts 150mm long sl 29 1 no's 58.00
no:172/p14
6 no's M.S power coated butt hinges 150mm long 33 1 no's 198.00
s.no187/p 14
2 no's M.S power coated Aldrops 300mm long 134 1 no's 268.00
s.no202/p 14
1 no's M.S power coated Laches 300mm long 54 1 no's 54.00
sno:209/p 14
6 no's M.S power coated Hold fasts 20 1 no's 120.00
2 no's M.S power coated door stoppers- s no 210 /p 37 1 no's 74.00
10
1 no's Heavy duty mortise lock 6/7 levers with P.C 512 1 no's 512.00
handils complet set-s no 223/p 14
3.15 Sqm Lobour charges for fixing Flush door shutters 265 1 Sqm 834.75
of any thickness to the existing door frame
including fixtures to the existing door shutter
excluding cost shutter-sno 874/p90
11290.17 Each
4 BMT-N.55 Supply and Fixing of single leaf shutter, Door Size 0.90x2.10 mtrs with teakwood Frame of sections size 75mm x
100mm
Size with Flush
of Door-0.90 Door mts
x 2.10 Shutter Solid Bond Wood
0.9 block boardxtype with commercial ply on both faces of 35mm thick
2.10
Area 1.89 Sqm
Size of teak wood 0.075 x 0.10
Verticals 2 0.075 0.10 2.10 = 0.0315 Cum
Horizontal 1 0.075 0.10 0.90 = 0.0068 Cum
0.0383 Cum
0.038 Cum Cost of teak wood 120036 1.0 Cum 4597.38
BMT-N.15 Flush door shutters, solid bond wood block board type with commercial ply on both
1.89 Cum Area of Door faces.: 25 mm thick conforming
595.0 to IS:2202
1.00 of Cum 1124.55
2 no's M.S power coated tower bolts 150mm long sl 29 1 no's 58.00
no:172/p19
6 no's M.S power coated butt hinges 150mm long 33 1 no's 198.00
s.no187/p 19
1 no's M.S power coated Aldrops 300mm long 134 1 no's 134.00
s.no202/p 19
1 no's M.S power coated Laches 300mm long 54 1 no's 54.00
sno:209/p 20
6 no's M.S power coated Hold fasts 20 1 no's 120.00
2 no's M.S power coated door stoppers- s no 210 /p 37 1 no's 74.00
20
1 no's Heavy duty mortise lock 6/7 levers with P.C 512 1 no's 512.00
handils complet set-s no 223/p 20
3.15 Sqm Lobour charges for fixing Flush door shutters 265 1 Sqm 834.75
of any thickness to the existing door frame
including fixtures to the existing door shutter
excluding cost shutter-sno 859/p81
9023.52 Each
5 Supply and Fixing of Window of size 2.40x1.200 mtrs, by using Best teak wood Frame of sections size 75mm x 100mm with
8 Nos shutters made with BISON DESIGNER BOARD of 12mm thick and supply and fixing of fixtures such as 6 Nos. Hold
fasts, MS Powder coated Tower Bolts 100mm long 8Nos, MS Powder coated Handles 100mm long 8 Nos, 75mm long
M.S.Powder Coated butt hinges 32Nos, Window Stays 8Nos and providing ms grill of 12mm square bars including 18mm
width M.S flats , Sales and Other Taxes cost and convenyance of all materials to site all Labour charges such as Fixing of
Window Frame on shutter Fixing in position , with Hardware fixtures etc., complete for finsihed item of work.
17954.90 Each
6 Supply and Fixing of Window of size 1.800x1.200 mtrs, by using Best teak wood Frame of sections size 75mm x 100mm
with 2 Nos shutters made with BISON DESIGNER BOARD of 12mm thick and supply and fixing of fixtures such as 4 Nos.
Hold fasts, MS Powder coated Tower Bolts 100mm long 6Nos, MS Powder coated Handles 100mm long 3 Nos, 75mm long
M.S.Powder Coated butt hinges 9Nos, Window Stays 3Nos and providing 9 nos of 12mm square bars including 18mm width
M.S flats , Sales and Other Taxes cost and convenyance of all materials to site all Labour charges such as Fixing of Window
Frame on shutter Fixing in position , with Hardware fixtures etc., complete for finsihed item of work.
17458.10 Each
Supply and Fixing of Window of size 1.50x2..10 mtrs, by using Best teak wood Frame of sections size 75mm x 100mm with
2 Nos shutters made with BISON DESIGNER BOARD of 12mm thick and supply and fixing of fixtures such as 4 Nos. Hold
fasts, MS Powder coated Tower Bolts 100mm long 6Nos, MS Powder coated Handles 100mm long 3 Nos, 75mm long
M.S.Powder Coated butt hinges 9Nos, Window Stays 3Nos and providing 9 nos of 12mm square bars including 18mm width
M.S flats , Sales and Other Taxes cost and convenyance of all materials to site all Labour charges such as Fixing of Window
Frame on shutter Fixing in position , with Hardware fixtures etc., complete for finsihed item of work.
14608.07 Each
7 Supplying & fixing collapsible steel shutters with vertical, double channel of 20 x10x2 mm of 100 mm centre ,Bracers with
flat iron 40x40x6 mm with 38 mm dia steel pulleys, the top, bottom and side vertical frames of the collapsible gate with
65x65mmx8mm MS Angle and middle guide rail at site height with 65mmx8mm MS flat for the pulleys to guide and fixed
with necessary hold fasts, bolts, nuts, rivets, locking arrangements, stoppers, handles, all accessories all fixtures and painted
with one coat of approved steel primer etc., complete for finished item of work as per special spn 1105
1 Sqm Rate as per item no.157 p/12 1855 1.00 Sqm 1855.00
1855.00
Add contractor profit and over head charges 14% 259.70
2114.70 Sqm
BMT-N-36 Supply and fixing Sintex or equivalent doors are made out of PVC section and panels. The overall dimension of the same is
33mm X 47mm with usual process variation and having a wall thickness of 1.5mm with a variation of ± 0.3mm. The infill is
seamless hallow multi chambered PVC single panel having an effective dimension of 762mm X 20mm having a wall thickness
of 1mm ± 0.3mm complete with door frames made from extruded sections in overall dimensions of 40 X 48mm having a wall
thickness of 1.5mm with usual process variation of ± 0.3mm,, for finished item of work.
1.575 Sqm toilet door shutter D1 0.75mrs*2.10mts 2018 1.00 Sqm 3178.35
size Sno678 p/49
2 no's M.S power coated tower bolts 150mm long sl 29 1 no's 58
no:172/p19
3 no's M.S power coated butt hinges 150mm long 33 1 no's 99
s.no187/p 19
1 no's M.S power coated Aldrops 300mm long 134 1 no's 134
s.no202/p 14
1 no's M.S power coated Laches 300mm long 54 1 no's 54
sno:209/p 14
3 no's M.S power coated Hold fasts 20 1 no's 60
3583.35
Add contractor profit and over head charges 0.14 501.67
4085.02 Each
57
supply and fixing of M.S Ventilator of size 0.60x0.45 mts with outer angle of size 25*25*5mm and 10mm square MS rods &
4nos 230mm long hold fasts,painting with enamel paint over metal primary including cost and conveyance of all material to
site all labour charges such as fabrication, fixing, painting charges complete for finished iteam of work
9
SSR 2012-13
size of ventilator as per specification 0.60 x 0.45
Lenth of outer frame-25*25*5 mm 2.40 mts 1.80 mts/kg 4.32
Lenth of hold fastes 0.60 mts 1.80 mts/kg 1.08
Horizontal square rod 10mm -0.60x6 no's
3.00
Vertical square rod 10mm -0.60x6 no's 2.7
5.70 mts 0.78 mts/kg 4.45
9.85
Add waistage @ 5% 0.49
10.34 kgs
I Sand filling
Unit = cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.31 250.00 77.50
labour componant 0.25 19.38
b) Material
Unit = cum
Taking output = 6 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 3.12 250.00 780.00
b&c) Overheads & Contractors Profit 14.00% 780.00 109.20
Add labour component 20% 780.00 156.00
Cost for 6 cum = a+b+c 1045.20
Rate per cum = (a+b+c)/6 174.20 174.20
RBR-FNDN-1 1 Excavation for Pipe Lines &
Foundation Trenches
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1
including setting out, removal of stumps and other deleterious material and disposal upto a lead of
50 m, etc complete for pipe line trenches & building foundations where depth is less than 1.50 times
the width
(I) Ordinary soil
(A) Manual Means
(i) Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 3.64 250.00 910.00
Add extra at 50 % 455.00
Add extra at 20 % 182.00
Sub Total 1547.00
RBR-FNDN-2 2 Filling in foundation / Pipe line trenches with excavated earth as per drawing and technical
specification Clause 305.3.9 MORD & 304 MORTH
II Filling in foundation trenches and basement with gravel as per drawing and technical
specification Clause 305.3.9 MORD & 304 MORTH
Unit = cum
Taking output = 1 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.31 250.00 77.50
Add extra at 20 % 77.50 15.50
Gravel 529.92
622.92
b&c) Overheads & Contractors Profit 14% 87.21
Cost for 1 cum = a+b+c Total 710.13 /Cum
yyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy
yyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy
DETAILED ESTIMATE CUM ABSTRACT
yyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyyy
Nme of work- Chimakurthy Nagar Panchayat - General Funds 2019-20 - Extension of distribution line at NSP colony and Reddy palem from
sudula Guruvamma House to Jogiru Subbarao house in Chimakurthy Nagara Panchayat.
ABSTRACT ESTIMATE
Estimate Amount : Rs. 8.50 LACKS
S.No Qty Description of work Rate per Amount
90.00 Rmt 75 MM dia PVC pipes 6Kg / Sq.Cm 126.11 1 Rmt 11350.14
420.00 Rmt 90 MM dia PVC pipes 6Kg / Sq.Cm 181.78 1 Rmt 76349.28
90.00 Rmt c) 110 MM dia PVC pipes 6 Kg / Sq.Cm 263.59 1 Rmt 23722.81
1.00 No.s d) 110 MM Long Bend 6Kg PVC 230.00 1 No.s 230.00
4.00 No.s e) 90 MM Long Bend 6 Kg PVC 135.00 1 No.s 540.00
2.00 No.s f) 200 MM X 3 Feet Talipeace ci 4160.00 1 No.s 8320.00
2.00 No.s g) 100 MM X 3 Feet Talipeace ci 2290.00 1 No.s 4580.00
2.00 No.s h)200 MM PVC 6 Kg socket 410.00 1 No.s 820.00
1.00 No.s i)110 MM PVC 6Kg socket 65.00 1 No.s 65.00
3.00 No.s j) 90 MM Plain Dummy PVC 45.00 1 No.s 135.00
2.00 No.s a) 200 MM dia CID joints class 15 1187.03 1 No's 2374.05
2.00 No.s b) 100 MM dia CID joints class 15 521.53 1 No's 1043.06
Supply and delivery of "Resilient Seated Soft Sealing" Gate Valves
(Sluice Valves) with Body and Bonnet of Ductile Iron GGG-40/SG-
400/15 or GGG-50/SG-500/7 or Equivalent as per IS1865,
IS:3896-2 and Wedge fully Rubber Lined with food grade quality
grade W270 grade EPDM, Replaceable Spindle Nut without gland
packing with 3-O ring protection system on the Shaft and Seals of
NBR. The Valves should be Vacuum tight and 100% leak proof
with face to face dimensions as BS:5163 Type A/IS:14846. All the
5
valves should be with fusion bonded Electrostatic Powder coating
both inside and outside (Min 250 Microns)-RAL 5005 with Pocket
Less Straight through body Passage conforming to Design
standards of DIN-3202F4/BS:5163 Type A Flange drilling as per IS
- 1538 excluding all taxes, duties and transportation.
Collection, Supply and filling with Crusher Stone Dust for road
7 fromation or dip filling as per drawing and technical specification
Clause 305.3.9 MORD
4.20 M3 a) For pipe line trenches 664.56 1 M3 2791.14
0.90 M3 b) For relaying of CC Patch work 664.56 1 M3 598.10
Laying VCC (1:4:8) using 40mm HBG m/c metal and OPC
including cost & conveyance of all materials, labor charges,
8
centering, amchinery, laying in position, vibration curing and all
incidental charges etc., complete for lean concrete.
PH SUB-DIVISION
CHIRALA
Nme of work-Chimakurthy Nagar Panchayat - General Funds 2019-20 - Shifting of protected water Pipeline existed below the Bridge opposite to
Hindu Burial Ground of Chimakurthy Nagara Panchayat.
DETAILED ESTIMATE
S.No Description Nos L B D Quantity
Cutting road surface including stacking of excavated materials for pipe line trench
1 72.00
work.
Cutting open C.C. road surface with concrete saw cutter and removal with Breaker 1 x 1 480 0.60 0.25
72.00 Rmt
2 Manufacture supply and delivery of Unplasticised PVC pipes for portable water
suppliers conforming to IS 4985/2000 with sacket as per specification. Inclusive of
transportation any ware in A.P. excluding excise duty and sales tax etc., complete
600.00 Rmt
ASSISTANT ENGINEER
COMMISSIONER
NAGARA PANCHAYAT
NAGARA PANCHAYAT
CHIMKAURTHY
Dy. EXECUTIVE ENGINEER CHIMAKURTHY
PH SUB-DIVISION
MARKAPUR
DATA 2019-20
S. Rate
Description Unit Quantity Amount Rs.
No. Rs.
1 2 3 4 5 6
Earthwork in excavation for structures as per drawing and technical specifications Clause
305.1 including setting out, construction of shoring and bracing, removal of stumps and
1 other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom
and backfilling in trenches with excavated suitable material as per Technical Specification
305 MORD / 304 MORTH.
Ordinary soil
Manual Means
Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 3.64 420.00 1528.80
Add M.A @ 20% 305.76
1834.56
b&c) Overheads & Contractors Profit 13.615% 208.15
Cost for 10 cum = a+b+c 2042.71
Rate per cum = (a+b+c)/10 204.27
Collection, Supply and filling with Crusher Stone Dust for road fromation or dip filling as
2
per drawing and technical specification Clause 305.3.9 MORD
Collection, Supply and filling with Sand for road fromation or dip filling as per drawing
3
and technical specification Clause 305.3.9 MORD
Crusher Stone Dust
Unit = Cum
A) Labour
Mazdoor day 0.3100 420.00 130.20
Add M.A @ 20% 26.04
B) Materials
sand Cum 1.0000 478.50 478.50
634.74
Add 13.615% over heads and Contractor Profit 82.87
Rate per Cum 717.61
4 Cutting road surface including stacking of excavated materials for pipe line trench work.
Manufacture supply and delivery of CID joints conforming to IS No. 8794/1988 including
6 loading, unloading and transportation to site of work but excluding taxes and duties etc.,
complete
a) 80 MM dia CID joints class 15
Weight of CID joint Kg 3.00 81.74 245.22
Bolts and nuts 3 No's of 12X90 mm size (page Sl-31) Kg 0.39 132.00 51.48
Rubber Rings ( BIS: 5382/1988) 1 set 1.00 75.00 75.00
371.70
Add 13.615% over heads and Contractor Profit 50.61
422.31
b) 150 MM dia CID joints class 15
Weight of CID joint Kg 6.30 81.74 514.96
Bolts and nuts 3 No's of 16X120 mm size (page Sl-
Kg 0.62 132.00 81.84
31)
Rubber Rings ( BIS: 5382/1988) 1 set 1.00 150.00 150.00
746.80
Add 13.615% over heads and Contractor Profit 101.68
848.48
c) 200 MM dia CID joints class 15
Weight of CID joint Kg 9.00 81.74 735.66
Bolts and nuts 3 No's of 16X120 mm size (page Sl-
Kg 1.16 132.00 153.12
31)
Rubber Rings ( BIS: 5382/1988) 1 set 1.00 156.00 156.00
1044.78
Add 13.615% over heads and Contractor Profit 142.25
1187.03
d) 100 MM dia CID joints class 15
Weight of CID joint Kg 3.80 81.74 310.61
Bolts and nuts 3 No's of 16X120 mm size (page Sl-
Kg 0.435 132.00 57.42
31)
Rubber Rings ( BIS: 5382/1988) 1 set 1.00 91.00 91.00
459.03
Add 13.615% over heads and Contractor Profit 62.50
521.53
Supply and delivery of "Resilient Seated Soft Sealing" Gate Valves (Sluice Valves) with
Body and Bonnet of Ductile Iron GGG-40/SG-400/15 or GGG-50/SG-500/7 or Equivalent
as per IS1865, IS:3896-2 and Wedge fully Rubber Lined with food grade quality grade
W270 grade EPDM, Replaceable Spindle Nut without gland packing with 3-O ring
protection system on the Shaft and Seals of NBR. The Valves should be Vacuum tight and
7 100% leak proof with face to face dimensions as BS:5163 Type A/IS:14846. All the valves
should be with fusion bonded Electrostatic Powder coating both inside and outside (Min
250 Microns)-RAL 5005 with Pocket Less Straight through body Passage conforming to
Design standards of DIN-3202F4/BS:5163 Type A Flange drilling as per IS - 1538
excluding all taxes, duties and transportation.
A) Without By-Pass
200 MM A) Without By-Pass PN 1.0 (MPa) 1.00 100.00 23980.00 23980.00
Transportation @ 5 % 1199.00
B) Without By-Pass
100 MM A) Without By-Pass PN 1.0 (MPa) 1.00 100.00 11880.00 11880.00
Transportation @ 5 % 594.00
Manufacture supply and delivery of Unplasticised PVC pipes for portable water suppliers
8 conforming to IS 4985/2000 with sacket as per specification. Inclusive of transportation
any ware in A.P. excluding excise duty and sales tax etc., complete
BLD-CSTN-2-5 -Plain Cement concrete nominal mix (1:4:8) prop (Cement : fine aggregate:
coarse aggregate ) using 40mm size Hard Granite Machine Crushed Metal including cost
and conveyance of all materials like cement, sand, coarse aggregate water etc., to site ,
9 seigniorage charges on all materials, labour charges , for mixing , laying, concrete ,
ramming in 15 cm layers, finishing top surface to the required level curing etc., complete
for finished item of work.for foundation and under flooring bed.
Unit = 1cum
A. MATERIALS:
Cement kg 162.00 3.90 631.80
Coarse aggregate 40 mm cum 0.90 911.80 820.62
Fine aggregate (Sand) cum 0.45 613.50 276.08
Water (including for curing) kl 1.20 107.00 128.40
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity hour 1.00
394.40 394.40
C. LABOUR:
Mason 1st class day 0.10 500.00 50.00
Mazdoor (unskilled) day 1.39 420.00 583.80
Add M.A @ 20% 126.76
3011.86
Add 13.615% Contractor Profit 392.81
Grand Total 3404.66
Unit = cum
Taking output = 75 cum (172.50 t)
(100 x 3.75 x 0.200)
a) Labour
Mate day -
Mason (1st class) day 5.00 500.00 2500.00
Mason (2nd class) day 5.00 460.00 2300.00
Mazdoor (Unskilled) day 150.00 420.00 63000.00
Mazdoor (Skilled) day 6.00 450.00 2700.00
Add 20% extra on Labour for Municipal limits day 0.20 14100.00
b) Machinery
Concrete mixer 0.28 / 0.4 cum capacity (6 mixers) hour 36.00 524.70 18889.20
with weigh batcher and suitable capacity
calibrated water tank
Needle vibrator hour 9.00 209.10 1881.90
Plate shearing machine up to 12 mm hour 9.00 368.80 3319.20
c) Material
Crushed stone coarse aggregates, grading will be cum 67.50 - -
as per Clause 1501.2.4.1 (Table 1500.1) of
specifications @ 0.90 cum/cum of concrete (20
mm & 10 mm blending)
(20mm & 10mm blending)
Cost of 20mm Metal (2/3 x 67.50) cum 45.00 1421.80 63981.00
Cost of HBG Metal 10mm (1/3 x 67.50) cum 22.50 1001.80 22540.50
Sand as per IS:383 and conforming to Clause cum 33.75 613.50 20705.63
1500.2.4.2 @ 0.45 cum/cum of concrete
Cement @ 350 kg/cum of concrete t 26.25 3900.00 102375.00
Water for curing kl 18.00 107.00 1926.00
Joint filler board 20 mm thick as per IS:1838 sqm 3.00 735.00 2205.00
(4 x 3.75 x 0.200 = 3 sqm) (BMT-U.02)
322423.43
Formwork 3% 9672.70
332096.13
Overheads & Contractors Profit @ 13.615% 43295.17
Rate per cum = a+b+c+d 375391.30
Rate per cum = a+b+c+d/75 5005.22
Lowering, laying, jointing and testing to hydralic test pressure including cost of water
with minimum water lead of 500m for UPVC pressure pipes in ready made trenches true to
11 alignment and gradient including all sundries but excluding cost & conveyance of pipes
from source of supply and jointing materials as per BIS No. 7634 - Part III - 1975.
BMWG.152
75 mm dia pipe
Weight of 1m length = (0.655+0.923+1.439)/3
=1.005 kgs
(a) Labour charges for laying, jointing & testing rm
1.00 70.00 70.00
COMMISSIONER
ASSISTANT ENGINEER NAGARA PANCHAYAT
NAGARA
PANCHAYAT CHIMAKURTHY
CHIMKAURTHY
Cetified that the above leads are correct to the best of my Knowledge and Belief.
Commissioner
Assistant Engineer
Chimakurthy nagara panchayat
Chimakurthy nagara panchayat
AMOUNT
648.00
1944.00
382.50
2975.00
Commissioner
thy nagara panchayat