BUILDERS’
BOOK
An illustrated guide to
building energy efficient homes
CONTACTS ACKNOWLEDGEMENTS
Further copies of this guide are The Zero Carbon Hub is very grateful to the following
available as a PDF download from contributors/organisations for their involvement in developing
www.zerocarbonhub.org this good practice guide.
2
CONTENTS
Introduction
How to use this book
Summary - Top Issues Leading to Poor Performance
Site Posters - Fabric and Services
1 Groundworks
2 Beam and Block Floor
3 Door Threshold 13
4 Cavity Wall 15
5 Cavity wall
6 Floor Joists
12
7 Separating wall
14 8 11
8 Lintels 9
9 Windows
10 Bay windows 6 7 4 5
11 Projecting windows
12 Eaves 10
13 Roof 16
3
14 Dryline / Plaster
15 Ventilation
16 Heating / hotwater 1 2
17 Finals
3
INTRODUCTION
The builders' book is a good craftsmanship guide that This edition of the builders’ book is for traditional
highlights key construction details when building a new masonry construction of new homes and extensions.
home, and good practice for delivering them. During It follows the construction phase of the house-
multiple site inspections, these details were most building process, and is aimed at helping site
commonly identified as requiring further guidance. personnel and trades improve quality of the
The book aims to improve the quality of new homes end product. It also highlights areas where built
built, especially with regards to comfort levels and environment professionals can improve the design.
energy bills. It helps builders improve site processes to
deliver better performing homes and reduce the risk of
condensation and mould growth, excessive heat loss
and failure to meet Building Regulations.
4
SUMMARY - TOP ISSUES LEADING TO POOR PERFORMANCE
Problems Recommendations
Different, lesser performing insulation fitted. Check insulation against design specification.
Product substitution for poorer materials: Check materials are same as design
blocks, insulation, windows, lintels, boiler, specification or discuss with architect/designer
controls, fans, windows, doors and lights all and site manager.
affect the energy efficiency of a new home.
Air leakage through small gaps in insulation, Make sure insulation has no gaps and is
blockwork and plasterboard can lead to heat sufficiently sealed at joints/ends.
losses and condensation issues.
Cold air blowing behind or through insulation. Fit insulation close to structure, and ensure
e.g. insulation floating off substrate. it is windtight. Seal accordingly.
Cold bridging: steel, concrete or timber Consult with design team. Designer to reduce
structure going through insulation layer. cold bridges as Part L Building Regulations.
Site damage of fragile materials including Ensure that insulation and other fragile
insulation, blocks and windows. Rain and mud materials are not damaged by rain, wind and
will worsen performance of materials. mechanical damage.
Services: ducting, TV aerial, lights can Check insulation in roof is continuous after all
all disrupt insulation in roof causing heat services have been installed. Ensure services in
loss / cold spots. service zone to stop this. Label importance of
insulation for homeowner.
Windows installed badly leading to airleakage Ensure correct windows installed with less than
and heat loss. 10mm tolerance.
5
ZERO CARBON HUB BUILDERS' BOOK
FOUNDATION /
GROUNDWORKS 1.0
PROBLEM TO AVOID INSULATION MISSING BELOW DPC
OUTSIDE
COLD SPOT =
CONDENSATION
INSULATION
MISSING
BRICK
INSULATION
BLOCK
INSIDE
WHAT TO DO?
it insulation boards
F
tight to blockwork with
no air gap (3)
AIR GAP
FLOOR
© NHBC INSULATION
it horizontal floor
F
insulation tight with no
gaps between boards
estrain perimeter
R
floor insulation to
prevent ‘floating’ during SERVICE PIPE CUT
screed pour THROUGH INSULATION
WITH TIGHT FIT
revent screed bridging
P
the perimeter insulation
GOOD PRACTICE Fit insulation boards tightly and seal all penetrations
DOOR
THRESHOLD 3.0
PROBLEM TO AVOID MISSING EDGE INSULATION
INCORRECT OR MISSING
EDGE INSULATION
THERMAL BRIDGE
FINISH
SCREED
INSULATION
INSULATION
MISSING
FLOOR STRUCTURE
WHAT TO DO?
Install a thermal
break at the
threshold – at
least 25mm high REINFORCED THRESHOLD PERIMETER
performance CAVITY DRAIN INSULATION
insulation CLOSER
Install damp proof AIRCRETE
membrane, gas
membranes and FINISH
separating layer as SCREED
necessary INSULATION
GOOD PRACTICE 50mm thick insulation at door threshold or reinforced cavity closer
CAVITY WALL
4.0
PROBLEM TO AVOID GAPS IN INSULATION
INSULATION
NOT TIGHT
GAPS!
TO WALL
AIR GAP FACE DUE TO
ROUGH
SURFACE
CREATED
BY EXCESS
MORTAR
GAPS BETWEEN
ADJACENT BOARDS
= HEAT LOSS
WHAT TO DO?
1 3
CAVITY WALL
5.0
PROBLEM TO AVOID MISSING INSULATION
MISSING
INSULATION
MISSING
NO INSULATION
BEHIND METER BOX
WHAT TO DO?
INSULATION CUT
Install rigid insulation BEHIND CAVITY
behind steel beams, TRAYS
cavity trays, meter boxes
and subfloor vents or any
other elements bridging
cavity
Blown or injected
insulation, ensure this
reaches the whole wall
with no gaps
FLOOR JOISTS
6.0
PROBLEM TO AVOID AIR-LEAKAGE AROUND JOISTS
AIR GAP
MORTAR SLUMP
DIFFICULT TO SEAL
FOR AIRTIGHTNESS
MORTAR WILL NOT BE AIRTIGHT AROUND JOISTS
WHAT TO DO?
GOOD PRACTICE Apply parge coat to party wall to ensure continuous airtightness line
SEPARATING WALL
7.0
PROBLEM TO AVOID INCORRECTLY SEALED PARTY WALL
TOP
ROOF TILES
INSULATION POORLY
UNPROTECTED
SEALED
JUNCTIONS
AND AIR GAPS
IN INSULATION
EDGE ALLOWS HEAT
SEAL LOSS
LOFT
INSULATION
WHAT TO DO?
3
Ensure fully filled
mortar joints (1)
GOOD PRACTICE Cavity should be fully filled with edge seal at wall end and roof junctions
LINTELS
8.0
PROBLEM TO AVOID COLD BRIDGING & MISSING INSULATION
CONTINUOUS
SPLIT PLATE
INSULATION
GAP
CONTINUOUS
SPLIT PLATE
ut insulation tight
C
around lintel and
cavity tray
Improve energy
performance by using
separate lintels or
thermally broken lintels
Cavity trays to be
installed as needed
WINDOW INSTALLATION
9.0
PROBLEM TO AVOID WINDOWS INSTALLED FORWARD OF DESIGN POSITION
INSIDE
COLDSPOT
WHAT TO DO?
GOOD PRACTICE A large overlap with cavity will improve thermal performance. For improved
airtightness, use air barrier tapes between the window/door and structure
BAY WINDOWS
10.0
PROBLEM TO AVOID COLD BRIDGING
COLDSPOT
Continuous insulation
inside
PROJECTING WINDOWS
11.0
PROBLEM TO AVOID COLD BRIDGING
INSIDE
COLD SPOT
UNINSULATED STEEL
& CONCRETE
CONTINUOUS
STEEL CREATES
COLD BRIDGE
WHAT TO DO?
STEEL AND
educe thermal bridges
R TIMBER
of steel, concrete STRUCTURE
or timber through
insulation layer
Install continuous
insulation outside
structure 1
If GRP structure, ensure
sufficient thickness
of continuous insulation
as design
EAVES
12.0
PROBLEM TO AVOID NO INSULATION AT EAVES
NO SPACE FOR
INSULATION
SQUASHED INSULATION
INSULATION MISSING
REDUCED SPACE
ABOVE JOISTS MAKES
INSTALLATION OF FULL
INSULATION IMPOSSIBLE
150mm
Install rigid insulation to
top of the wall plate (1)
2
2
300mm
russ design to
T
accommodate space
for insulation at eaves -
300mm is best practice (2)
1 1
ay mineral wool
L
insulation into eaves (3)
4
OPTION 2 - WITH EAVES LINTEL
© CREST NICHOLSON
ROOF
13.0
PROBLEM TO AVOID MISSING ROOF INSULATION
SERVICES DISRUPT
INSULATION
ROOF
INSULATION DOWNLIGHTERS
= HEAT LOSS
INSULATION DISTURBED BY SERVICES
WHAT TO DO?
Install continuous
insulation across the roof
and into the eaves
se insulation
U
support box above
down-lighters to maintain
insulation thickness and
prevent burn
GOOD PRACTICE Cross lapped insulation checked at final inspection before handover
DRYLINE/
PLASTER 14.0
PROBLEM TO AVOID AIR-LEAKAGE
AIR GAP
AIR GAP
WHAT TO DO?
MARK
Foam fill all penetrations/ SOLID DAB
gaps before drylining
© CREST NICHOLSON
GOOD PRACTICE Use a parge coat or plaster on block work to improve airtightness
VENTILATION
15.0
PROBLEM TO AVOID POORLY SPECIFIED AND INSTALLED DUCTWORK
FLEXI DUCT TOO LONG AND NOT SUPPORTED = FANS WILL BE NOISY / INEFFICIENT
VENTILATION COMMISSIONING NOT DONE CORRECTLY
WHAT TO DO?
ommissioning
C
sheets to be provided to
site manager
HEATING /
HOT WATER 16.0
PROBLEM TO AVOID HEAT LOSS THROUGH UNINSULATED PIPES
PIPES NOT
INSULATED
AIR GAP
GOOD PRACTICE Pipe insulation continuous around the full length and secured in place
FINALS
17.0
PROBLEM TO AVOID AIR LEAKAGE AS SEALANT DOES NOT LAST
MISSING
SKIRTING
SEALANT
SEAL IN
VULNERABLE
POSITION
GOOD PRACTICE Final inspection to use eyeball test to pick up on missing insulation
Notify SAP Assessor of changes to original design