Computation of Project Duration

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

-COMPUTATION OF PROJECT DURATION

-Table from Department Order No. 71, Series of 2013, ANNEX B - b - 2


Reinforced Concrete, Type 1
Interpolated Values
Length 1198.00 1796.83 2994.50 *
Reference/Given Amount 20,000,000.00 30,000,000.00 50,000,000.00
Reference Duration 264 395.67 659
Duration Reduction Factor 0.4 0.333 0.2
Estimated Duration 120.60 146.89 146.80 **
"Say" 121 147.00 147

* Assumed Equivalent Length without Steel Sheet Pile 147 = 147


Project Cost = 30,000,000.00 ∴ use 147 days
** Computations from Department Order No. 71, Series of 2013, ANNEX A
Calendar Days = [(given reference amount X reference duration per ln.m.)/estimated
amount per ln.m.] X Duration Reduction Factor
+ (duration of mob./demob. on the given reference amount)
Mob./Demob. Duration for P5 Million up to P50 Million - 15 c.d.