HOUSE DRAINS AND HOUSE SEWER

SECTION 1201 SEWER REQUIRED


- Connection to a Public or Private Excreta Sewerage system
- No public sewer -drainage piping shall connect to a private sewage disposal sys.
- mandatory connection to an existing public sewer fronting the lots
- Public sewer is not available 62 meters from any proposed building
- No permit shall be issued for the installation, alteration or repair of any
private sewage disposal system
- Every lot shall be connected with such Public sewer

SECTION 1202 DAMAGE TO PUBLIC SEWER/PRIVATE SEWAGE


DISPOSAL SYSTEM
- Deposition of any material that could damage the disposal system is unlawful
- Rain or surface water shall not be discharged into excreta drainage system
- No Cesspool, Septic tank effluents, Seepage pit or Underdrain system
shall be connected to the excreta building sewer leading to public sewer main
- No food waste grinder shall be connected to disposal system
- Approved Type Watertight Sewage
*Waste water holding tank

SECTION 1203 BUILDING SEWER MATERIALS


- Building Sewer
beginning 0.60 meters from the outside face of the wall

SECTION 1204 MARKINGS


- Approved requirements

SECTION 1205 SIZE OF THE BUILDING SEWER


Table 12-2
- Basis on the total number of fixture units drained by sewer
*Minimum Size of Building sewer = 150 mm or 6"

SECTION 1206 GRADE, SUPPORT and PROTECTION of BUILDING SEWER


- Building Sewers
a. Slope
20mm/m or 2% towards
1. Septic tank
2. Street sewer main
Except
a. Due to the depth of the street sewer
b. Due to structural features conflict
c. Due to adverse arrangement of any building
20mm/m or 2% smaller than 102 mm pipe
10mm/m or 1% 102 mm to 152.4 mm pipe
5mm/m or 5% 204 mm or larger
b. Shall be laid over Conrete Cradle or Bed
c. Shall be laid 0.60 meters from the building wall, or 0.30 meters below the
finish surface of the ground

SECTION 1207 CLEANOUTS


- CO not required for 3.0 meter length of building sewer from building drain
Note
All required building sewer cleanouts shal be extended to finish grade
- CO shall be installed to allow cleaning on the direction of flow, or at
right angle
- CO under concrete or asphalt shall be made accessible by strong yard boxes
with hinged cover or extending the top cover with counter sunk operating
nut flush
- CO on manhole should be approved by the administrative authority
*Maximum distance of Manhole = 91.0 meters
- Inlet and outlet pipes connection of manhole shall be made by a Flexible
Compression Joints and closer than 0.3 meters
- No flexible compression joint shall be embedded inside the manhole base

SECTION 1208 SEWER AND WATER PIPES


- Bottom of the water pipe at all points shall have atleast 3.0 meters
above the top of the drain line
- The water pipe shall be placed on a solid shelf with horizontal clear
distance atleast 3.0 meters
- Water pipe crossing sewer line shall be laid 3.0 meters above the sewer or drain line
- Water pipe joints shall have a clear distance of 3.0 meters to any sewer line

SECTION 1209 LOCATIONS

SECTION 1210 ABANDONED SEWERS AND SEWAGE DISPOSAL FACILITIES


- Every abandoned sewer line shall be Plugged or Capped 1.50 meters
from the property line
- All abandoned sewerage compartments shall have the sewage removed and
completely filled with Earth, Sand , Gravel, Concrete or approved materials