Professional Documents
Culture Documents
BRIDGE-TO-INDIA Anti Dumping Duty
BRIDGE-TO-INDIA Anti Dumping Duty
Policy Brief
on PV cells and modules
November 2017
Introduction
In July 2017, India Solar Manufacturers Association (ISMA) filed a petition
with Directorate General of Anti-Dumping & Allied Duty (DGAD), Ministry of
Commerce and Industry, Government of India for investigating imports of solar
cells and modules from China, Taiwan and Malaysia. The investigation petition
covers both thin film and crystalline technologies and affects imports making
up more than 85% of total cells and modules used in India.
As described in Section 9A (1), Customs Tariff Act, 1975, DGAD may recommend
an anti-dumping duty not exceeding dumping margin or the injury margin. DGAD
is required to conclude the investigation and give its recommendation to the
Ministry of Finance within 12 months, subject to a 6-month extension in certain
cases. Final decision on appropriate trade remedies is taken by the Ministry of
Finance. Under the Act, the anti-dumping duty is imposed for a time-period of 5
years. At the end of this period, DGAD is required to conduct a sunset review to
determine if the imposed duty needs to continue. It can also conduct an interim
DGAD may also decide to review to examine need for continued imposition of the duty.
impose a provisional duty,
is levied under critical Analysing timelines of 35 anti-dumping cases from 1999-2016 in India in
circumstances in which which anti-dumping duties were levied, we observed that the anti-dumping
duty decision took an average of 15 months from initiation of investigation. For
there is a clear evidence that
instance, an anti-dumping petition was filed in Jun-2016 for colour coated, pre-
imports have caused serious painted flat steel products imported from China and EU and the anti-dumping
injury to the domestic duty was imposed in Aug-2017, 14 months after petition submission date. As
industry per this time line, final decision on anti-dumping duty on import of PV cells and
modules may be expected by October 2018.
Some industry experts feel that DGAD may also decide to impose a provisional
duty. Provisional duty is levied under critical circumstances in which there is a
clear evidence that imports have caused serious injury to the domestic industry.
Expected Expected
provisional duty anti-dumping duty
2017 2018
Source: BRIDGE TO INDIA research
But there is a very strong buzz in the industry that a duty announcement is
about to come anytime now. The government is under pressure about the
poor state of manufacturing despite its ‘Make in India’ initiative and ten times
growth in module demand in the last three years. If DGAD and the Ministry of
Finance are sympathetic to the case, it is certainly possible that a provisional or
anti-dumping duty may be imposed imminently.
3,000
ADD imposed in Oct-2018
2,000
1,500
1,200
1,000 750
340 500 500
100 250 250 250
0
Pending pipeline
Pending pipeline
Karnataka-1,200 MW
SECI-Andhra
Pradesh-100 MW
SECI-
Bhadla-250 MW
SECI-Bhadla-500 MW
Tamil Nadu-1,500 MW
NTPC-Kadapa-250 MW
NTPC-250 MW
Gujarat-500 MW
Madhya Pradesh-
REWA-750 MW
Commissioning timeline
Open DCR
6.0 6.0
5.4 5.4
6 4.7
4.1
3.7
4
0
0% 10% 20% 30% 40%
Anti-dumping duty, %
The optimistic scenario for the sector is that projects auctioned before the date
of petition (July 2017) are grandfathered or that the central or state governments
compensate them for extra costs. We are however, not aware of any such
precedence across different sectors and believe that the probability of such an
outcome is at best 50%.
Some developers have argued that they would seek change-in-law protection if
a provisional or anti-dumping duty is imposed. Our analysis shows that if 30%
duty is imposed and module cost is USD 0.36/ Wp, tariff will need to go up by
Upcoming auctions
Solar auctions in India are Any auctions conducted while a duty decision is pending also face an uncertain
so aggressive that it seems future. As of September 2017, there are 2,655 MW (2,087 MW in open category
and 568 MW in DCR category) of tenders, which have been announced and are
unrealistic a developer awaiting auctions. SECI is expected to imminently conduct an auction for 750
building a sufficient financial MW in Bhadla solar park.
buffer would be able to win
any capacity The challenge for developers is how to price duty risk. Solar auctions in India
are so aggressive that it seems unrealistic a developer building a sufficient
financial buffer would be able to win any capacity. The recent Gujarat 500 MW
auction in September 2017, is a good example – it was won by Azure Power,
GRT Jewellers, Gujarat State Electricity Corporation Limited and Gujarat
Industries Power Company Limited at extremely competitive tariffs between
INR 2.65-2.67/ kWh.
There are two broad range of possibilities for auctions held in the intervening
period, both equally unappealing – developers continue to bid aggressively, in
which case, the projects would be financially unviable if a duty is subsequently
announced; or the developers exercise restraint, resulting in less competition
and higher tariffs, in which case, the DISCOMs might retreat and refuse to sign
PPAs as seen in many tenders recently.
Others
10%
India
11%
China
79%
Operational capacity, MW
5,507
Actual production, MW
1,764
Installed capacity, MW
3,164
Operational capacity, MW
1,667
Actual production, MW
591
The key issue for the sector The domestic manufacturers have been struggling because of their inability to
is whether Indian or other compete on price with Chinese manufacturers. Most of them have sub-scale
capacities, high cost base and are completely reliant on imported technology
manufacturers would be and raw materials. Imposition of ADD or provisional duty exceeding 10% shall
able to use the opportunity enable them to price at profitable levels and increase production.
afforded by duties to make
investments and create a But the key issue for the sector is whether Indian or other manufacturers
thriving, competitive module would be able to use the opportunity afforded by duties to make investments
manufacturing sector in India and create a thriving, competitive module manufacturing sector in India. There
is a huge gulf between the scale and technological or operational capability
of Indian and Chinese manufacturers. Moreover, the Chinese manufacturers
have been expanding internationally to counter threat from trade barriers.
Canadian Solar, Jinko, Trina, JA Solar and Talesun are some of the notable
names to set up manufacturing facilities in Indonesia, South Korea, South
Africa and Thailand precisely for such purposes. They should be able to
circumvent duties, at least partly, by routing exports from these manufacturing
bases, in turn mitigating the negative and positive impact on developers and
manufacturers respectively.
We believe that trade barriers alone will fail to achieve their target to promote
domestic manufacturing unless they are backed up by other policy reforms to
improve competitiveness of Indian manufacturing.
Disclaimer
For further enquiries, © 2017 BRIDGE TO INDIA Energy Private Limited
please contact
contact@bridgetoindia.com
Authors
Arti Mishra Saran, BRIDGE TO INDIA
BRIDGE TO INDIA Energy Pvt. Ltd.
Vinay Rustagi, BRIDGE TO INDIA
C - 8/5, DLF Phase I,
Gurgaon 122001 India This report is owned exclusively by BRIDGE TO INDIA and is protected by Indian
www.bridgetoindia.com copyright and international copyright and intellectual property laws.
Subscribe to our mailers BRIDGE TO INDIA hereby grants the user a personal, non-exclusive, non-
contact@bridgetoindia.com transferable license to use the report pursuant to the terms and conditions
of this agreement. The user agrees not to export full or any part of the report
Read our blog for up-to-date to a country that does not have copyright and intellectual property laws that
market insights and opinions will protect BRIDGE TO INDIA's rights therein. The user cannot engage in
www.bridgetoindia.com/blog any unauthorized use, reproduction, distribution, publication or electronic
transmission of this report or the information/forecasts therein without the
Track the Indian solar market express written permission of BRIDGE TO INDIA.
with our reports
www.bridgetoindia.com/reports The information contained in this report is of a general nature and is not
intended to address the requirements of any particular individual or entity.
Follow us on Twitter BRIDGE TO INDIA aims to provide accurate and up-to-date information, but is
www.twitter.com/bridgetoindia not legally liable for accuracy or completeness of such information.
Follow us on
www.facebook.com/bridgetoindia