Exhibit D - Milestone Payment Schedule

Construction Contract / Contract Amendment 1

ACHIEVED 31-03-17

RE-SCHEDULE

(1) Advance Payment

(2) Pre-NTP Payment

Milestone Milestone Milestone


Project Month Start Finish Achievement Achievement Achievement LOT Milestone ID SC Wasa Milestone Event Supporting Documents
(Estimate) (signed by EPC) (signed by BJP)

4 ON - ○ Advance Payment N/A


Sep-16 4 ON Pre-1 ○ Mobilization of Manpower & Equipment Photo report evidencing achievement of Milestone and acknowledged by Owner
Before
Jan-17 4 ON Pre-2 ○ Completion of pavement works of Access road Field Inspection Report signed by Owner
Commencement
Date Jan-17 4 ON Pre-3 ○ Completion of Access road works Field Inspection Report signed by Owner
Mar-17 4 ON Pre-4 ○ Completion of Sekuping gate modification works Field Inspection Report signed by Owner
Mar-17 4 ON Pre-5 ○ Completion of all works Field Inspection Report signed by Owner

(3) Milestone Payment

Project Month Start Finish LOT Milestone ID SC Wasa Milestone Event Supporting Documents

Apr-18 20-04-18 23-04-18 1 ON 1-1 ○ Receiving Material for 1st Earthing Grid Work Material Receiving Report
Project Specific Technical Documents Required for Subcontractor Specifications (Document No.
1 31-03-17 30-04-17 May-17 N/A 08-05-17 3 ON 1-2 ○ Prepare Project specific commercial and technical documents required for subcontractor specifications
TJB56-L3-OPN-C-00-F-SPC-0001-RA)
May-17 N/A 08-05-17 4 ON 1-3 ○ Completion of Soil Investigation for DEX (study report of SNI & Soil Resistivity) Soil Investigation Report
Jul-17 N/A 13-07-17 2 ON 2-1 ○ Delivery to site of Anchor Frame for Pulverizer for Unit 5 Material Receiving Report
Contractor's transmittal by which the Technical Specification of Field Erected Tanks is submitted
2 01-05-17 31-05-17 Jun-17 N/A 05-06-17 3 ON 2-2 ○ Completion of Technical Specifications - Field Erected Tanks
to Owner
Oct-17 26-10-17 4 ON 2-3 ○ Completion of Deep Well Drilling for Batching Plant Copy of SIP license and Field Inspection Report signed by Owner
Contractor's transmittal by which the Technical Specification of M&E Construction is submitted to
Jun-17 N/A 23-06-17 3 ON 3-1 ○ Completion of Technical Specifications- M&E Construction
3 01-06-17 30-06-17 Owner
Aug-17 N/A 31-08-17 4 ON 3-2 ○ Completion for PC Pile Delivery for Boiler Unit 5 Material Receiving Report
May-18 24-05-18 25-05-18 1 ON 4-1 ○ Receiving Material for 2nd Earthing Grid Work Material Receiving Report
4 01-07-17 31-07-17 Jul-17 N/A 13-07-17 3 ON 4-2 ○ Mobilize to Site for Site Services Notification Letter acknowledged by Owner
Sep-17 19-09-17 4 ON 4-3 ○ Completion for construction of Batching Plant Site Inspection Report
Jul-17 N/A 27-07-17 3 ON 5-1 ○ Completion of Technical Specifications - Insulated Conductors Contractor's transmittal by which the Technical Specification is submitted to Owner
5 01-08-17 31-08-17
Sep-17 28-09-17 4 ON 5-2 ○ Completion for PC Pile Delivery for Central Control & Electrical Switchgear Building Material Receiving Report
May-18 24-05-18 25-05-18 1 ON 6-1 ○ Receiving Material for 3rd Earthing Grid Work Material Receiving Report
6 01-09-17 30-09-17 Sep-17 19-09-17 3 ON 6-2 ○ Completion of Technical Specifications - Cable Tray Contractor's transmittal by which the Technical Specification is submitted to Owner
Sep-17 28-09-17 3 ON 6-3 ○ Completion of PC Pile Delivery for Steam Turbine Building Unit 5 Material Receiving Report
Oct-17 20-10-17 2 ON 7-1 ○ Delivery to site of Anchor Frame for Pulverizer for Unit 6 Material Receiving Report
7 01-10-17 31-10-17
Jan-18 25-01-18 30-01-18 4 ON 7-2 ○ (CHO) Commencement of SWFGD Piping Installation at Section 1 Civil Handover Certificate
Unpriced LOI or LOA or PO issued to Supplier to be submitted as proof of placement of Award
Sep-17 19-09-17 3 ON 8-1 ○ Completion of Award - Field Erected Tanks
with Supplemental Letter from Lot 3
8 01-11-17 30-11-17
Dec-17 22-12-17 26-12-17 3 ON 8-2 ○ Completion of PC Pile Delivery for Aeration Basin, Discharge Basin and Aeration Pump Basin Material Receiving Report
Nov-17 30-11-17 4 ON 8-3 ○ Execution of Change Order Copy of Executed Change Order
Unpriced LOI or LOA or PO issued to Supplier to be submitted as proof of placement of Award
Sep-17 19-09-17 3 ON 9-1 ○ Completion of Award - Field Applied Protective Coating
9 01-12-17 31-12-17 with Supplemental Letter from Lot 3
Jan-18 25-01-18 30-01-18 4 ON 9-2 ○ (CHO) Commencement of SWFGD Piping Installation at Section 2 Civil Handover Certificate
Jan-18 24-01-18 25-01-18 3 ON 10-1 ○ Start Erection of SWFGD U/G Pipe Notification Letter with Photo
10 01-01-18 31-01-18
Jan-18 25-01-18 30-01-18 4 ON 10-2 ○ Completion of PC Pile Delivery for Steam Turbine Building Unit 6 Material Receiving Report
Unpriced LOI or LOA or PO issued to Supplier to be submitted as proof of placement of Award
Sep-17 11-09-17 19-09-17 3 ON 11-1 ○ Completion of Award - Insulated Conductors
11 01-02-18 28-02-18 with Supplemental Letter from Lot 3
Feb-18 21-02-18 23-02-18 4 ON 11-2 ○ (CHO) Commencement of SWFGD Piping Installation at Section 3 Civil Handover Certificate

12 01-03-18 31-03-18 Feb-18 21-02-18 23-02-18 4 ON 12-1 ○ Completion of PC Pile Delivery for Transformer Unit 5 Material Receiving Report

Unpriced LOI or LOA or PO issued to Supplier to be submitted as proof of placement of Award


Apr-18 05-04-18 09-04-18 3 ON 13-1 ○ Completion of Award - BMH Mobile Equipment
13 01-04-18 30-04-18 with Supplemental Letter from Lot 3
Apr-18 24-04-18 27-04-18 4 ON 13-2 ○ (CHO) Commencement of SWFGD Piping Installation at Section 4 Civil Handover Certificate
Jul-18 25-07-18 26-07-18 1 ON 14-1 ○ Delivery to Site of Embedded Material for Steam Turbine (Unit 5) Material Receiving Report
Unpriced LOI or LOA or PO issued to Supplier to be submitted as proof of placement of Award
14 01-05-18 31-05-18 Mar-18 01-03-18 02-03-18 3 ON 14-2 ○ Completion of Award - Cable Tray
with Supplemental Letter from Lot 3
May-18 22-05-18 24-05-18 4 ON 14-3 ○ (CHO) FDN_Boiler Area for Preparation Work (Unit 5) Civil Handover Certificate
Jun-18 25-06-18 26-06-18 2 ON 15-1 ○ Start of Boiler Steel Structure Erection for Unit 5 Notification Report with photo
Unpriced LOI or LOA or PO issued to Supplier to be submitted as proof of placement of Award
15 01-06-18 30-06-18 Dec-17 26-12-17 27-12-17 3 ON 15-2 ○ Completion of Award - Fuel Oil Filling Facility
with Supplemental Letter from Lot 3
Jun-18 06-06-18 08-06-18 4 ON 15-3 ○ (CHO) FDN_Boiler Partial Access (Unit 5) (see note: 10) Civil Handover Certificate
Apr-18 05-04-18 09-04-18 3 ON 16-1 ○ Mobilization of B&V Erection Subcontractor Notification Letter
16 01-07-18 31-07-18
Jun-18 06-06-18 08-06-18 4 ON 16-2 ○ (CHO) Boiler FDN for Erection (Unit-5) Civil Handover Certificate
Jan-19 24-01-19 25-01-19 1 ON 17-1 ○ Factory Acceptance Test (Functional Test ) of EOT (Electric Overhead Traveling) Crane (Unit 5) Test Report
17 01-08-18 31-08-18
Sep-18 21-09-18 25-09-18 4 ON 17-2 ○ (CHO) Commencement of SWFGD Piping Installation at Section 5 Civil Handover Certificate

190304 Exhibit D - Milestone Payment Schedule (Contract Amend 1) for MAR (PM23)_PK 1/5
Exhibit D - Milestone Payment Schedule
Construction Contract / Contract Amendment 1

ACHIEVED 31-03-17

RE-SCHEDULE

(1) Advance Payment

(2) Pre-NTP Payment

Milestone Milestone Milestone


Project Month Start Finish Achievement Achievement Achievement LOT Milestone ID SC Wasa Milestone Event Supporting Documents
(Estimate) (signed by EPC) (signed by BJP)

Sep-18 20-09-18 21-09-18 3 ON 18-1 ○ Complete Erection (First step) - Water Treatment Equipment Notification Letter with Photo
18 01-09-18 30-09-18 Aug-18 21-08-18 27-08-18 3 ON 18-2 ○ Initial Delivery to Site - Insulated Conductors Material Receiving Report
Nov-18 15-11-18 21-11-18 4 ON 18-3 ○ (CHO) 500kV SWYD Civil Handover Certificate
Dec-18 21-12-18 26-12-18 1 ON 19-1 ○ Delivery to Site of Embedded Material for Steam Turbine (Unit 6) Material Receiving Report
Oct-18 15-10-18 19-10-18 3 ON 19-2 ○ Initial Delivery to Site - Cable Tray Material Receiving Report
19 01-10-18 31-10-18
Oct-18 24-10-18 25-10-18 3 ON 19-3 ○ Completion of First Step Erection for Demineralization Plant Notification Letter with Photo
Oct-18 22-10-18 23-10-18 4 ON 19-4 ○ (CHO) Dehydrator Civil Handover Certificate
Nov-18 21-11-18 22-11-18 2 ON 20-1 ○ First Header Lifting for Unit 5 Notification Report with photo
Nov-18 21-11-18 22-11-18 2 ON 20-2 ○ Start of Boiler Steel Structure Erection for Unit 6 Notification Report with photo
20 01-11-18 30-11-18
Nov-18 22-11-18 23-11-18 3 ON 20-3 ○ Complete Erection (First step) - Compressed Air Equipment Water Treatment Area Milestone Certificate of initial installation or project pictures of the work
Dec-18 06-12-18 12-12-18 4 ON 20-4 ○ (CHO) Unloading Ramp (West) Civil Handover Certificate
Jan-19 21-01-19 21-01-19 2 ON 21-1 ○ Start of erection for SH&RH Pendant Coils for Unit 5 Notification Report with photo
Dec-18 21-12-18 21-12-18 3 ON 21-2 ○ Complete Erection (First step) - Wastewater Treatment Equipment Notification Letter with Photo
21 01-12-18 31-12-18
Jan-19 21-01-19 21-01-19 3 ON 21-3 ○ Complete Erection (First step) -Conveyor Structural Steel Notification Letter with Photo
Mar-19 4 ON 21-4 ○ (CHO) EOT Crane Rail Girder (TA&TE, T1~T13) (Unit 5) Civil Handover Certificate
Jan-19 24-01-19 25-01-19 1 ON 22-1 ○ Factory Acceptance Test (Functional Test) of EOT (Electric Overhead Traveling) Crane (Unit 6) Test Report
22 01-01-19 31-01-19 Jan-19 21-01-19 21-01-19 3 ON 22-2 ○ Start LV Switchgear Erection (Water Treatment) Notification Letter with Photo
Jan-19 29-01-19 30-01-19 4 ON 22-3 ○ (CHO) Dea FL Rail Setting allowed (T1-T12) (Steam Turbine Building) Civil Handover Certificate
Mar-19 2 ON 23-1 ○ Start of Pulverizer Assembly for Unit 5 Notification Report with photo
23 01-02-19 28-02-19 Mar-19 3 ON 23-2 ○ Complete Erection (First step) -Conveyor Equipment Notification Letter with Photo
Mar-19 4 ON 23-3 ○ (CHO) Dea FL Rail Setting allowed (T12-T15) (Steam Turbine Building) Civil Handover Certificate
Apr-19 1 ON 24-1 ○ Delivery to Site of Sole Plate for Steam Turbine (Unit 5) Material Receiving Report
24 01-03-19 31-03-19 Nov-18 22-11-18 23-11-18 3 ON 24-2 ○ Complete Erection (First step) - Field Erected Tanks (De Min) Notification Letter with Photo
Apr-19 4 ON 24-3 ○ (CHO) Full Access to Elevated Slab (GL, T1-T13) (Steam Turbine Building) Civil Handover Certificate
May-19 1 ON 25-1 ○ Delivery to Site of Generator Stator / Condenser Shell (Unit 5) Material Receiving Report
Apr-19 2 ON 25-2 ○ Start of Erection for SH, RH&Eco Horizontal Coils for Unit 5 Notification Report with photo
Apr-19 2 ON 25-3 ○ First Header Lifting for Unit 6 Notification Report with photo
Apr-19 3 ON 25-4 ○ Completion of Initial Walkdown - Medium Voltage Switchgear (Unit 5) Copy of Initial Walkdown Completion Certificate
Apr-19 3 ON 25-5 ○ Completion of Initial Walkdown - Unit Substation Transformers (Unit 5) Copy of Initial Walkdown Completion Certificate
25 01-04-19 30-04-19 Apr-19 3 ON 25-6 ○ Completion of Initial Walkdown - Distribution Transformer (Unit 5) Copy of Initial Walkdown Completion Certificate
Apr-19 3 ON 25-7 ○ Completion of Initial Walkdown - Wastewater Treatment Equipment (De sal) Copy of Initial Walkdown Completion Certificate
Apr-19 3 ON 25-8 ○ Completion of Initial Walkdown - Wastewater Treatment Equipment (Cycle Makeup) Copy of Initial Walkdown Completion Certificate
Apr-19 3 ON 25-9 ○ Complete Erection (First step) - Fire Water Pumps Notification Letter with Photo
Apr-19 3 ON 25-10 ○ Complete Erection (First step) - Seawater FGD (Unit 5) Notification Letter with Photo
Apr-19 4 ON 25-11 ○ (CHO) Stacker and Reclaimer Foundation_North Civil Handover Certificate
May-19 1 ON 26-1 ○ Delivery to Site of Steam Turbine (HP Casing) (Unit 5) Material Receiving Report
May-19 2 ON 26-2 ○ Start of Eerection for Spiral Wall for Unit 5 Notification Report with photo
May-19 2 ON 26-3 ○ Start of Erection for SH&RH Pendant Coils for Unit 6 Notification Report with photo
May-19 3 ON 26-4 ○ Completion of Pre-Operational Checkout - Medium Voltage Switchgear Copy of Preoperational Checkout Commencement Certificate
May-19 3 ON 26-5 ○ Completion of Pre-Operational Checkout - Unit Substation Transformers Copy of Preoperational Checkout Commencement Certificate
26 01-05-19 31-05-19 May-19 3 ON 26-6 ○ Completion of Pre-Operational Checkout - Distribution Transformer Copy of Preoperational Checkout Commencement Certificate
May-19 3 ON 26-7 ○ Completion of Initial Walkdown - Compressed Air Equipment Water Treatment Area Copy of Initial Walkdown Completion Certificate
May-19 3 ON 26-8 ○ Completion of Initial Walkdown - Water Treatment Equipment Copy of Initial Walkdown Completion Certificate
May-19 3 ON 26-9 ○ Completion of Pre-Operational Checkout - Wastewater Treatment Equipment (De sal) Copy of Preoperational Checkout Commencement Certificate
May-19 3 ON 26-10 ○ Completion of Pre-Operational Checkout - Wastewater Treatment Equipment (Cycle Makeup) Copy of Preoperational Checkout Commencement Certificate
May-19 4 ON 26-11 ○ (CHO) Intake Pond (Unit-5) Fore Bay Flooding Civil Handover Certificate
Apr-19 1 ON 27-1 ○ Delivery to Site of Generator Transformer Main Tank Assembly (Unit 5) Material Receiving Report
Jun-19 2 ON 27-2 ○ Start of IDF Erection for Unit 5 Notification Report with photo
Jun-19 3 ON 27-3 ○ Completion of Pre-Operational Checkout - Compressed Air Equipment Copy of Preoperational Checkout Commencement Certificate
Jun-19 3 ON 27-4 ○ Complete Erection (First step) - Fire Protection and Detection System Notification Letter with Photo
27 01-06-19 30-06-19 Jun-19 3 ON 27-5 ○ Complete Erection (First step) - Diesel Generators (Unit 5) Notification Letter with Photo
Jun-19 3 ON 27-6 ○ Completion of Pre-Operational Checkout - Water Treatment Equipment Copy of Preoperational Checkout Commencement Certificate
Jun-19 3 ON 27-7 ○ Complete Erection (First step) - Auxiliary Boiler Notification Letter with Photo
Jun-19 3 ON 27-8 ○ Complete Erection (First step) - Circulating Water Pumps (Unit 5) Notification Letter with Photo
Jun-19 4 ON 27-9 ○ (CHO) Aux. Boiler System (PP-600) Civil Handover Certificate
May-19 1 ON 28-1 ○ Delivery to Site of DCS (Common Electrical control Cubicle "CES" for Common DCS System) (Unit 5) Material Receiving Report
Jul-19 2 ON 28-2 ○ Start of Pulverizer Assembly for Unit 6 Notification Report with photo
28 01-07-19 31-07-19 Jul-19 3 ON 28-3 ○ Complete Erection (First step) - Fly Ash Conveying System (Unit 5) Notification Letter with Photo
Jul-19 3 ON 28-4 ○ Complete Erection (First step) - Fuel Oil Pumps Notification Letter with Photo
Jul-19 4 ON 28-5 ○ (CHO) Fuel Oil Pump House Civil Handover Certificate
Jun-19 1 ON 29-1 ○ Delivery to Site of Sole Plate for Steam Turbine (Unit 6) Material Receiving Report

190304 Exhibit D - Milestone Payment Schedule (Contract Amend 1) for MAR (PM23)_PK 2/5
Exhibit D - Milestone Payment Schedule
Construction Contract / Contract Amendment 1

ACHIEVED 31-03-17

RE-SCHEDULE

(1) Advance Payment

(2) Pre-NTP Payment

Milestone Milestone Milestone


Project Month Start Finish Achievement Achievement Achievement LOT Milestone ID SC Wasa Milestone Event Supporting Documents
(Estimate) (signed by EPC) (signed by BJP)

Aug-19 2 ON 29-2 ○ Start of FDF Erection for Unit 5 Notification Report with photo
29 01-08-19 31-08-19
Aug-19 3 ON 29-3 ○ Initial Delivery to Site - Field Erected Tanks (Fuel Oil) Material Receiving Report
Sep-19 4 ON 29-4 ○ (CHO) U6 Full Access to Elevated Slab (GL, T13-T23) Civil Handover Certificate
Aug-19 1 ON 30-1 ○ Delivery to Site of Generator Stator / Condenser Shell (Unit 6) Material Receiving Report
Sep-19 2 ON 30-2 ○ Start of Erection for SH, RH&Eco Horizontal Coils for Unit 6 Notification Report with photo
Sep-19 3 ON 30-3 ○ Completion of Initial Walkdown - Fire Protection and Detection System Copy of Initial Walkdown Completion Certificate
Sep-19 3 ON 30-4 ○ Complete Erection (First step) - Field Erected Tanks (Fuel Oil) Notification Letter with Photo
30 01-09-19 30-09-19
Sep-19 3 ON 30-5 ○ Completion of Initial Walkdown - Diesel Generators (Unit 5) Copy of Initial Walkdown Completion Certificate
Sep-19 3 ON 30-6 ○ Completion of Initial Walkdown - Fire Water Pumps Copy of Initial Walkdown Completion Certificate
Sep-19 3 ON 30-7 ○ Complete Erection (First step) - Seawater FGD (Unit 6) Notification Letter with Photo
Sep-19 4 ON 30-8 ○ (CHO) Stacker and Reclaimer Foundation_South Civil Handover Certificate
Sep-19 1 ON 31-1 ○ Delivery to Site of Steam Turbine (HP Casing) (Unit 6) Material Receiving Report
Oct-19 2 ON 31-2 ○ Start of PAF Erection for Unit 5 Notification Report with photo
Oct-19 2 ON 31-3 ○ Start of Eerection for Spiral Wall for Unit 6 Notification Report with photo
31 01-10-19 31-10-19 Oct-19 3 ON 31-4 ○ Completion of Pre-Operational Checkout - Diesel Generators (Unit 5) Copy of Preoperational Checkout Commencement Certificate
Oct-19 3 ON 31-5 ○ Completion of Pre-Operational Checkout - Fire Protection and Detection System Copy of Preoperational Checkout Commencement Certificate
Oct-19 3 ON 31-6 ○ Completion of Pre-Operational Checkout - Fire Water Pumps Copy of Preoperational Checkout Commencement Certificate
Oct-19 4 ON 31-7 ○ (CHO) 2nd Stage Work - FDN_PAF (Unit 5) Civil Handover Certificate

Nov-19 1 ON 32-1 ○ 500kV Backfeed Inspection Report approved by Owner, with Bus Bar Print Screen Indicating Bus Bar Voltage

Nov-19 2 ON 32-2 ○ Start of IDF Erection for Unit 6 Notification Report with photo
Nov-19 3 ON 32-3 ○ Completion of Initial Walkdown - Medium Voltage Switchgear (Unit 6) Copy of Initial Walkdown Completion Certificate
Nov-19 3 ON 32-4 ○ Completion of Initial Walkdown - Unit Substation Transformers (Unit 6) Copy of Initial Walkdown Completion Certificate
32 01-11-19 30-11-19
Nov-19 3 ON 32-5 ○ Completion of Initial Walkdown - Distribution Transformer (Unit 6) Copy of Initial Walkdown Completion Certificate
Nov-19 3 ON 32-6 ○ Complete Erection (First step) - Continous Emissions Monitoring System (CEMS) Equipment (Unit 5) Notification Letter with Photo
Nov-19 3 ON 32-7 ○ Complete Erection (First step) - Diesel Generators (Unit 6) Notification Letter with Photo
Nov-19 3 ON 32-8 ○ Completion of Initial Walkdown - Field Erected Tanks (Demin) Copy of Initial Walkdown Completion Certificate
Nov-19 4 ON 32-9 ○ (CHO) CEMS Room Civil Handover Certificate
Sep-19 1 ON 33-1 ○ Delivery to Site of DCS (Turbine Sequence & Modulating Control System "TSQ") (Unit 6) Material Receiving Report
Dec-19 2 ON 33-2 ○ Completion of Hydro-test for Unit 5 Test Report
Dec-19 3 ON 33-3 ○ Complete Erection (First step) - Fly Ash Conveying System (Unit 6) Notification Letter with Photo
Dec-19 3 ON 33-4 ○ Complete Erection (First step) -Crusher Notification Letter with Photo
33 01-12-19 31-12-19
Dec-19 3 ON 33-5 ○ Completion of Initial Walkdown - Stacker Reclaimer Copy of Initial Walkdown Completion Certificate
Dec-19 3 ON 33-6 ○ DeMin Water Avaliable Notification Letter with Photo
Dec-19 3 ON 33-7 ○ Completion of Pre-Operational Checkout - Field Erected Tanks (De Min) Copy of Preoperational Checkout Commencement Certificate
Dec-19 4 ON 33-8 ○ (CHO) 2nd Stage Work - FDN_Flame Scanner Cooling Fan for Chipping (Unit 5) Civil Handover Certificate
Jan-20 1 ON 34-1 ○ T/G Lube Oil Flushing for Steam Turbine & Generator (Unit 5) Record of Oil Flushing Completion
Jan-20 2 ON 34-2 ○ Start of FDF Erection for Unit 6 Notification Report with photo
Jan-20 3 ON 34-3 ○ Completion of Initial Walkdown - Conveyors Copy of Initial Walkdown Completion Certificate
34 01-01-20 31-01-20 Jan-20 3 ON 34-4 ○ Completion of Initial Walkdown - Ship Unloader Copy of Initial Walkdown Completion Certificate
Jan-20 3 ON 34-5 ○ Completion of Pre-Operational Checkout - Stacker Reclaimer Copy of Preoperational Checkout Commencement Certificate
Jan-20 3 ON 34-6 ○ Completion of Initial Walkdown - Auxiliary Boiler Copy of Initial Walkdown Completion Certificate
Jan-20 4 ON 34-7 ○ (CHO) 2nd Stage Work - FDN_Flame Scanner Cooling Fan (Unit 5) Civil Handover Certificate
Feb-20 3 ON 35-1 ○ Completion of Initial Walkdown - Travelling Water Screen (Unit 5) Copy of Initial Walkdown Completion Certificate
Feb-20 3 ON 35-2 ○ Completion of Initial Walkdown - Chlorination System Copy of Initial Walkdown Completion Certificate
Feb-20 3 ON 35-3 ○ Completion of Pre-Operational Checkout - Coal Handling Conveyors Copy of Preoperational Checkout Commencement Certificate
Feb-20 3 ON 35-4 ○ Completion of Pre-Operational Checkout - Ship Unloader Copy of Preoperational Checkout Commencement Certificate
35 01-02-20 29-02-20 Feb-20 3 ON 35-5 ○ Complete Erection (First step) - Circulating Water Pumps (Unit 6) Milestone Certificate of initial installation or project pictures of the work
Feb-20 3 ON 35-6 ○ Completion of Pre-Operational Checkout - Auxiliary Boiler Copy of Preoperational Checkout Commencement Certificate
Feb-20 3 ON 35-7 ○ Completion of Initial Walkdown - Circulating Water Pumps (Unit 5) Copy of Initial Walkdown Completion Certificate
Feb-20 3 ON 35-8 ○ Completion of Initial Walkdown - Diesel Generators (Unit 6) Copy of Initial Walkdown Completion Certificate
Feb-20 4 ON 35-9 ○ (CHO) 2nd Stage Work - FDN_FDF (Unit 6) Civil Handover Certificate
Mar-20 1 ON 36-1 ○ Delivery to Site of Generator Transformer Main Tank Assembly (Unit 6) Material Receiving Report
Mar-20 2 ON 36-2 ○ Start of PAF Erection for Unit 6 Notification Report with photo
Mar-20 3 ON 36-3 ○ Completion of Pre-Operational Checkout - Travelling Water Screen (Unit 5) Copy of Preoperational Checkout Commencement Certificate
Mar-20 3 ON 36-4 ○ Completion of Initial Walkdown - Seawater FGD (Unit 5) Copy of Initial Walkdown Completion Certificate
Mar-20 3 ON 36-5 ○ Completion of Pre-Operational Checkout - Chlorination System Copy of Preoperational Checkout Commencement Certificate
36 01-03-20 31-03-20
Mar-20 3 ON 36-6 ○ Completion of Initial Walkdown - Field Erected Tanks (Fuel Oil) Copy of Initial Walkdown Completion Certificate
Mar-20 3 ON 36-7 ○ Completion of Pre-Operational Checkout - Circulating Water Pumps (Unit 5) Copy of Preoperational Checkout Commencement Certificate
Mar-20 3 ON 36-8 ○ Completion of Initial Walkdown - Fuel Oil Pumps Copy of Initial Walkdown Completion Certificate
Mar-20 3 ON 36-9 ○ Completion of Pre-Operational Checkout - Diesel Generators (Unit 6) Copy of Preoperational Checkout Commencement Certificate

190304 Exhibit D - Milestone Payment Schedule (Contract Amend 1) for MAR (PM23)_PK 3/5
Exhibit D - Milestone Payment Schedule
Construction Contract / Contract Amendment 1

ACHIEVED 31-03-17

RE-SCHEDULE

(1) Advance Payment

(2) Pre-NTP Payment

Milestone Milestone Milestone


Project Month Start Finish Achievement Achievement Achievement LOT Milestone ID SC Wasa Milestone Event Supporting Documents
(Estimate) (signed by EPC) (signed by BJP)

Mar-20 4 ON 36-10 ○ (CHO) 2nd Stage Work - FDN_PAF (Unit 6) Civil Handover Certificate
Apr-20 1 ON 37-1 ○ Gland Steam Blow Out (Unit 5) Record of Gland Steam Blow out Completion
Apr-20 3 ON 37-2 ○ Completion of Pre-Operational Checkout - Field Erected Tanks (Fuel Oil) Copy of Preoperational Checkout Commencement Certificate
37 01-04-20 30-04-20 Apr-20 3 ON 37-3 ○ Complete Erection (First step) - Continous Emissions Monitoring System (CEMS) Equipment (Unit 6) Milestone Certificate of initial installation or project pictures of the work
Apr-20 3 ON 37-4 ○ Completion of Pre-Operational Checkout - Fuel Oil Pumps Copy of Preoperational Checkout Commencement Certificate
Apr-20 4 ON 37-5 ○ (CHO) 2nd Stage Work - FDN_PAF Outlet Duct Support (Unit 6) Civil Handover Certificate
May-20 1 ON 38-1 ○ Condenser Vacuum Up System Tests (Unit 5) Test Report
May-20 2 ON 38-2 ○ Completion of Hydro-test for Unit 6 Test Report
38 01-05-20 31-05-20
May-20 3 ON 38-3 ○ Completion of Pre-Operational Checkout - Sea Water FGD (Unit 5) Copy of Preoperational Checkout Commencement Certificate
May-20 4 ON 38-4 ○ (CHO) 2nd Stage Work - FDN_Flame Scanner Cooling Fan for Chipping (Unit 6) Civil Handover Certificate
Jun-20 1 ON 39-1 ○ Plant Hydrostatic Test (Unit 6) Test Report
Jun-20 2 ON 39-2 ○ First Oil Fire for Unit 5 Notification Report with photo
Jun-20 3 ON 39-3 ○ Completion of Initial Walkdown - Continous Emissions Monitoring System (CEMS) Equipment (Unit 5) Copy of Initial Walkdown Completion Certificate
39 01-06-20 30-06-20
Jun-20 3 ON 39-4 ○ Completion of Initial Walkdown - Fly Ash Conveying System (Unit 5) Copy of Initial Walkdown Completion Certificate
Jun-20 3 ON 39-5 ○ Ready to Receive Bedding Coal Notification Letter with Photo
Jun-20 4 ON 39-6 ○ (CHO) 2nd Stage Work - FDN_Flame Scanner Cooling Fan (Unit 6) Civil Handover Certificate
Jul-20 3 ON 40-1 ○ Completion of Initial Walkdown - Circulating Water Pumps (Unit 6) Copy of Initial Walkdown Completion Certificate
Jul-20 3 ON 40-2 ○ Completion of Pre-Operational Checkout - Continous Emissions Monitoring System (CEMS) Equipment (Unit 5) Copy of Preoperational Checkout Commencement Certificate
40 01-07-20 31-07-20
Jul-20 3 ON 40-3 ○ Completion of Pre-Operational Checkout - Fly Ash Conveying System (Unit 5) Copy of Preoperational Checkout Commencement Certificate
Jul-20 3 ON 40-4 ○ Ready to Receive Commissioning Coal Notification Letter with Photo
Aug-20 2 ON 41-1 ○ Synchronization (Unit 5) Inspection Report Approved by Owner, with Print Screen of Unit Synchronization
41 01-08-20 31-08-20 Aug-20 3 ON 41-2 ○ Completion of Initial Walkdown - Seawater FGD (Unit 6) Copy of Initial Walkdown Completion Certificate
Aug-20 3 ON 41-3 ○ Completion of Pre-Operational Checkout - Circulating Water Pumps (Unit 6) Copy of Preoperational Checkout Commencement Certificate
Sep-20 2 ON 42-1 ○ 100% Load Rejection Test (Unit 5) Test Report
42 01-09-20 30-09-20 Sep-20 2 ON 42-2 ○ First Coal Fire for Unit 5 Notification Report with photo
Sep-20 3 ON 42-3 ○ Ready for Coal to Silos Notification Letter with Photo
Oct-20 1 ON 43-1 ○ Fine Mesh Removal (Unit 5) Record of Fine Mesh Removal Completion
43 01-10-20 31-10-20
Oct-20 3 ON 43-2 ○ Full Load Operation FGD - (Unit 5) Notification Letter with Photo
Nov-20 2 ON 44-1 ○ HP Heater Bypass Test (Unit 5) Test Report
44 01-11-20 30-11-20 Nov-20 2 ON 44-2 ○ First Oil Fire for Unit 6 Notification Report with photo
Nov-20 3 ON 44-3 ○ Completion of Pre-Operational Checkout - Seawater FGD (Unit 6) Copy of Preoperational Checkout Commencement Certificate
Dec-20 2 ON 45-1 ○ Completion of Performance Test (Unit 5) Test Report
45 01-12-20 31-12-20 Dec-20 3 ON 45-2 ○ Completion of Initial Walkdown - Continous Emissions Monitoring System (CEMS) Equipment (Unit 6) Copy of Initial Walkdown Completion Certificate
Dec-20 3 ON 45-3 ○ Completion of Initial Walkdown - Fly Ash Conveying System (Unit 6) Copy of Initial Walkdown Completion Certificate
Jan-21 2 ON 46-1 ○ Unit 5 Reliability Run Test Report
46 01-01-21 31-01-21
Jan-21 3 ON 46-2 ○ Completion of Pre-Operational Checkout - Continous Emissions Monitoring System (CEMS) Equipment (Unit 6) Copy of Preoperational Checkout Commencement Certificate
Feb-21 2 ON 47-1 ○ 100% Load Rejection Test (Unit 6) Test Report
47 01-02-21 28-02-21
Feb-21 2 ON 47-2 ○ First Coal Fire for Unit 6 Notification Report with photo
Mar-21 2 ON 48-1 ○ Oprerational Acceptance of Unit 5 Operational Acceptance Certificate for Unit 5
48 01-03-21 31-03-21 Mar-21 1 ON 48-2 ○ Fine Mesh Removal (Unit 6) Notification Report with Photo
Mar-21 3 ON 48-3 ○ Full Load Operation FGD- Unit 6 Notification Letter with Photo
49 01-04-21 30-04-21 Apr-21 2 ON 49-1 ○ HP Heater Bypass Test (Unit 6) Test Report
50 01-05-21 31-05-21 May-21 2 ON 50-1 ○ Completion of Performance Test (Unit 6) Test Report
51 01-06-21 30-06-21 Jun-21 2 ON 51-1 ○ Unit 6 Reliability Run Test Report
52 01-07-21 31-07-21 Jul-21 (No Event)
53 01-08-21 31-08-21 Aug-21 (No Event)
54 01-09-21 29-09-21 Sep-21 2 ON 54-1 ○ Operational Acceptance of Unit 6 Operational Acceptance Certificate for Unit 6

(4) TJB 5&6 Ash Pond Contract Price

Fixed Sum (1) + (2) + (3) + (4)

*Note:
(1) "Mobilize to Site for Site Services / Mobilization of B&V Erection Subcontractor" means when that particular party’s site personnel first arrive at site as a "Permanent resident of the Local area" for execution of the work scope.

(2) "Complete Erection (First step)" is defined as placement of 1st set of equipment/material on the foundation or near the foundation or structure. It also includes work in the Temporary Facilities or other designated area in preparation of the work activity associated with the erection milestone, i.e. assembly or pre-assembly prior to erection at the permanent location.

(3) "Completion of Initial Walkdown" is the timing of the first Walkdown performed to verify the level of construction completion. The parties create an internal contractor erection completion punchlist. This list defines items to be completed prior to formal hand-over to commissioning teams in order to commence pre-commissioning/commissioning works. Provided that there are no
major items listed on Punch list (Only A Category Items in line with Project Quality Plan/TJB56-EPC-ON-C-00-PM-PLA-0016), Initial Walkdown Completion Certificate can be used as Supporting Document.
(4) "Completion of Preoperational Checkout" is the timing of the first Preoperational Checkout performed designating the start of the commissioning of the equipment/system after handover from construction.

190304 Exhibit D - Milestone Payment Schedule (Contract Amend 1) for MAR (PM23)_PK 4/5
Exhibit D - Milestone Payment Schedule
Construction Contract / Contract Amendment 1

ACHIEVED 31-03-17

RE-SCHEDULE

(1) Advance Payment

(2) Pre-NTP Payment

Milestone Milestone Milestone


Project Month Start Finish Achievement Achievement Achievement LOT Milestone ID SC Wasa Milestone Event Supporting Documents
(Estimate) (signed by EPC) (signed by BJP)

(5) "Site Inspection Report" shall be reviewed and signed by Owner, before it is submitted as Supporting Document.
(6) "Material Receiving Report" shall be reviewed and signed by Owner, before it is submitted as Supporting Document.
(7) "Notification Report with Photo" and "Notification Letter with Photo"shall be reviewed and signed by Owner, before it is submitted as Supporting Document.
(8) "Test Report" shall be submitted for Owner's review/reference or approal in accordance with the relevant Inspection Test Plan/ Inspection test Procedures and should be at "Approved" or "Approved with Comment" or "Accepted for Information/Reference" or "Accepted with Comment" status, before its is submitted as Supporting Document.
(9) "(CHO)": Civil Handover
(10) "Partial Access" is the timing when access for preparation work by Lot 2 is commenced.
(11) "Start LV Switchgear Erection (Water Treatment)" is defined as placement of 1st set of equipment/material of LV Switchgear (Water Treatment) on the foundation or near the foundation or structure. It also includes work in the Temporary Facilities or other designated area in preparation of the work activity associated with the erection milestone, i.e. assembly or pre-
assembly prior to erection at the permanent location.
(12) "Start Erection of SWFGD U/G Pipe" is defined as placement of 1st set of pipe in the trench or near the trench.
(13) "DeMin Water Avaliable" is defined as when the water treatment system is able to produce permanent demin water.
(14) "Ready to/for Receive" is defined as when particular system is ready to receive fuel (oil or coal) to support commissioning works.
(15) "Full Load Operation FGD - (Unit 5/ Unit 6)" is defined as when each Unit 5 and Unit 6 SWFGD achieves full load for the first time under ECR conditions.
(16) "Civil Handover Certificate" should have been accepted by Lot(s) who takes the civil handover.

190304 Exhibit D - Milestone Payment Schedule (Contract Amend 1) for MAR (PM23)_PK 5/5