JPNPL (12.

75"x 342 Km) DPR


DATE:- 26.12.17 30.12.99
SP #01 KM:00.00 to KM 80.00

CREW - 01 (0.0-45.00) TODAY CUMULATIVE PREVIOUS


Grading : 0 / 45000 / 45000
Stringing : 0 / 45000 / 45000
Mainline Welding no. : 0 / 3064 / 3064
Mainline Welding Mtr : 0 / 45000 / 45000
Tie-in Welding : 0 / 730 / 730
Joint Coating : 0 / 3735 / 3735
Trenching : 0 / 45000 / 45000
Lowering & Holiday Testing : 0 / 45000 / 45000
HDPE Duct Laying : 0 / 45000 / 45000
Backfilling : 0 / 45000 / 45000
OFC Blowing : 0 / 45000 / 45000
Boundary Marker : 0 / 500 / 500
warning marker : 0 / 66 / 66
kilometer marker : 0 / 46 / 46
Direction marker : 0 / 71 / 71
Restoration : 0 / 37550 / 37550

JPNPL (12.75"x 342 Km) DPR


DATE:- 26.12.17 30.12.99
CREW - 02 (45.0-70.00) TODAY CUMULATIVE PREVIOUS
Grading : 0 / 25000 / 25000
Stringing : 0 / 25000 / 25000
Mainline Welding no. : 0 / 1603 / 1603
Mainline Welding Mtr : 0 / 25000 / 25000
Tie-in Welding : 0 / 395 / 395
Joint Coating : 0 / 1983 / 1983
Trenching : 0 / 25000 / 25000
Lowering & Holiday Testing : 0 / 25000 / 25000
HDPE Duct Laying : 0 / 25000 / 25000
Backfilling : 0 / 25000 / 25000
OFC Blowing : 0 / 25000 / 25000
Boundary Marker : 0 / 140 / 140
warning marker : 0 / 9 / 9
kilometer marker : 0 / 8 / 8
Direction marker : 0 / 13 / 13
Restoration : 0 / 11245 / 11245

JPNPL (12.75"x 342 Km) DPR


DATE:- 26.12.17 30.12.99

SP #02 KM:80.00to KM 220.00


CREW - 01 (70.0-110.00) TODAY CUMULATIVE PREVIOUS
Grading : 0 / 40000 / 40000
Stringing : 0 / 40000 / 40000
Mainline Welding no. : 0 / 2775 / 2775
Mainline Welding Mtr : 0 / 40000 / 40000
Tie-in Welding : 0 / 499 / 499
Joint Coating : 0 / 3320 / 3320
Trenching : 0 / 40000 / 40000
Lowering & Holiday Testing : 0 / 40000 / 40000
HDPE Duct Laying : 0 / 40000 / 40000
Backfilling : 0 / 40000 / 40000
OFC Blowing : 0 / 40000 / 40000
Boundary Marker : 0 / 194 / 194
warning marker : 0 / 23 / 23
kilometer marker : 0 / 23 / 23
Direction marker : 0 / 44 / 44
Restoration : 0 / 37350 / 37350
JPNPL (12.75"x342 Km) DPR Dt.- 30.12.99

SP #02 KM:80.00to KM 220.00


CREW - 02 (110-162) (TODAY & Cumulative)
Survey : 0 / 53000 53000
Panchnama : 0 / 53000 53000
Grading : 0 / 53000 53000
Stringing : 0 / 53000 53000
Mainline Welding no. : 0 / 3839 3839
Mainline Welding Mtr : 0 / 53000 53000
Tie-in Welding : 3 / 631 628
Cold field bend No. : 0 / 0 0
RT Taken : 0 / 4469 4469
RT Reviewed : 0 / 4470 4470
RT Accepted : 0 / 3332 3332
DRS/GRS : 0 / 61 61
Repair : 0 / 1077 1077
Joint Coating : 6 / 4322 4316
Trenching : 50 / 52911 52861
Lowering & Holiday Testing : 50 / 52911 52861
HDPE Duct Laying : 0 / 52861 52861
Backfilling : 0 / 51512 51512
OFC Blowing 500 / 51500 51000
OFC Pit : 0 / 0 0
Boundary Marker : 0 / 195 195
warning marker : 0 / 15 15
kilometer marker : 0 / 28 28
Direction marker : 0 / 36 36
Restoration : 0 / 11000 11000

SP #02 KM:80.00to KM 220.00


CREW - 02 (162-215) (TODAY & Cumulative)
Survey : 0 / 52500 52500
Panchnama : 0 / 52500 52500
Grading : 0 / 52500 52500
Stringing : 0 / 52500 52500
Mainline Welding no. : 0 / 3701 3701
Mainline Welding Mtr : 0 / 52500 52500
Tie-in Welding : 0 / 1148 1148
Cold field bend No. : 0 / 0 0
RT Taken : 0 / 4375 4375
RT Reviewed : 0 / 4375 4375
RT Accepted : 0 / 2742 2742
DRS/GRS : 0 / 49 49
Repair : 0 / 1584 1584
Joint Coating : 0 / 4691 4691
Trenching : 0 / 52500 52500
Lowering & Holiday Testing : 0 / 52500 52500
HDPE Duct Laying : 0 / 38500 38500
Backfilling : 0 / 52450 52450
OFC Blowing 600 / 37750 37150
OFC Pit : 0 / 6 6
Boundary Marker : 0 / 302 302
warning marker : 0 / 45 45
kilometer marker : 0 / 36 36
Direction marker : 0 / 107 107
Restoration : 0
…. / 37000 37000
TOTAL CUMLATIVE KM:00.00 to KM 342.00
(CREW - 01 ; CREW - 02 ; CREW - 03)
DPR (TODAY & Cumulative)
Survey : 0 / 342000 ###
Panchnama : 0 / 342000 ###
Grading : 0 / 342000 ###
Line Pipe Received : #REF! / 2
6.3 5mm : #REF! / #REF!
7.92 mm : #REF! / #REF!
9.52 mm : #REF! / #REF!
11.12mm : 0 / #REF!
Stringing : 0 / 342000 ###
Mainline Welding no. : 0 / 23937 ###
Mainline Welding Mtr : 0 / 342000
Tie-in Welding : 3 / 5109 ###
Cold field bend No. : 0 / 193 ###
RT Taken : 0 / 22253 ###
RT Reviewed : 0 / 22242 ###
RT Accepted : 0 / 16297 ###
DRS/GRS : 0 / 552 ###
Repair : 0 / 5393 ###
Joint Coating : 6 / 28611 ###
Trenching : 50 / 341911 ###
Lowering & Holiday Testing : 50 / 341911 ###
HDPE Duct Laying : 0 / 327861 ###
Backfilling : 0 / 340462 ###
OFC Blowing : 1100 / 325750 ###
OFC Pit installed 0 / 59
Boundary Marker installed : 0 / 1882
warning marker installed : 0 / 250
kilometer marker installed : 0 / 202
Direction marker : 0 / 369
Restoration : 0 / 206805
Length Updated as Per Report's and Pipebook.
Nimera Sanganer Section
: 0 / 46374
(OFC Blowing)
ETBPNMTPL Project (Group-C IP-103, Trichy to IP-104, Madurai)

DAILY PROGRESS REPORT


Report Date: 4/13/2020
Report No: DPR/002
Weather Sunny
Working Hours:
Sl. No. Activity Description UOM Scope of Work Previous Today's Cumulative Remarks
1 Pre Construction Survey Mtr 113,500.000 5,506.000 - 5,506.000
2 ROU Handover Mtr 113,500.000 5,506.000 - 5,506.000 From KM 413.092 to KM 418.598

3 ROU Clearing & Grading Mtr 113,500.000 - - -


4 Line Pipe Received - - -
4.1 24"X-70X10.3 mm Mtr - - -
4.2 24"X-70X12.7 mm Mtr 113,500.000 - - -
4.3 24"X-70X15.8 mm Mtr 11.550 - 11.550
5 Stringing Mtr 113,500.000 - -
6 Installation of Cold Field Bends Nos. TBA - -
Nos. TBA - -
7 Mainline Welding
Mtr 113,500.000 - -
8 Tie-in Welding Nos. - -
Nos. 9,307
9 Total Welding
Mtr 113,500.000 - -
10 RT Taken Nos. 9,307 - -
a RT Reviewed Nos. 9,307 - -
b RT Accepted Nos. 9,307 - -
a Repair Nos. - - -
b RT/DRS/GRS Nos. - - -
a Repair Accepted Nos. - - -
b RT/DRS/GRS Accepted Nos. - - -
j Total Radiography Accepted Nos. - - -
k Repair % % - 0% #DIV/0!
l Joint Coating Nos. 9,307.000 - -
11 Trenching Mtr 113,500.000 - -
12 Lowering & Holiday Testing Mtr 113,500.000 - -
13 HDPE Duct Laying Mtr 113,500.000 - -
14 Backfilling Mtr 113,500.000 - -
15 OFC Blowing Mtr 113,500.000 - -
Cased /Shallow HDD Nos. - -
16 Casing Pipe Mtr - -
Carrier Pipe Mtr - -
Nos. TBA - -
17 Sub Merged Crossing
Mtr - -
18 Open Cut Crossing Nos. TBA - -
Nos. TBA - -
19 HDD Crossing
Mtr - -
Today's Highlights: WPS Conducted at EEL yard

Next day plan


1 WQT at EEL Yard.

2 Grading at KM 413
3 Pipe Transporation
4 Stringing at KM 413
ETBPNMTPL Project (Group-C IP-103, Trichy to IP-104,
Madurai)

DAILY RESOURCE REPORT


Report Date: 4/13/2020

Report No: DRR/002


EQUIPMENT
Sr.No. Description UoM 24" Line MLV Remark

1 Air Compressor 300 CFM Nos 11.00

2 Blasting Hopper Nos 1.00

3 Dozer DZ Nos 1.00

4 JCB Nos 1.00

5 DG 62.5 KVA Nos 3.00

6 DG 32 KVA Nos -

7 Excavator Nos 2.00

8 Holiday Machine Nos -

9 Pay Welder Nos -

10 Pipe Bending Machine 24" Nos -

11 Pipe layer Nos -

12 Hydra K12- Pick & Carry Crane Nos 2.00

13 Internal Clamp Nos 1.00

14 External Clamp- 24" Nos 1.00

15 Pump - Diesel Dewatering Nos 1.00

16 Pump- Water Filling Pump Nos -

17 Pump- Pressurising Pump Nos -

18 Total Station Nos 2.00

19 Trailer - Flat Bed Nos -

20 Trailer - Low bed Nos 2.00

21 Trailer - Semi Low bed Nos -

22 Tractor With Trolly Nos 3.00

23 Welding machine - 400 Amps Nos 20.00

24 Grinding Machine AG-07 Nos 10.00

25 Grinding Machine AG-05 Nos 10.00

26 NDT Internal Crawler Nos -

27 NDT Externall Crawler Nos -

28 HDD Boring machine 24" Nos -

29 Bevel Cutting Machine Nos -


ETBPNMTPL Project (Group-C IP-103, Trichy to
IP-104, Madurai)
DAILY RESOURCE REPORT
Report Date: 4/13/2020
Report No: DRR/002
MANPOWER
Sr.No. SUPERVISION UoM Total Remark

1 Project Manager Nos 1


2 Construction Manager Nos 1
3 Planning Manager/Engineer Nos 1
4 Q/A & Q/C Manager/Engineer Nos 1
5 QC Inspector Nos -
6 Safety Manager/Engineer Nos 1
7 Site Incharge/Superitendent Nos 2
8 HR/Admin Nos 1
9 Civil Engineer Nos 1
10 HDD Engineer Nos -
11 Cathodic Protection Engineer Nos 1
12 Site Supervisor Nos 2
13 Store Assistant Nos 1
14 Accountant Nos 1
15 Liosining Officer Nos 1
WORKMEN
16 Welder Nos 13
17 Grinders Nos 12
18 Fitters Nos 2
19 Gas Cutter Nos 2
20 Supervisor Nos 2
21 Foreman Nos 2
22 Riggers Nos 10
23 Mason Nos -
24 Electrician/Machanic Nos -
25 Operator Nos 7
26 Surveyor Assistant Nos 1
27 Helpers Nos 14
28 Security guards Nos -
29 Painter /Blaster/Insulator Nos -
30 Store Assistants/Office Assistants Nos -
31 Cook, House keeping & Others Nos 2
32 Driver Nos 9
33 HDD Crew Nos -
Overall Working Manpower Err:522
JAIPUR PANIPAT NAPHTHA PIPELINE PROJECT
DAILY PROGRESS REPORT
Specific Notic date 5/4/2017 Report Date:
Date of Completion : 7/28/2018 Report No.
Days Elapsed #VALUE! Weather
Days Balance : #VALUE! Working Hours:
SPREAD - I
SPREAD - II SPREAD - III
Sl. Scope of CH 0 +000 - CH 80+000
CH 80+000 - CH 220+000 CH 220+000 - CH 342+000
TOTAL CUMMU
Activity Description UOM
No. Work
Previous Today's Cumulative Previous Today's Cumulative Previous Today's Cumulative Previous

1 Pre Construction Survey Mtr 342000 46550 250 46800 33400 0 33400 62996 175 63171 142946
2 Panchnama/Notification Mtr 342000 46550 250 46800 33400 0 33400 44316 175 44491 124266
3 ROU Handover Mtr 342000 46550 250 46800 33400 0 33400 44316 175 44491 124266
4 ROU Clearing & Grading Mtr 342000 46400 200 46600 33350 0 33350 44366 175 44541 124116
5 Line Pipe Received Mtr 342000 50899.94 1202 52101.94 26444 300.5 26744.5 27129.14 180.3 27309.44 104473.08
5.1 12.75" ,X-46 X 6.3 5mm Mtr 297000 31179.16 841.4 32020.56 25434.32 300.5 25734.82 26119.46 180.3 26299.76 82732.94
5.2 12.75" ,X-46 X 7.92 mm Mtr 25000 15325.5 360.6 15686.1 1009.68 0 1009.68 1009.68 0 1009.68 17344.86
5.3 12.75" ,X-46 X 9.52 mm Mtr 4000 432.82 0 432.82 0 0 0 0 0 0 432.82
5.4 12.75" ,X-46 X 11.12mm Mtr 16000 3962.46 0 3962.46 0 0 0 0 0 0 3962.46
6 Stringing Mtr 342000 41224.92 613.02 41837.94 26090.03 230 26320.03 36120.11 552 36672.11 103435.06

7 Installation of Cold Field Bends Nos. 377 21 0 21 0 0 0 24 1 25 45

Nos. 19994 2977 42 3019 1901 35 1936 2389 0 2389 7267


8 Mainline Welding
Mtr 240727.76 35170.52 504.84 35675.36 22152.86 0 22152.86 21744.18 0 21744.18 79067.56
Free Tie 7096 183 5 188 138 4 142 201 5 206 522
Free Tie Nos.
9 /Tie-in Tie-In 1296 6 0 6 38 0 38 38 0 38 82
Welding
Length Mtr 101039.68 631.2 631.2 0 0 0 0 0 631.2
Nos. 28386 3099 47 3146 2280 0 2280 2244 5 2249 7623
10 Total Welding
Mtr 341767.44 36116.52 564.94 36681.46 25478.46 0 25478.46 25045.74 60.1 25105.84 86640.72
12 RT Taken Nos. 28386 806 0 806 598 0 598 1930 50 1980 3334
a RT Reviewed Nos. 28386 797 0 797 598 0 598 1884 43 1927 3279
b RT Accepted Nos. 28386 687 0 687 527 0 527 1234 23 1257 2448
a Repair Nos. 85 0 85 40 0 40 560 20 580 685
b RT/DRS/GRS Nos. 25 0 25 31 0 31 83 0 83 139
a Repair Accepted Nos. 68 0 68 37 0 37 37 1 38 142
b RT/DRS/GRS Accepted Nos. 25 0 25 21 0 21 21 0 21 67
j Total Radiography Accepted Nos. 780 0 780 494 0 494 513 24 537 1787
k Repair % % 11% #DIV/0! 11% 7% #DIV/0! #DIV/0! 10% 47% 30% 0.2798237403
l Joint Coating Nos. 28386 2740 19 2759 1848 28 1876 2482 7 2489 7070
13 Trenching Mtr 342000 21004 1039 22043 20532 24 20556 27137 624 27761 68673
14 Lowering & Holiday Testing Mtr 342000 20961.93 1019 21980.93 20515.19 20 20535.19 27085.32 580 27665.32 68562.44
15 HDPE Duct Laying Mtr 390000 20961.93 1019 21980.93 20515.19 20 20535.19 27085.32 580 27665.32 68562.44
16 Backfilling Mtr 342000 20847.3 489 21336.3 20468 15 20483 26627.2 525 27152.2 67942.5
17 OFC Blowing Mtr 390000 0 0 0 0 0 0 0 0 0 0
Cased Crossings Nos. 19 0 0 0 0 0 0 0 0 0 0
17 Casing Pipe Mtr 882 0 0 0 0 0 0 0 0 0 0
Carrier Pipe Mtr 996 0 0 0 0 0 0 0 0 0 0
18 Sub Merged Crossing Nos. 43 0 0 0 0 0 0 0 0 0 0
19 Open Cut Crossing Nos. 514 0 0 0 0 0 0 0 0 0 0
Nos. 48 4 0 4 0 0 0 6 0 6 10
20 HDD Crossing
Mtr 7430 870 0 870 0 0 0 1100 0 1100 1970
21 Cleaning & Gauging Mtr 342000 0 0 0 0 0 0 0 0 0 0
22 Hydrotesting Mtr 360000 0 0 0 0 0 0 0 0 0 0

Today's Highlights:

Remarks
Report Date: 13.10.2017
Report No. 135
Weather SUNNY
Working Hours: 10 hrs
TOTAL CUMMULATIVE
Today's Cumulative

425 143371
425 124691
425 124691
375 124491
1682.8 106155.88
1322.2 84055.14
360.6 17705.46
0 432.82
0 3962.46
1395.02 104830.08

1 46

77 7344
504.84 79572.4
14 536
0 82
0 631.2
52 7675
625.04 87265.76
50 3384
43 3322
23 2471
20 705
0 139
1 143
0 67
24 1811
47% 21%
54 7124
1687 70360
1619 70181.44
1619 70181.44
1029 68971.5
0 0
0 0
0 0
0 0
0 0
0 0
0 10
0 1970
0 0
0 0
JAIPUR PANIPAT NAPHTHA PIPELINE PROJECT

DAILY PROGRESS REPORT (EQUIPMENT DEPLOYMENT)


DAILY PROGRESS REPORT (EQUIPMENT DEPLOYMENT)
CLIENT : INDIAN OIL CORPORATION LIMITED REPORT NO : #REF!
CONTRACTOR : CORRTECH INTERNATIONAL PVT. LTD REPORT DATE : 30.12.99
COMPLETION DT. :28.7.2018 WEATHER : #REF!
DATE OF SPECIFIC NOTIC :4.5.2017

Minimum No. of Equipment to be deployed Available at each Spread


Total Total
Sl. Nos DESCRIPTION Require Availabl Remarks
Spread - II Spread - III Spread - I Spread - II Spread - III
Spread - I (0 - 80)
(80-220) (220-342)
d (0 - 80) (80-220) (220-342)
e

1 Excavator (crawler mounted) / Backhoe 7 7 7 21 7 4 7 18

2 Pipe layers (Side Booms) - 572G or higher capacity 9 9 9 27 0 0 7 7

3 Dozer: CAT D7 / D8 or equivalent /JCB 2 2 2 6 3 4 4 11

4 Crane (20 T)/ HYDRA 3 3 3 9 6 5 7 18

5 Grader 1 1 1 3 0 1 1

6 Welding machine – 300 Amp 26 26 26 78 16 12 16 44

7 Pay welder 1 1 1 3 4 3 8 15

8 Bending machine 1 1 1 3 1 2 3

9 Boring machine 1 1 1 3 1 1

10 Internal X-Ray Crawler Machine 1 1 1 3 1 1 2

11 External X-Ray Machine 1 1 1 3 1 1 2

12 Internal line-up Clamp (Pneumatic) 1 1 1 3 3 2 5 10

13 External line-up clamp 3 3 3 9 4 4 5 13

14 Compressor (600 cfm) 1 1 1 3 0 0

15 Joint coating crew with compressor (300 cfm) and hopper assembly 2 2 2 6 2 1 2 5

16 Filling pump (250 – 300 m3 / hr) 1 1 1 3 1 1

17 High pressure pump (200 bar) 1 1 1 3 1 1

18 Chemical dosing pump 1 1 1 3 0

Complete Hydrotest kit with all instruments (Dead Weight Tester,


19
Pressure & Temperature recorder, thermocouple etc.) & Test cabin
1 1 1 3 1 1

20 Crane truck 1 1 1 3 0

21 Farm tractor 5 5 5 15 8 5 10 23

22 Low bed trailer 2 2 2 6 0

23 Flatbed trailer 1 1 1 3 4 1 8 13

24 Automatic Cutting & Beveling machine 3 3 3 9 0

25 Holiday Detector (of suitable range) 3 3 3 9 2 2 2 6

26 Voltmeter 2 2 2 6 2 2 2 6

27 Jeep meter 1 1 1 3 2 2 2 6

HDD Rig (of adequate pull capacity & torque requirement as per
28
design)
1 1 1 3 2 4 6
29 Crawler mounted drill 1 1 1 3 0

30 Rock Hammer / Jack Hammer 4 4 4 12 0


JAIPUR PANIPAT NAPHTHA PIPELINE PROJECT

DAILY PROGRESS REPORT (Next Day Plan with Contact Numbers)


CLIENT : INDIAN OIL CORPORATION LIMI REPORT NO : #REF!
CONTRACTOR : CORRTECH INTERNATIONAL PVTREPORT DATE : 30.12.99

COMPLETION DT. :28.7.2018 WEATHER : #REF!

DATE OF SPECIFIC NOTIC :4.5.2017

Site Office Key Person


Sr. No Description Location Name Contact No. Remarks
1 JhajjarCh. 215 towards panipat Pritam Dhar 7082010152
2 JPNPL SPREAD 2 Kotputli ch. 98 towards rewari Subodh sharma 9079245940
3 JPNPL Spread 1 Amer ch. 0.00 towards ch 45 Pritam singh 7082010163
4
5
6
Site Activities Responsibility Details
Sr. No Activities Location Responsible Person Contact No. Remarks
1 Survey CH:240 onwards Parmar 7082010156

2 ROW Gradding CH:230 onwards Prabhakar Tiwari 7082010157

3 Stringing CH: 223 Vinod Choubey 7082010166

4 PQT/WQT Jhajjar Vikram Singh 7082010165

5 Mainline Welding CH: 221 Sandeep Pandey 7082010158

6 PQT of Radiography CH: 217 Vikram Singh 7082010165

7 Mainline Welding ch.102 Subodh sharma 9079245940

8 Stringing ch.109 Subodh sharma 9079245940


Remarks: