Professional Documents
Culture Documents
CD 180 PDF
CD 180 PDF
10-Day Scheduled
Owner Delay Pay Increase
FIGURE 9.3
shifted into the period of the increased labor rate. The Contractor should calcu-
late $280 ($2/hour × 140 hours) for the escalated labor cost of the carpenters.
In this example, the actual distribution of carpenter labor was caused solely by
the Owner’s delay. In a different situation, if the Owner can demonstrate that
this was not the case, then the delay damages would not include the escalated
labor calculation.
Of course, many projects do not have a resource-loaded CPM schedule
to allow a reasonably precise comparison between the planned and the actual
distribution of labor. Without the CPM schedule, the analyst can estimate the
planned labor distribution from the Project bar chart. The analyst can com-
pare the labor hours actually expended on the job (taken from the Project daily
reports) to the planned labor hour distribution. The following example illustrates
this procedure.
EXAMPLE 93
A Contractor plans to perform the work in accordance with the bar chart shown
in Figure 9.4. No labor hours are shown in the bar chart. Due to an Owner-
caused delay, the Contractor’s work is performed later than originally planned.
As a result, the Contractor experiences escalated labor cost on the Project, after
a rate increase (from $35 per hour to $36 per hour) went into effect on day 200
of the Project.
Figure 9.4 is the Contractor’s bar chart for the work as originally planned.
Figure 9.5 shows the actual bar chart for the Project, reflecting the delays. It
also shows the actual carpenter labor hours worked on each activity. These labor
hours were taken from the contemporaneously recorded Project daily reports.