Professional Documents
Culture Documents
Seminar Slides (85p) PDF
Seminar Slides (85p) PDF
Seminar Slides (85p) PDF
FIDIC
Cornerstone Seminar
1
TANER DEDEZADE
CASABLANCA
1-3 FEBRUARY 2017
Workshops
2
1 2 3 4 5 6
Man Utd Contractor Engineer Employer Contractor Engineer Employer
FIDIC
4
FIDIC Objectives
5
continued
6
December 1945
January 1950 (second ed.)
March 1951 (third ed.)
January 1955 (fourth ed. Later amended in 1969)
1973 (5th edition) – controversial prompted new
revision of the FIDIC book
1991 (6th edition)
Orange Book
12
The
The
Conditions of
Conditions of
contract for
contract for
construction plant and
(red book) design-build
(Yellow book)
The
The short
Conditions of
form of
contract for
contract
EPC turnkey
(green)
(silver book)
Transfer of risk
14
Employer Risk
Contractor Risk
RED BOOK
15
Type of contract
16
Traditional model
17
Yellow Book
19
Employer
Design-
Employer’s
Build
advisors
Contractor
Silver Book
24
Green Book
25
Subcontract
29
Book sales
31
Risk
32
33
Coffee - 10.30-10.45
35
Sub-Clause 2.4
39
Sub-Clause 16.1
40
Sub-Clause 16.2
41
Engineer’s duties
Managing Time
Clause 8
designer
contractor
Design
Certifying Payment
Making determinations
Under Sub-Clause 3.5
3 Measurement and
Programming
Legal skills
evaluation Skills
4 Design
Engineer
5 Certifying Payment
6 Making 3.5 determinations
Financial and
accounting Legal skills
7 Inspection and testing skills
8 Issuing TOC
Design Skills
Role of Engineer
50
3 main roles:
To act on behalf of the Employer as his agent
Importance of Engineer
51
Sub-Clause 3.1
52
Sub-Clause 3.5
53
Sub-Clause 3.4
55
White book
56
Agreement (i)
Particular Conditions (a-h)
A) References from clauses in GCC (like App.to T)
B) Additional Clauses
Appendices
1) Scope of Services; 2) Personnel Equipment,
Facilities and Services of Others to be provided by
Client; 3) Remuneration and Payment; 4) Time
Schedule for Services
GCC (1-12)
Letter of offer by Consultant/Letter of
acceptance by Client
4.4 delays
61
Insurance
63
Scope of Services
64
Dispute Resolution
65
3 tiers
Negotiation
Mediation
Arbitration
RISK
RESPONSIBILITY
LIABILITY
INSURANCE
OVERVIEW
69
IDENTIFY RISKS
ALLOCATE RISKS
MANAGE AND MITIGATE RISKS IF POSSIBLE
AS THE RISK HAS BEEN ALLOCATED THE PARTY
RESPONSIBLE FOR THAT RISK SHOULD BE APPARENT
CONTRACTOR TO PRICE FOR THE RISKS
WHEN/IF RISK EVENTUATES LIABILITY FOR THAT
RISK WILL NEED TO BE ESTABLISHED BY REFERENCE
TO THE RESPONSIBLE PARTY
INDEMNITIES AND INSURANCE TO BE ASSESSED
What is risk?
70
R=PxC
R=risk
P= probability or frequency of occurrence of a
defined event
C= consequences of the occurrence of the hazard
E to IDENTIFY RISKS
71
The 4 principles
72
Which party
1. can best foresee the risk?
2. can best control the risk?
3. can best bear the risk?
4. most benefits/suffers if the risk eventuates?
E to ALLOCATE RISKS
73
Un-allocated risks
74
Manage risks
75
Insurance
78
FIDIC
Limitation of Liability
80
Sub-Clause 17.6
"Neither Party shall be liable to the other Party for loss of use
of any Works, loss of profit, loss of any contract or for any
indirect or consequential loss or damage which may be
suffered by the other Party in connection with the Contract
(...)“
Remoteness
81
(ii) Loss that does not arise naturally but that "may
reasonably be supposed to have been in the
contemplation of both parties, at the time they made
the contract, as the probable result of the breach". This
is the second limb of the test and is concerned with
knowledge of special circumstances outside the usual
course of things and what loss could have reasonably
been contemplated by the party in breach with
knowledge of the special circumstances. Loss falling
under the second limb is referred to by the courts as
"indirect" or "consequential" loss.
Recoverable loss?
86
Recoverable loss?
87
Recoverable loss?
88
Sub-Clause 20.1
1st paragraph
90
Sub-Clause 20.1
2nd paragraph
91
20.1
92
Cases
Sisters of Mercy case in Australia
Steria v Sigma case in England
Bremer case in England
Education 4 Ayrshire case in Scotland
WW Gear case in England
Gibraltar Tunnel case in England
Sub-Clause 2.5
93
Workshop 2 –
95
End of Day 1
96
DAY 1 is over
97
https://uk.linkedin.com/in/dedezade
Time 1/4
99
Time 2/4
100
Time 3/4
101
Time 4/4
102
Introduction
103
FIDIC regime
105
BB v Chestermount contd.
107
8.2
108
Question
110
Prolongation costs
114
POW
118
8.3 programme
What is the overall duration of the project?
How detailed should the plan be?
How often should the plan be updated?
Who needs to receive information about progress?
What kind of reports should be prepared?
What graphics will be required to help communicate best?
How much time can be afforded on P.M.?
As-built POW
120
1. As planned vs as-built
2. Impacted as-planned
3. Collapsed as-built
4. Windows analysis
5. Time impact analysis
Prospective/retrospective
122
1) As planned vs as-built
123
2) Impacted as-planned
124
3) Collapsed as-built
125
4) Windows analysis
126
2 types
Time slice windows analysis
Coffee - 10.30-10.45
129
Concurrency
Acceleration
Time at large
Concurrency
131
Concurrency – time
132
England
C is entitled to EOT where delay caused by matters falling
within the clause notwithstanding the matter relied upon by C
is not the dominant cause of delay and is of at least equal
“causative potency” with all the other matters causing delay.
De beers C “is entitled to have the time within which the
contract allows or which the employer’s conduct has made
reasonably necessary.”Notwithstanding that the would have
been unable to complete absent any breaches of contract on
the part of the employer
Scotland
Apportionment where there are concurrent
causes of delay, none of which can be
described as dominant
Concurency - money
133
Summary on concurrency
134
Acceleration
135
Constructive acceleration
136
137
Prevention and
time at large
PREVENTION
138
EOT clause
140
142
Is that right?
144
The questions
145
DEVICES
146
Australia
147
England
148
Workshop 3 –
11.30-13.00
149
Step 2 Sub-Clause 14.6 Eng to issue IPC within 28 days (unless < min.
amount and notice is given). No sanction for not
issuing within 28 days.
If no notice given within 56 days – termination
right under Sub-Clause 16.2 (b)
Step 3 Sub-Clause 14.7 E shall pay amount in IPC within 56 days. No
sanction for non-payment within 56 days.
If no payment is made within 42 days of the
expiry of the 56 days set out in Sub-Clause 14.7
– termination right under Sub-Clause 16.2(c)
Variations
152
Variations
153
RB Definition of Variation
155
Sub-Clause 1.1.6.9
RB Sub-Clause 13.1
156
Exception
157
Cardinal change
160
Question of Fact
161
Valuation of Variations in RB
162
Sub-Clause 12.3
Rule 1 – Contract rates and prices
Defects
164
Defects Liability
165
Termination right
166
Concept
General
Arrangement
Detail
Working
Shop
Material Selection
Basic dynamic of DB
168
170
Design responsibility
171
5.1
172
Sub-Clause 1.9
174
Workshop 4 –
175
End of Day 2
176
DAY 2 is over
Lecture 12
Why did FIDIC create the Silver Book?
177
Typical use
178
BOT project
181
Transfer of risk
184
2.4
186
Turnkey contracting
189
Turnkey contracting
190
Risk
In the SB, there is a strict standard for design – fitness for
purpose - and a clear responsibility on the C for that design
including ensuring accuracy of the ERs
Interference
Yet the project company has the same power to instruct, vary
and condemn works as in the other FIDIC books.
Sub-Clause 5.2
203
Interference
206
Interference contd.
207
Definition of Contract
208
Contract Agreement √ √
Letter of Acceptance √
Tender √
Employer’s Requirements √ √
Schedules √
Contractor’s Proposal √
or Letter of Acceptance √
No Letter of Acceptance in SB
No Contractor’s Proposal. In YB. The Proposal
includes the Contractor’s preliminary design (a term
which is not defined). In SB the tenderer includes the
details of his proposals in the Tender. The definition
of Tender (1.1.1.4) excludes Conditions and ER’s so
that each of the documents can be allocated
appropriate priority in SB 1.5
No Appendix to Tender in SB. PC will contain info
This is to provide greater flexibility.
* Employer’s Representative *
210
Employer’s Rep
211
Approval of sub-contractors
212
Testing
215
Testing
216
Testing
217
Testing
218
Payment
219
time
220
221
Delay damages
222
3 ways:
E may instruct the variation under sub-clause 13.1, without
prior agreement as to feasibility or price. C is given a right of
objection which can be overridden by the E or Eng. There is no
provision as to the result if the performance specification is not
met due to a variation being instructed despite the objections
of the contractor. It is difficult to see that the contractor could
be liable in such circumstances for the failure.
C may initiate his own proposals under sub-clause 13.2
(effectively value engineering) which are intended to benefit
both parties, or
E may request a proposal under sub-clause 13.3,
thus seeking agreement as to the time and cost
impact, prior to seeking the variation.
Valuation of variations
226
Coffee - 10.30-10.45
227
Global Claims
229
2.5
3 ROUTES TO
ARBITRATION 20.8 20.7 20.6
CLAIM
DISPUTE
Adhoc/standing
Adhoc formed when dispute arises
Standing formed at outset of project
Terms of appointment
Skills: communication skills, availability, technical knowledge,
legal knowledge, dispute resolution experience, independence
and impartiality
Renumeration
Replacement
Termination of DAB appointment
Independence
233
Impartiality
234
20.4
235
20.5
236
20.6
237
Arbitration.
Default position under the 1999 forms is ICC
arbitration.
The two particular features of ICC arbitration which
distinguish themselves from other forms of
arbitration are
scrutiny of the award; and
Terms of Reference.
20.7
238
20.8
239
Jurisdictional objections
240
Reaching a Decision
241
Form of decision
244
Form of decision
245
Form of decision
246
Form of decision
247
Form of decision
248
Dissent
249
Jurisdictional objections
250
ICC Arbitration
251
20.6 20.6 Unless settled amicably, any dispute in respect of which the DAB’s decision
(if any) has not become final and binding shall be finally settled by inter-
national arbitration. Unless otherwise agreed by both Parties:
(a) the dispute shall be finally settled under the Rules of Arbitration of the
International Chamber of Commerce,
(b) the dispute shall be settled by three arbitrators appointed in
accordance with these Rules, and
(c) the arbitration shall be conducted in the language for communications
defined in Sub-Clause 1.4 [Law and Language].
The arbitrator(s) shall have full power to open up, review and revise any
certificate, determination, instruction, opinion or valuation of the
Engineer, and any decision of the DAB, relevant to the dispute. Nothing
shall disqualify the Engineer from being called as a witness and giving
evidence before the arbitrator(s) on any matter whatsoever relevant to the
dispute.
Neither Party shall be limited in the proceedings before the arbitrator(s) to
the evidence or arguments previously put before the DAB to obtain its
decision or to the reasons for dissatisfaction given in its notice of dis-
satisfaction. Any decision of the DAB shall be admissible in evidence in the
arbitration.
Arbitration may be commenced prior to or after completion of the Works.
The obligations of the Parties, the Engineer and the DAB shall not be
altered by reason of any arbitration being conducted during the progress of
the Works.
TOR
scrutiny
ICC Rules
253
Workshop 6 –
16.00-17.30
254
End of Day 3
255
DAY 3 is over