Beginning The Project

Milestone Date: Sun 01/01/17


ID: 1

Preliminary G&G Study to Detect The Seismic Area Permits Seismic Acquisition Seismic Processing Seismic Inter
Start: Sun 01/01/17ID: 2 Start: Sun 26/03/17ID: 10 Start: Fri 28/07/17 ID: 12 Start: Sun 28/01/18ID: 20 Start: Sun 07
Finish: Thu 23/03/17
Dur: 60 days Finish: Thu 27/07/17
Dur: 90 days Finish: Sat 27/01/18Dur: 184 days Finish: Thu 04/10/18
Dur: 180 days Finish: Thu 2
Res: Res: Res: Res: Res:

Page 1
Tender for Seismic Processing Invitation Receive Offe
Start: Sun 30/07/17
ID: 13 Start: Sun 30/07/17ID: 14 Start: Tue 08
Finish: Sun 08/10/17
Dur: 51 days Finish: Mon 07/08/17
Dur: 7 days Finish: Mon 2
Comp: 0% Res: Res:

End of The Second Tender

Milestone Date: Sun 08/10/17


ID: 19

Completing The Permits

Milestone Date: Thu 27/07/17


ID: 11

Tender for 3D Seismic Acquisition Invitation Receive Offer Technical Eva


Start: Sun 26/03/17
ID: 3 Start: Sun 26/03/17ID: 4 Start: Tue 04/04/17ID: 5 Start: Tue 25
Finish: Sun 04/06/17
Dur: 51 days Finish: Mon 03/04/17
Dur: 7 days Finish: Mon 24/04/17
Dur: 15 days Finish: Mon 1
Comp: 0% Res: Res: Res:

End of The First Tender

Milestone Date: Sun 04/06/17


ID: 9
Page 2
ID: 9

Page 3
eismic Interpretation Define Prospects Rank Prospects Detect The First Location to be Drilled Approval
tart: Sun 07/10/18ID: 21 Start: Sun 30/12/18ID: 23 Start: Thu 17/01/19ID: 24 Start: Wed 06/02/19
ID: 26 Start: Wed 06/02/19ID: 27
inish: Thu 27/12/18
Dur: 60 days Finish: Wed 16/01/19
Dur: 14 days Finish: Tue 05/02/19Dur: 14 days Finish: Thu 21/05/20
Dur: 337 days Finish: Thu 14/02/19
Dur: 7 days
es: Res: Res: Comp: 0% Res:

Drilling Well Base of Design


Start: Sun 24/05/20ID: 34
Finish: Thu 02/07/20Dur: 30 days
Res:

Page 4
Completing of Rank Prospects

Milestone Date: Tue 05/02/19


ID: 25

Completing Seismic
Interpretation
Milestone Date: Thu 27/12/18
ID: 22

eceive Offer Technical Evaluation Commercial Evaluation Award


tart: Tue 08/08/17ID: 15 Start: Tue 29/08/17ID: 16 Start: Tue 19/09/17ID: 17 Start: Thu 28/09/17ID: 18
inish: Mon 28/08/17
Dur: 15 days Finish: Mon 18/09/17
Dur: 15 days Finish: Wed 27/09/17
Dur: 7 days Finish: Sun 08/10/17
Dur: 7 days
es: Res: Res: Res:

echnical Evaluation Commercial Evaluation Award


tart: Tue 25/04/17ID: 6 Start: Tue 16/05/17ID: 7 Start: Thu 25/05/17ID: 8
inish: Mon 15/05/17
Dur: 15 days Finish: Wed 24/05/17
Dur: 7 days Finish: Sun 04/06/17
Dur: 7 days
es: Res: Res:

Page 5
Page 6
Permits Army Permits
Start: Sun 17/02/19
ID: 28 Start: Sun 17/02/19ID: 29
ys Finish: Thu 20/06/19
Dur: 90 days Finish: Thu 20/06/19
Dur: 90 days
Comp: 0% Res:

Environmental Permits
Start: Sun 17/02/19ID: 30
Finish: Thu 20/06/19
Dur: 90 days
Res:

Tendering For Rigs and Service Company Tender For Materials Purchasing The Materials
Start: Sun 23/06/19ID: 31 Start: Sun 04/08/19ID: 32 Start: Sun 15/09/19ID: 33
Finish: Thu 01/08/19
Dur: 30 days Finish: Thu 12/09/19
Dur: 30 days Finish: Thu 21/05/20
Dur: 180 days
Res: Res: Res:

Cost Estimate Access Road and Well Site Preparation Rig Move Drilling Well
Start: Sun 05/07/20ID: 35 Start: Thu 23/07/20ID: 38 Start: Wed 23/09/20 ID: 39 Start: Wed 07/10/20
ID: 41
ays Finish: Wed 22/07/20
Dur: 14 days Finish: Tue 22/09/20Dur: 62 days Finish: Tue 06/10/20Dur: 14 days Finish: Sat 28/11/20
Dur: 53 days
Res: Res: Res: Comp: 0%

Completing The Rig Move and


Ready to Start of Drilling
Milestone Date: Tue 06/10/20
ID: 40

Completing The Cost Estimate


Page 7
Milestone Date: Wed 22/07/20
ID: 36

AFE
Start: Sun 05/07/20ID: 37
Finish: Wed 22/07/20
Dur: 14 days
Res:

Page 8
Page 9
Rigging up Rig Acceptance Hummer Driving The Conductor Drill The Second Section Run Surface Casing & Cement
Start: Wed 07/10/20 ID: 42 Start: Sat 10/10/20ID: 43 Start: Sat 10/10/20ID: 44 Start: Tue 13/10/20ID: 45 Start: Sun 25/10/20ID: 46
Finish: Fri 09/10/20Dur: 3 days Finish: Sat 10/10/20Dur: 0.5 days Finish: Tue 13/10/20Dur: 3 days Finish: Sun 25/10/20
Dur: 12 days Finish: Wed 28/10/20
Dur: 3 days
Res: Res: Res: Res: Res:

Completing The Drilling

Milestone Date: Sat 28/11/20


ID: 56

Page 10
Page 11
Page 12
ement Rig up The BOP Drill The Third Section Run Intermediate Casing & Cementing Drill The Fourth Section Run Producti
46 Start: Wed 28/10/20ID: 47 Start: Thu 29/10/20ID: 48 Start: Mon 09/11/20 ID: 49 Start: Sat 14/11/20ID: 50 Start: Fri 20/
3 days Finish: Thu 29/10/20
Dur: 1 day Finish: Mon 09/11/20Dur: 11 days Finish: Sat 14/11/20Dur: 5 days Finish: Fri 20/11/20Dur: 6 days Finish: Mon 2
Res: Res: Res: Res: Res:

Page 13
Page 14
Page 15
un Production Casing & Cementing Run The Production Liner Run Test String Perform Underbalance Perforate The Promising Interval
tart: Fri 20/11/20 ID: 51 Start: Mon 23/11/20 ID: 52 Start: Tue 24/11/20ID: 53 Start: Thu 26/11/20ID: 54 Start: Fri 27/11/20 ID: 55
nish: Mon 23/11/20Dur: 3 days Finish: Tue 24/11/20Dur: 1 day Finish: Thu 26/11/20
Dur: 2 days Finish: Fri 27/11/20Dur: 1 day Finish: Sat 28/11/20Dur: 1 day
es: Res: Res: Res: Res:

Page 16
Page 17
Page 18
Test The Well
Complete of Testing The Well
Start: Sat 28/11/20ID: 57
Finish: Sat 12/12/20Dur: 14 days Milestone Date: Sat 12/12/20
Res: ID: 58

Commercial Announce Completing The Tasks for this


Start: Sun 13/12/20ID: 59 Project
Finish: Mon 21/12/20
Dur: 7 days Milestone Date: Mon 21/12/20
Res: ID: 60

Page 19
Page 20
Page 21
Critical Milestone Critical Inserted Marked Project Summary
Project: Petroleum Project Noncritical Critical Summary Inserted Critical External Highlighted Critical
Date: Sat 17/12/16
Critical Milestone Summary Critical Marked External Highlighted Noncritical

Page 22