Professional Documents
Culture Documents
Bar Chart Detail of IRBN
Bar Chart Detail of IRBN
ADMINISTATIVE BLOCK
Toilet Block, Bath Room, Multi Puropse Hall, Quarter Master Store, Office, Changes by client (Commandent IRBN) on dt. 07.09.2018 and jointly meeting with S.E &
F.F Masonry Work E.E, Architect and other's on dt. 13.11.2018 for ammendment of changes as recommended by client and assure to provide us ammended drawings and still waiting of
same
Toilet Block, Bath Room, GYM Hall, Changes by client (Commandent IRBN) on dt. 07.09.2018 and jointly meeting with S.E & E.E, Architect and other's on dt.
S.F Masonry Work 13.11.2018 for ammendment of changes as recommended by client and assure to provide us ammended drawings and still waiting of same
External Plastring
Tile's Work G.F Tiles reached at site before15-02-2019
Tile's Work F.F Tiles reached at site before15-02-2019
Tile's Work S.F Tiles reached at site before15-02-2019
Still amended architecture Drawings are pending from department along with Drainage Drg.
Plumbing Works
Stainless steel S.S reached at site before 20-02-2019
Painting Works Paint reached at site before 26-02-2019, Need colour scheme drawing from department
Toughend Glass Still Architecture Drawing and approval of rates are pending from department
Handing Over
ADMINISTATIVE BLOCK
Jän.19 Feb.19 Mär.19 Apr.19 Mai.19 Jun.19 Jul.19 Aug.19 Sep.19 Okt.19 Nov.19