BAR CHART :- CONSTRUCTION OF 80 MEN BARRACKS AT KAVARATTI LAKSHAWDEEP

Agency :- M/s SKYLINE AIRCONDITIONING ENGINEERS PVT. LTD. NEW DELHI


Jawan Barracks
Jän.19 Feb.19 Mär.19 Apr.19 Mai.19 Jun.19 Jul.19 Aug.19 Sep.19 Okt.19 Nov.19

material Aggange ment


S. Labour Permit
Earth Work & P.C.C Complited
G.F Roof Slab Concreting Complited
F.F Roof Slab Concreting Complited
S.F Roof Slab Concreting Complited
G.F Masonry Work Complited
F.F Masonry Work
S.F Masonry Work
Inside Plastring G.F
Inside Plastring F.F
Inside Plastring S.F
External Plastring
Plumbing Works
Electrical Works
Pinting Works
Tile, Granite, Wood, S.S Etc.
Handing Over

ADMINISTATIVE BLOCK

Earth Work & P.C.C


G.F Roof Slab Concreting
F.F Roof Slab Concreting
S.F Roof Slab Concreting
G.F Masonry Work
F.F Masonry Work
S.F Masonry Work
BAR CHART :- CONSTRUCTION OF 80 MEN BARRACKS AT KAVARATTI LAKSHAWDEEP
Agency :- M/s SKYLINE AIRCONDITIONING ENGINEERS PVT. LTD. NEW DELHI
Jawan Barracks
Jän.19 Feb.19 Mär.19 Apr.19 Mai.19 Jun.19 Jul.19 Aug.19 Sep.19 Okt.19 Nov.19

material Aggange ment


S. Labour Permit
Kitchen, Painter Room, Dining hall, WET Canteeb, Changes by client (Commandent IRBN) on dt. 07.09.2018 and jointly meeting with S.E & E.E, Architect and other's
G.F Masonry Work on dt. 13.11.2018 for ammendment of changes as recommended by client and assure to provide us ammended drawings and still waiting of same

Toilet Block, Bath Room, Multi Puropse Hall, Quarter Master Store, Office, Changes by client (Commandent IRBN) on dt. 07.09.2018 and jointly meeting with S.E &
F.F Masonry Work E.E, Architect and other's on dt. 13.11.2018 for ammendment of changes as recommended by client and assure to provide us ammended drawings and still waiting of
same
Toilet Block, Bath Room, GYM Hall, Changes by client (Commandent IRBN) on dt. 07.09.2018 and jointly meeting with S.E & E.E, Architect and other's on dt.
S.F Masonry Work 13.11.2018 for ammendment of changes as recommended by client and assure to provide us ammended drawings and still waiting of same

Inside Plastring G.F Metrials Reached at site

Inside Plastring F.F Material Reached at site

Inside Plastring S.F Material Reached at site

External Plastring
Tile's Work G.F Tiles reached at site before15-02-2019
Tile's Work F.F Tiles reached at site before15-02-2019
Tile's Work S.F Tiles reached at site before15-02-2019

Granite Work Granite reached at site before 28-02-2019

Wood Wood reached at site before 28-02-2019

Aluminium work Aluminium reached at site before 15-02-2019

Still amended architecture Drawings are pending from department along with Drainage Drg.
Plumbing Works
Stainless steel S.S reached at site before 20-02-2019

Painting Works Paint reached at site before 26-02-2019, Need colour scheme drawing from department

Toughend Glass Still Architecture Drawing and approval of rates are pending from department

Electrical Works Material Reached at site

Handing Over
ADMINISTATIVE BLOCK
Jän.19 Feb.19 Mär.19 Apr.19 Mai.19 Jun.19 Jul.19 Aug.19 Sep.19 Okt.19 Nov.19

material Aggange ment


S. Labour Permit
Surveyer marking given by department on dt. 26.12.2018
Earth Work & P.C.C
G.F Roof Slab Concreting
F.F Roof Slab Concreting
S.F Roof Slab Concreting
G.F Masonry Work
F.F Masonry Work
S.F Masonry Work
Inside Plastring G.F
Inside Plastring F.F
Inside Plastring S.F
External Plastring
Granite Work
Wood
Aluminium work
Plumbing Works
Stainless steel
Painting Works
Toughend Glass Still Architecture Drawing and approval of rates are pending from department
Electrical Works
Handing Over