WEEKLY REPORT (WEEK #1)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 14 – 20 JUNI 2011

A. MANPOWER REPORT

Mon Tue Wed Thu Fri Sat Sun


14/06/11 15/06/11 16/06/11 17/06/11 18/06/11 19/06/11 20/06/11
Supervisor 1 1 1 1 1 0 0
Safety 1 1 1 1 1 0 0
Foreman 0 0 0 0 0 0 0
Labor 4 2 2 10 10 0 0
Security 0 0 0 0 0 0 0
Total Manpower/Days 6 4 4 12 12 0 0
Hours / Days 8 8 8 8 8 8 8
Total Hours/ Days 48 32 32 96 96 0 0

Total Hours / Weeks 304

Man Powers
Last Week This Week Up to Date
Man Hours
0 304 304

B. PROGRESS REPORT

Progress Last Week : 0%


This Week : 7.45 %
Up To This Week : 7.45 %

Sorowako, 21 Jun1 2011


PT. Welani Jaya Sorowako

H. UMAR RANGGO
Project Manager
PT.Welani Jaya Sorowako

WEEKLY REPORT (WEEK #2)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 13 – 19 JUNI 2011

C. MANPOWER REPORT

Mon Tue Wed Thu Fri Sat Sun


14/06/11 15/06/11 16/06/11 17/06/11 18/06/11 19/06/11 20/06/11
Supervisor 1 1 1 1 1 0 0
Safety 1 1 1 1 1 0 0
Foreman 0 0 0 0 0 0 0
Labor 13 11 13 12 12 0 0
Security 0 0 0 0 0 0 0
Total Manpower/Days 15 13 15 14 14 0 0
Hours / Days 8 8 8 8 8 8 8
Total Hours/ Days 120 104 120 112 112 0 0

Total Hours / Weeks 568

Man Powers
Last Week This Week Up to Date
Man Hours
304 568 872

D. PROGRESS REPORT

Progress Last Week : 7.45 %


This Week : 12.85 %
Up To This Week : 20.30 %

Sorowako, 21 Jun1 2011


PT. Welani Jaya Sorowako

H. UMAR RANGGO
Project Manager
PT.Welani Jaya Sorowako

WEEKLY REPORT (WEEK #3)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 20 – 26 JUNI 2011

A. MANPOWER REPORT

Mon Tue Wed Thu Fri Sat Sun


20/06/11 21/06/11 22/06/11 23/06/11 24/06/11 25/06/11 26/06/11
Supervisor 1 1 1 1 1 0 0
Safety 1 1 1 1 1 0 0
Foreman 0 0 0 0 0 0 0
Labor 14 11 14 14 14 0 0
Security 0 0 0 0 0 0 0
Total Manpower/Days 16 13 16 16 16 0 0
Hours / Days 8 8 8 8 8 8 8
Total Hours/ Days 128 104 128 128 128 0 0

Total Hours / Weeks 616

Man Powers
Last Week This Week Up to Date
Man Hours
872 616 1488

B. PROGRESS REPORT

Progress Last Week : 20.30 %


This Week : 0.89 %
Up To This Week : 21.19 %

Sorowako, 27 Juni 2011


PT. Welani Jaya Sorowako

H. UMAR RANGGO
Project Manager
PT.Welani Jaya Sorowako

WEEKLY REPORT (WEEK #4)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 27 JUNI – 03 JULI 2011

A. MANPOWER REPORT
a. Performance Record

No Description Last Week This Week Total To Date


1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

b. Manpower Record

Mon Tue Wed Thu Fri Sat Sun


27/06/09 28/06/09 29/06/09 30/06/09 01/07/09 02/07/09 03/07/09
Site Manager 1 1 0 1 1 0 0
Site Supervisor 1 1 0 1 1 0 0
Safety Officer 1 1 0 1 1 0 0
Surveyor 1 1 0 0 1 0 0
Labor 14 10 0 12 10 0 0
Security 0 0 0 0 0 0 0
Total
18 14 0 15 14 0 0
Manpower/Days
Hours / Days 8 8 8 8 8 8 0
Total Hours/ Days 144 112 0 120 112 0 0
Total Hours / Weeks 488

Man Powers
Last Week This Week Up to Date
Man Hours
1488 488 1976

B. PROGRESS REPORT

Progress Last Week : 21.19 %


This Week : 3,72 %
Up To This Week : 24,92 %

A. Remark By Contractor
On Schedule
B. OUT STANDING ITEMS

No Description
1
2

C. PLAN NEXT WEEK

No Description
1 Bending Rebar for Septic Tank
2 Excavation Finishing & excavation pipe ground
3 Hauling & Filling AP25

Sorowako, 04 Juli 2011


PT. Welani Jaya Sorowako

H. UMAR RANGGO
Project Manager
PT.Welani Jaya Sorowako

WEEKLY REPORT (WEEK #5)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 04 – 10 JULI 2011

B. MANPOWER REPORT
a. Performance Record

No Description Last Week This Week Total To Date


1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

b. Manpower Record

Mon Tue Wed Thu Fri Sat Sun


04/07/09 05/07/09 06/07/09 07/07/09 08/07/09 09/07/09 10/07/09
Site Manager 1 1 1 1 1 0 0
Site Supervisor 1 1 1 1 1 0 0
Safety Officer 1 1 1 1 1 0 0
Surveyor 0 1 1 1 1 0 0
Labor 12 18 19 23 21 0 0
Security 0 0 0 0 0 0 0
Total
Manpower/Days
15 22 23 27 25 0 0
Hours / Days 8 8 8 8 8 8 0
Total Hours/ Days 120 176 184 216 200 0 0
Total Hours / Weeks 896

Man Powers
Last Week This Week Up to Date
Man Hours
1976 896 2872

B. PROGRESS REPORT

Progress Last Week : 24,92 %


This Week : 2,53 %
Up To This Week : 27,45 %

D. Remark By Contractor
On Schedule
E. OUT STANDING ITEMS

No Description
1
2

F. PLAN NEXT WEEK

No Description
1 Fill AP20 and compaction
2 Install rebar column / pedestal
3 Lean concrete for foundation

Sorowako, 11 Juli 2011


PT. Welani Jaya Sorowako

H. UMAR RANGGO
Project Manager
PT.Welani Jaya Sorowako

WEEKLY REPORT (WEEK #6)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 11 – 17 JULI 2011

C. MANPOWER REPORT
a. Performance Record

No Description Last Week This Week Total To Date


1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

b. Manpower Record

Mon Tue Wed Thu Fri Sat Sun


11/07/11 12/07/11 13/07/11 14/07/11 15/07/11 16/07/11 17/07/11
Site Manager 1 1 1 1 1 0 0
Site Supervisor 1 1 1 1 1 0 0
Safety Officer 1 1 1 1 1 0 0
Surveyor 1 1 1 1 0 0 0
Labor 21 20 18 19 19 0 0
Security 0 0 0 0 0 0 0
Total
Manpower/Days
25 24 22 23 22 0 0
Hours / Days 8 8 8 8 8 8 0
Total Hours/ Days 200 192 176 184 176 0 0
Total Hours / Weeks 928

Man Powers
Last Week This Week Up to Date
Man Hours
2872 928 3800

B. PROGRESS REPORT

Progress Last Week : 27,45 %


This Week : 2,65 %
Up To This Week : 30.10 %

G. Remark By Contractor
SCHEDULE TERLAMBAT (MATERIAL LEAN CONCRETE BY CS-PTI STOCK
OUT)
H. OUT STANDING ITEMS

No Description
1 Lean concrete for foundation
2 Install rebar column / pedestal

I. PLAN NEXT WEEK

No Description
1 Lean concrete for foundation
2 Install rebar column / pedestal
3 Fabrication and install formwork
4 Install rebar for septictank

Sorowako, 18 Juli 2011 Approved,


PT. Welani Jaya Sorowako PTI Representative,

H. UMAR RANGGO SAPTO SUPRIYANTO


Project Manager B/N : 5799
Date :
PT.Welani Jaya Sorowako

WEEKLY REPORT (WEEK #7)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 18 – 24 JULI 2011

D. MANPOWER REPORT
a. Performance Record

No Description Last Week This Week Total To Date


1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

b. Manpower Record

Mon Tue Wed Thu Fri Sat Sun


18/07/11 19/07/11 20/07/11 21/07/11 22/07/11 23/07/11 24/07/11
Site Manager 1 1 1 1 1 0 0
Site Supervisor 1 1 1 1 1 0 0
Safety Officer 1 1 1 1 1 0 0
Surveyor 1 1 1 1 0 0 0
Labor 20 20 20 19 21 15 2
Security 0 0 0 0 0 0 0
Total
Manpower/Days
24 24 24 23 24 15 2
Hours / Days 8 8 8 8 8 8 8
Total Hours/ Days 192 192 192 184 192 120 16
Total Hours / Weeks 1088

Man Powers
Last Week This Week Up to Date
Man Hours
3800 1088 4888

B. PROGRESS REPORT

Progress Last Week : 30.10 %


This Week : %
Up To This Week : %
J. Remark By Contractor
SCHEDULE TERLAMBAT (MATERIAL LEAN CONCRETE BY CS-PTI STOCK
OUT)

K. OUT STANDING ITEMS

No Description
1 Install rebar column / pedestal

L. PLAN NEXT WEEK

No Description
1 Install rebar column / pedestal
2 Fabrication and install formwork
3 Install rebar for septictank

Sorowako, 23 Juli 2011 Approved,


PT. Welani Jaya Sorowako PTI Representative,

H. UMAR RANGGO SAPTO SUPRIYANTO


Project Manager B/N : 5799
Date :
PT.Welani Jaya Sorowako

WEEKLY REPORT (WEEK #8)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 25 – 31 JULI 2011

E. MANPOWER REPORT
a. Performance Record

No Description Last Week This Week Total To Date


1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

b. Manpower Record

Mon Tue Wed Thu Fri Sat Sun


25/07/11 26/07/11 27/07/11 28/07/11 29/07/11 30/07/11 31/07/11
Site Manager 1 1 1 1 1 0 0
Site Supervisor 1 1 1 1 1 0 0
Safety Officer 1 1 1 1 1 0 0
Surveyor 0 0 0 0 1 0 0
Labor 18 17 18 18 15 0 0
Security 0 0 0 0 0 0 0
Total
Manpower/Days
21 20 21 21 19 0 0
Hours / Days 8 8 8 8 8 8 8
Total Hours/ Days 168 160 168 168 152 0 0
Total Hours / Weeks 816

Man Powers
Last Week This Week Up to Date
Man Hours
4888 816 5704

B. PROGRESS REPORT

Progress Last Week : 30.10 %


This Week : %
Up To This Week : %
M. Remark By Contractor
SCHEDULE TERLAMBAT (MATERIAL LEAN CONCRETE BY CS-PTI STOCK
OUT)

N. OUT STANDING ITEMS

No Description
1

O. PLAN NEXT WEEK

No Description
1 Install rebar for septictank

Sorowako, 01 Agustus 2011 Approved,


PT. Welani Jaya Sorowako PTI Representative,

H. UMAR RANGGO SAPTO SUPRIYANTO


Project Manager B/N : 5799
Date :
PT.Welani Jaya Sorowako

WEEKLY REPORT (WEEK #32)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 04– 10 Agustus 2011

F. MANPOWER REPORT
a. Performance Record

No Description Last Week This Week Total To Date


1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

b. Manpower Record

Mon Tue Wed Thu Fri Sat Sun


04/08/11 05/08/11 06/08/11 07/08/11 08/08/11 09/08/11 10/08/11
Site Manager 1 1 1 1 1 0 0
Site Supervisor 1 1 1 1 1 0 0
Safety Officer 1 1 1 1 1 0 0
Surveyor 0 0 0 0 1 0 0
Labor 14 14 14 14 14 0 0
Security 0 0 0 0 0 0 0
Total
Manpower/Days
17 17 17 17 17 0 0
Hours / Days 8 8 8 8 8 8 8
Total Hours/ Days 136 136 136 1136 136 0 0
Total Hours / Weeks 680

Man Powers
Last Week This Week Up to Date
Man Hours
5704 680 6384

B. PROGRESS REPORT

Progress Last Week : 30.10 %


This Week : %
Up To This Week : %
P. Remark By Contractor
SCHEDULE TERLAMBAT (MATERIAL LEAN CONCRETE BY CS-PTI STOCK
OUT)

Q. OUT STANDING ITEMS

No Description
1

R. PLAN NEXT WEEK

No Description
1 Install rebar for septictank

Sorowako, 10 Agustus 2011 Approved,


PT. Welani Jaya Sorowako PTI Representative,

H. UMAR RANGGO SAPTO SUPRIYANTO


Project Manager B/N : 5799
Date :
PT.Welani Jaya Sorowako

WEEKLY REPORT (WEEK #33)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 11– 18 Agustus 2011

G. MANPOWER REPORT
a. Performance Record

No Description Last Week This Week Total To Date


1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

b. Manpower Record

Thu Fri Sat Sun Mon Tue Wed


11/08/11 12/08/11 13/08/11 14/08/11 15/08/11 16/08/11 17/08/11
Site Manager 1 1 1 1 1 1 0
Site Supervisor 1 1 1 1 1 1 0
Safety Officer 1 1 1 1 1 1 0
Surveyor 0 0 0 0 0 0 0
Labor 12 12 9 10 13 13 0
Security 0 0 0 0 0 0 0
Total
Manpower/Days
15 15 15 13 16 16 0
Hours / Days 8 8 8 8 8 8 8
Total Hours/ Days 120 120 120 104 128 128 0
Total Hours / Weeks 720

Man Powers
Last Week This Week Up to Date
Man Hours
6384 712 7096

B. PROGRESS REPORT

Progress Last Week : 30.10 %


This Week : %
Up To This Week : %
S. Remark By Contractor
SCHEDULE TERLAMBAT (MATERIAL LEAN CONCRETE BY CS-PTI STOCK
OUT)

T. OUT STANDING ITEMS

No Description
1

U. PLAN NEXT WEEK

No Description
1 Install rebar for septictank

Sorowako, 10 Agustus 2011 Approved,


PT. Welani Jaya Sorowako PTI Representative,

H. UMAR RANGGO SAPTO SUPRIYANTO


Project Manager B/N : 5799
Date :
PT.Welani Jaya Sorowako

WEEKLY REPORT (WEEK #34)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 18– 24 Agustus 2011

H. MANPOWER REPORT
a. Performance Record

No Description Last Week This Week Total To Date


1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

b. Manpower Record

Thu Fri Sat Sun Mon Tue Wed


18/08/11 19/08/11 20/08/11 21/08/11 22/08/11 23/08/11 24/08/11
Site Manager 1 1 1 0 1 1 1
Site Supervisor 1 1 1 0 1 1 1
Safety Officer 1 1 1 0 1 1 1
Surveyor 0 0 0 0 0 0 0
Labor 15 13 7 0 13 13 13
Security 0 0 0 0 0 0 0
Total
Manpower/Days
18 16 10 0 16 16 16
Hours / Days 8 8 8 8 8 8 8
Total Hours/ Days 144 128 80 0 128 128 128
Total Hours / Weeks 736

Man Powers
Last Week This Week Up to Date
Man Hours
7096 736 7832

B. PROGRESS REPORT

Progress Last Week : 25.75 %


This Week : 30.56%
Up To This Week : 49.72%
V. Remark By Contractor
SCHEDULE TERLAMBAT (MATERIAL LEAN CONCRETE BY CS-PTI STOCK
OUT)

W. OUT STANDING ITEMS

No Description
1

X. PLAN NEXT WEEK

No Description
1

Sorowako, 24 Agustus 2011 Approved,


PT. Welani Jaya Sorowako PTI Representative,

H. UMAR RANGGO SAPTO SUPRIYANTO


Project Manager B/N : 5799
Date :
PT.Welani Jaya Sorowako
WEEKLY REPORT (WEEK #37)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 9 – 15 September 2011

A. PERFORMANCE RECORD
No Description Last Week This Week Total To Date
1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

B. MANPOWER REPORT
Fri Sat Sun Mon Tue Wed Thu
9/9/11 10/9/11 11/9/11 12/9/11 13/9/11 14/9/11 15/9/11
Supervisor 2 0 0 2 2 2 2
Safety 1 0 0 1 1 1 1
Foreman 0 0 0 0 0 0 0
Labor 15 0 0 15 15 15 15
Security 0 0 0 0 0 0 0
Total Manpower/Days 18 0 0 18 18 18 18
Hours / Days 8 0 0 8 8 8 8
Total Hours/ Days 144 0 0 144 144 144 144
Total Hours / Weeks 720

Man Powers 18
Last Week This Week Up to Date
Man Hours
720 720 720

C. PROGRESS REPORT

Progress Last Week : 55.60%


This Week : 4.17 %
Up To This Week : 59.77 %

Sorowako, 22 September 2011


PT. Welani Jaya Sorowako

H. UMAR RANGGO
Project Manager

C. Remark By Contractor

D. OUT STANDING ITEMS

No Description
1 Piping Material (By PTI)
2 Electrical Instruments (By PTI)

E. PLAN NEXT WEEK

No Description
1 Drainage System
2 Piping Fabrication
3 Concrete Floor

Sorowako, 22 September 2011 Approved,


PT. Welani Jaya Sorowako PTI Representative,

H. UMAR RANGGO SAPTO SUPRIYANTO


Project Manager B/N : 5799
Date :
PT.Welani Jaya Sorowako
WEEKLY REPORT (WEEK #38)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 16 – 22 September 2011

B. PERFORMANCE RECORD
No Description Last Week This Week Total To Date
1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

D. MANPOWER REPORT
Sat Sun Mon Tue Wed Thu Fri
16/9/11 17/9/11 18/9/11 19/9/11 20/9/11 21/9/11 22/9/11
Supervisor 0 0 2 2 2 2 2
Safety 0 0 1 1 1 1 1
Foreman 0 0 0 0 0 0 0
Labor 0 0 15 15 15 15 15
Security 0 0 0 0 0 0 0
Total Manpower/Days 0 0 18 18 18 18 18
Hours / Days 0 0 20 20 8 12 8
Total Hours/ Days 0 0 360 360 144 216 144
Total Hours / Weeks 1224

Man Powers 18
Last Week This Week Up to Date
Man Hours
720 1224 1224

E. PROGRESS REPORT
Progress Last Week : 57.12%
This Week : 57.12%
Up To This Week : 57.12 %
Sorowako, 30 September 2011
PT. Welani Jaya Sorowako

H. UMAR RANGGO
Project Manager
F. Remark By Contractor

G. OUT STANDING ITEMS

No Description
1 Piping Material (By PTI)
2 Electrical Instruments (By PTI)

H. PLAN NEXT WEEK

No Description
1 Drainage System
2 Piping Fabrication
3 Concrete Block

Sorowako, 30 September 2011 Approved,


PT. Welani Jaya Sorowako PTI Representative,

H. UMAR RANGGO SAPTO SUPRIYANTO


Project Manager B/N : 5799
Date :

PT.Welani Jaya Sorowako


WEEKLY REPORT (WEEK #40)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 30 September – 6 Oktober 2011

C. PERFORMANCE RECORD
No Description Last Week This Week Total To Date
1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

F. MANPOWER REPORT
Fri Sat Sun Mon Tue Wed Thu
30/9/11 1/10/11 2/10/11 3/10/11 4/10/11 5/10/11 6/10/11
Supervisor 2 2 0 2 2 2 2
Safety 1 1 0 1 1 1 1
Foreman 0 0 0 0 0 0 0
Labor 15 9 0 15 15 10 6
Security 0 0 0 0 0 0 0
Total Manpower/Days 18 12 0 18 18 13 9
Hours / Days 8 8 0 8 8 8 8
Total Hours/ Days 144 96 0 144 144 104 72
Total Hours / Weeks 704

Man Powers 9
Last Week This Week Up to Date
Man Hours
1224 704 704

G. PROGRESS REPORT

Progress Last Week : 57.12%


This Week : 2.83%
Up To This Week : 59.96%

Sorowako, 7 Oktober 2011


PT. Welani Jaya Sorowako

H. UMAR RANGGO
Project Manager

I. Remark By Contractor
J. OUT STANDING ITEMS

No Description
1 Piping Material (By PTI)
2 Electrical Instruments (By PTI)

K. PLAN NEXT WEEK

No Description
1 Drainage System
2 Piping Fabrication
3 Concrete Block

Sorowako, 7 Oktober 2011 Approved,


PT. Welani Jaya Sorowako PTI Representative,

H. UMAR RANGGO SAPTO SUPRIYANTO


Project Manager B/N : 5799
Date :

PT.Welani Jaya Sorowako


WEEKLY REPORT (WEEK #41)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 7 – 13 Oktober 2011

D. PERFORMANCE RECORD
No Description Last Week This Week Total To Date
1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

H. MANPOWER REPORT
Fri Sat Sun Mon Tue Wed Thu
7/10/11 8/10/11 9/10/11 10/10/11 11/10/11 12/10/11 13/10/11
Supervisor 2 0 0 2 2 2 2
Safety 1 0 0 1 1 1 1
Foreman 0 0 0 0 0 0 0
Labor 6 0 0 15 15 15 15
Security 0 0 0 0 0 0 0
Total Manpower/Days 9 0 0 18 18 18 18
Hours / Days 8 0 0 8 8 8 8
Total Hours/ Days 72 0 0 144 144 144 144
Total Hours / Weeks 648

Man Powers 18
Last Week This Week Up to Date
Man Hours
704 648 1352

I. PROGRESS REPORT

Progress Last Week : 59.96%


This Week : 2.78%
Up To This Week : 62.73%

Sorowako, 14 Oktober 2011


PT. Welani Jaya Sorowako

H. UMAR RANGGO
Project Manager

L. Remark By Contractor
M. OUT STANDING ITEMS

No Description
1 Piping Material (By PTI)
2 Electrical Instruments (By PTI)

N. PLAN NEXT WEEK

No Description
1 Drainage System
2 Piping Fabrication
3 Concrete Block

Sorowako, 14 Oktober 2011 Approved,


PT. Welani Jaya Sorowako PTI Representative,

H. UMAR RANGGO SAPTO SUPRIYANTO


Project Manager B/N : 5799
Date :

PT.Welani Jaya Sorowako


WEEKLY REPORT (WEEK #41)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 7 – 13 Oktober 2011

E. PERFORMANCE RECORD
No Description Last Week This Week Total To Date
1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

J. MANPOWER REPORT
Fri Sat Sun Mon Tue Wed Thu
7/10/11 8/10/11 9/10/11 10/10/11 11/10/11 12/10/11 13/10/11
Supervisor 2 0 0 2 2 2 2
Safety 1 0 0 1 1 1 1
Foreman 0 0 0 0 0 0 0
Labor 6 0 0 15 15 15 15
Security 0 0 0 0 0 0 0
Total Manpower/Days 9 0 0 18 18 18 18
Hours / Days 8 0 0 8 8 8 8
Total Hours/ Days 72 0 0 144 144 144 144
Total Hours / Weeks 648

Man Powers 18
Last Week This Week Up to Date
Man Hours
704 648 1352

K. PROGRESS REPORT

Progress Last Week : 59.96%


This Week : 2.78%
Up To This Week : 62.73%

Sorowako, 14 Oktober 2011


PT. Welani Jaya Sorowako

H. UMAR RANGGO
Project Manager

O. Remark By Contractor
P. OUT STANDING ITEMS

No Description
1 Piping Material (By PTI)
2 Electrical Instruments (By PTI)

Q. PLAN NEXT WEEK

No Description
1 Drainage System
2 Piping Fabrication
3 Concrete Block

Sorowako, 14 Oktober 2011 Approved,


PT. Welani Jaya Sorowako PTI Representative,

H. UMAR RANGGO SAPTO SUPRIYANTO


Project Manager B/N : 5799
Date :

PT.Welani Jaya Sorowako


WEEKLY REPORT (WEEK #44)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 28 Oktober - 3 November 2011

F. PERFORMANCE RECORD
No Description Last Week This Week Total To Date
1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

L. MANPOWER REPORT
Fri Sat Sun Mon Tue Wed Thu
28/10/11 29/10/11 30/10/11 31/10/11 1/1/11 2/11/11 3/11/11
Supervisor 2 0 0 2 2 2 2
Safety 1 0 0 1 1 1 1
Foreman 0 0 0 0 0 0 0
Labor 15 0 0 15 15 15 15
Security 0 0 0 0 0 0 0
Total Manpower/Days 15 0 0 18 18 18 18
Hours / Days 8 0 0 8 8 8 8
Total Hours/ Days 144 0 0 144 144 144 144
Total Hours / Weeks 720

Man Powers 18
Last Week This Week Up to Date
Man Hours
1352 720 2072

M. PROGRESS REPORT

Progress Last Week : 62.73%


This Week : 4.36%
Up To This Week : 67.09%

Sorowako, 4 November 2011


PT. Welani Jaya Sorowako

H. UMAR RANGGO
Project Manager

R. Remark By Contractor
S. OUT STANDING ITEMS

No Description
1 Piping Material (By PTI)
2 Electrical Instruments (By PTI)

T. PLAN NEXT WEEK

No Description
1 Piping Fabrication
2 Concrete Block
3
4

Sorowako, 4 November 2011 Approved,


PT. Welani Jaya Sorowako PTI Representative,

H. UMAR RANGGO SAPTO SUPRIYANTO


Project Manager B/N : 5799
Date :

PT.Welani Jaya Sorowako


WEEKLY REPORT (WEEK #46)

Contract Title : GFS RECORD CENTER RELOCATION - INSTALLATION


MAIN BUILDING
Date : 11 November - 17 November 2011

A. PERFORMANCE RECORD
No Description Last Week This Week Total To Date
1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0

N. MANPOWER REPORT
Fri Sat Sun Mon Tue Wed Thu
11/11/11 12/11/11 13/10/11 14/10/11 15/1/11 16/11/11 17/11/11
Supervisor 2 0 0 2 2 2 2
Safety 1 0 0 1 1 1 1
Foreman 0 0 0 0 0 0 0
Labor 10 0 0 10 10 10 10
Security 0 0 0 0 0 0 0
Total Manpower/Days 13 0 0 13 13 13 13
Hours / Days 8 0 0 8 8 8 8
Total Hours/ Days 104 0 0 104 104 104 104
Total Hours / Weeks 520

Man Powers 13
Last Week This Week Up to Date
Man Hours
2072 520 2592

O. PROGRESS REPORT

Progress Last Week : 67.09%


This Week : 8.44%
Up To This Week : 75.53%

Sorowako, 22 November 2011


PT. Welani Jaya Sorowako

H. UMAR RANGGO
Project Manager

U. Remark By Contractor
V. OUT STANDING ITEMS

No Description
1 Piping Material (By PTI)
2 Electrical Instruments (By PTI)

W. PLAN NEXT WEEK

No Description
1
2
3
4

Sorowako, 22 November 2011 Approved,


PT. Welani Jaya Sorowako PTI Representative,

H. UMAR RANGGO SAPTO SUPRIYANTO


Project Manager B/N : 5799
Date :