Weekly Report GFS
Weekly Report GFS
A. MANPOWER REPORT
Man Powers
Last Week This Week Up to Date
Man Hours
0 304 304
B. PROGRESS REPORT
H. UMAR RANGGO
Project Manager
PT.Welani Jaya Sorowako
C. MANPOWER REPORT
Man Powers
Last Week This Week Up to Date
Man Hours
304 568 872
D. PROGRESS REPORT
H. UMAR RANGGO
Project Manager
PT.Welani Jaya Sorowako
A. MANPOWER REPORT
Man Powers
Last Week This Week Up to Date
Man Hours
872 616 1488
B. PROGRESS REPORT
H. UMAR RANGGO
Project Manager
PT.Welani Jaya Sorowako
A. MANPOWER REPORT
a. Performance Record
b. Manpower Record
Man Powers
Last Week This Week Up to Date
Man Hours
1488 488 1976
B. PROGRESS REPORT
A. Remark By Contractor
On Schedule
B. OUT STANDING ITEMS
No Description
1
2
No Description
1 Bending Rebar for Septic Tank
2 Excavation Finishing & excavation pipe ground
3 Hauling & Filling AP25
H. UMAR RANGGO
Project Manager
PT.Welani Jaya Sorowako
B. MANPOWER REPORT
a. Performance Record
b. Manpower Record
Man Powers
Last Week This Week Up to Date
Man Hours
1976 896 2872
B. PROGRESS REPORT
D. Remark By Contractor
On Schedule
E. OUT STANDING ITEMS
No Description
1
2
No Description
1 Fill AP20 and compaction
2 Install rebar column / pedestal
3 Lean concrete for foundation
H. UMAR RANGGO
Project Manager
PT.Welani Jaya Sorowako
C. MANPOWER REPORT
a. Performance Record
b. Manpower Record
Man Powers
Last Week This Week Up to Date
Man Hours
2872 928 3800
B. PROGRESS REPORT
G. Remark By Contractor
SCHEDULE TERLAMBAT (MATERIAL LEAN CONCRETE BY CS-PTI STOCK
OUT)
H. OUT STANDING ITEMS
No Description
1 Lean concrete for foundation
2 Install rebar column / pedestal
No Description
1 Lean concrete for foundation
2 Install rebar column / pedestal
3 Fabrication and install formwork
4 Install rebar for septictank
D. MANPOWER REPORT
a. Performance Record
b. Manpower Record
Man Powers
Last Week This Week Up to Date
Man Hours
3800 1088 4888
B. PROGRESS REPORT
No Description
1 Install rebar column / pedestal
No Description
1 Install rebar column / pedestal
2 Fabrication and install formwork
3 Install rebar for septictank
E. MANPOWER REPORT
a. Performance Record
b. Manpower Record
Man Powers
Last Week This Week Up to Date
Man Hours
4888 816 5704
B. PROGRESS REPORT
No Description
1
No Description
1 Install rebar for septictank
F. MANPOWER REPORT
a. Performance Record
b. Manpower Record
Man Powers
Last Week This Week Up to Date
Man Hours
5704 680 6384
B. PROGRESS REPORT
No Description
1
No Description
1 Install rebar for septictank
G. MANPOWER REPORT
a. Performance Record
b. Manpower Record
Man Powers
Last Week This Week Up to Date
Man Hours
6384 712 7096
B. PROGRESS REPORT
No Description
1
No Description
1 Install rebar for septictank
H. MANPOWER REPORT
a. Performance Record
b. Manpower Record
Man Powers
Last Week This Week Up to Date
Man Hours
7096 736 7832
B. PROGRESS REPORT
No Description
1
No Description
1
A. PERFORMANCE RECORD
No Description Last Week This Week Total To Date
1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0
B. MANPOWER REPORT
Fri Sat Sun Mon Tue Wed Thu
9/9/11 10/9/11 11/9/11 12/9/11 13/9/11 14/9/11 15/9/11
Supervisor 2 0 0 2 2 2 2
Safety 1 0 0 1 1 1 1
Foreman 0 0 0 0 0 0 0
Labor 15 0 0 15 15 15 15
Security 0 0 0 0 0 0 0
Total Manpower/Days 18 0 0 18 18 18 18
Hours / Days 8 0 0 8 8 8 8
Total Hours/ Days 144 0 0 144 144 144 144
Total Hours / Weeks 720
Man Powers 18
Last Week This Week Up to Date
Man Hours
720 720 720
C. PROGRESS REPORT
H. UMAR RANGGO
Project Manager
C. Remark By Contractor
No Description
1 Piping Material (By PTI)
2 Electrical Instruments (By PTI)
No Description
1 Drainage System
2 Piping Fabrication
3 Concrete Floor
B. PERFORMANCE RECORD
No Description Last Week This Week Total To Date
1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0
D. MANPOWER REPORT
Sat Sun Mon Tue Wed Thu Fri
16/9/11 17/9/11 18/9/11 19/9/11 20/9/11 21/9/11 22/9/11
Supervisor 0 0 2 2 2 2 2
Safety 0 0 1 1 1 1 1
Foreman 0 0 0 0 0 0 0
Labor 0 0 15 15 15 15 15
Security 0 0 0 0 0 0 0
Total Manpower/Days 0 0 18 18 18 18 18
Hours / Days 0 0 20 20 8 12 8
Total Hours/ Days 0 0 360 360 144 216 144
Total Hours / Weeks 1224
Man Powers 18
Last Week This Week Up to Date
Man Hours
720 1224 1224
E. PROGRESS REPORT
Progress Last Week : 57.12%
This Week : 57.12%
Up To This Week : 57.12 %
Sorowako, 30 September 2011
PT. Welani Jaya Sorowako
H. UMAR RANGGO
Project Manager
F. Remark By Contractor
No Description
1 Piping Material (By PTI)
2 Electrical Instruments (By PTI)
No Description
1 Drainage System
2 Piping Fabrication
3 Concrete Block
C. PERFORMANCE RECORD
No Description Last Week This Week Total To Date
1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0
F. MANPOWER REPORT
Fri Sat Sun Mon Tue Wed Thu
30/9/11 1/10/11 2/10/11 3/10/11 4/10/11 5/10/11 6/10/11
Supervisor 2 2 0 2 2 2 2
Safety 1 1 0 1 1 1 1
Foreman 0 0 0 0 0 0 0
Labor 15 9 0 15 15 10 6
Security 0 0 0 0 0 0 0
Total Manpower/Days 18 12 0 18 18 13 9
Hours / Days 8 8 0 8 8 8 8
Total Hours/ Days 144 96 0 144 144 104 72
Total Hours / Weeks 704
Man Powers 9
Last Week This Week Up to Date
Man Hours
1224 704 704
G. PROGRESS REPORT
H. UMAR RANGGO
Project Manager
I. Remark By Contractor
J. OUT STANDING ITEMS
No Description
1 Piping Material (By PTI)
2 Electrical Instruments (By PTI)
No Description
1 Drainage System
2 Piping Fabrication
3 Concrete Block
D. PERFORMANCE RECORD
No Description Last Week This Week Total To Date
1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0
H. MANPOWER REPORT
Fri Sat Sun Mon Tue Wed Thu
7/10/11 8/10/11 9/10/11 10/10/11 11/10/11 12/10/11 13/10/11
Supervisor 2 0 0 2 2 2 2
Safety 1 0 0 1 1 1 1
Foreman 0 0 0 0 0 0 0
Labor 6 0 0 15 15 15 15
Security 0 0 0 0 0 0 0
Total Manpower/Days 9 0 0 18 18 18 18
Hours / Days 8 0 0 8 8 8 8
Total Hours/ Days 72 0 0 144 144 144 144
Total Hours / Weeks 648
Man Powers 18
Last Week This Week Up to Date
Man Hours
704 648 1352
I. PROGRESS REPORT
H. UMAR RANGGO
Project Manager
L. Remark By Contractor
M. OUT STANDING ITEMS
No Description
1 Piping Material (By PTI)
2 Electrical Instruments (By PTI)
No Description
1 Drainage System
2 Piping Fabrication
3 Concrete Block
E. PERFORMANCE RECORD
No Description Last Week This Week Total To Date
1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0
J. MANPOWER REPORT
Fri Sat Sun Mon Tue Wed Thu
7/10/11 8/10/11 9/10/11 10/10/11 11/10/11 12/10/11 13/10/11
Supervisor 2 0 0 2 2 2 2
Safety 1 0 0 1 1 1 1
Foreman 0 0 0 0 0 0 0
Labor 6 0 0 15 15 15 15
Security 0 0 0 0 0 0 0
Total Manpower/Days 9 0 0 18 18 18 18
Hours / Days 8 0 0 8 8 8 8
Total Hours/ Days 72 0 0 144 144 144 144
Total Hours / Weeks 648
Man Powers 18
Last Week This Week Up to Date
Man Hours
704 648 1352
K. PROGRESS REPORT
H. UMAR RANGGO
Project Manager
O. Remark By Contractor
P. OUT STANDING ITEMS
No Description
1 Piping Material (By PTI)
2 Electrical Instruments (By PTI)
No Description
1 Drainage System
2 Piping Fabrication
3 Concrete Block
F. PERFORMANCE RECORD
No Description Last Week This Week Total To Date
1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0
L. MANPOWER REPORT
Fri Sat Sun Mon Tue Wed Thu
28/10/11 29/10/11 30/10/11 31/10/11 1/1/11 2/11/11 3/11/11
Supervisor 2 0 0 2 2 2 2
Safety 1 0 0 1 1 1 1
Foreman 0 0 0 0 0 0 0
Labor 15 0 0 15 15 15 15
Security 0 0 0 0 0 0 0
Total Manpower/Days 15 0 0 18 18 18 18
Hours / Days 8 0 0 8 8 8 8
Total Hours/ Days 144 0 0 144 144 144 144
Total Hours / Weeks 720
Man Powers 18
Last Week This Week Up to Date
Man Hours
1352 720 2072
M. PROGRESS REPORT
H. UMAR RANGGO
Project Manager
R. Remark By Contractor
S. OUT STANDING ITEMS
No Description
1 Piping Material (By PTI)
2 Electrical Instruments (By PTI)
No Description
1 Piping Fabrication
2 Concrete Block
3
4
A. PERFORMANCE RECORD
No Description Last Week This Week Total To Date
1 Personnel Injury ( PI ) 0 0 0
2 Firs Aid ( FA ) 0 0 0
3 Medical Aid ( MA ) 0 0 0
4 Near Miss ( NM ) 0 0 0
5 Facility 0 0 0
6 Traffic Accident/ Incident 0 0 0
7 Traffic Violation 0 0 0
TOTAL 0 0 0
N. MANPOWER REPORT
Fri Sat Sun Mon Tue Wed Thu
11/11/11 12/11/11 13/10/11 14/10/11 15/1/11 16/11/11 17/11/11
Supervisor 2 0 0 2 2 2 2
Safety 1 0 0 1 1 1 1
Foreman 0 0 0 0 0 0 0
Labor 10 0 0 10 10 10 10
Security 0 0 0 0 0 0 0
Total Manpower/Days 13 0 0 13 13 13 13
Hours / Days 8 0 0 8 8 8 8
Total Hours/ Days 104 0 0 104 104 104 104
Total Hours / Weeks 520
Man Powers 13
Last Week This Week Up to Date
Man Hours
2072 520 2592
O. PROGRESS REPORT
H. UMAR RANGGO
Project Manager
U. Remark By Contractor
V. OUT STANDING ITEMS
No Description
1 Piping Material (By PTI)
2 Electrical Instruments (By PTI)
No Description
1
2
3
4