Professional Documents
Culture Documents
Deploying Criticality Analysis in Multi-Plant Reliability Improvement Programs
Deploying Criticality Analysis in Multi-Plant Reliability Improvement Programs
Multi-Plant Reliability
Improvement Programs
Michel Cote & Serge Mathieu
Prosygma
Reliability and Maintenance
Professional Services
1
What is Criticality ?
A tool used to evaluate how equipment
failures impact organizational
performance in order to systematically
rank plant assets for the purpose of :
Reliability
PM /PdM Work Material
Improvement
Development Prioritization Classification
Initiatives
To ensure that
To prioritize To better
To support MRO reliability
activities dedicated prioritize work
initiatives to improvements are
to PM / PdM out of the
identify critical made based on risk
development or maintenance
spares rather than
optimization backlog
perception
2
The Process
Cross-functional analysis and input from
Operations and Maintenance, and as
required, input from Engineering,
Material Management, Environment and
Health and Safety representatives
3
Impact on Safety
0 Potential to cause death or permanent injuries
4
Deploying Criticality Analysis in
a Multi-Plant Reliability Program
5
One of the Major Tissue Producers
in North America
• Quebec (4)
• Ontario (2)
• Wisconsin (1)
• Pennsylvania (2)
• North Carolina (1)
• New York (2)
• Oregon (1)
• Arizona (1)
• Tennessee (1)
6
The Objective
• For all of the 15 mills, associate a criticality ranking to each
asset in the CMMS.
The Challenge
• Have the criticality ranking done for all of the 15 mills within
a schedule of 8 to 12 weeks.
• A total of 45,000 assets, ranging from 600 to 16,000 per mill.
7
Criticality Ranking
The criticality ranking is calculated by multiplying each of the scores (from 0 to 4) obtained
for each of the 4 criteria.
The total is then converted into one of the following 4 criticality rankings, namely A,B,C or D.
Equipment Criticality Evaluation Criticality
Description
Number Safety Environment Quality Economical Total = Ranking
PE-002 Pump xyz 4 4 4 1 64 A
PE-005 Pump ABC 4 4 4 2 128 B
VE-100 Blower YYZ 4 4 4 3 192 C
AG-201 Agitator DBC 0 1 4 4 0 A
CL-403 Air Conditionning 4 4 4 4 256 D
8
Lessons Learned
• Prevent mill personnel from taking shortcuts –this is an
objective and quantitative process
9
Keys to Success
• There is a wide variety of criticality tools and methods out there,
Keep it simple!
• Make sure to adapt the matrix with the operational context of each
facility
10
Questions ?
Michel Cote: mcote@prosygma.ca
Serge Mathieu: smathieu@prosygma.ca
WWW.PROSYGMA.CA
11