Man Hours Reduced 1921

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

ACTIVITY

VIBRATING SCREEN MESH REPLACEMENT

JOB CARRIED OUT BEFORE MODIFICATION:


*DURING MESH REPLACEMENT WE HAVE TO REMOVE THE CASING BOLTS..
*REMOVE THE CASING, REPLACE THE MESH AND FIX THE CASING AND FASTEN IT.
*MANPOWER REQUIRED: (1F+3K)
*MINIMUM TIME TAKEN: 8HRS
*TOTAL MAN HOURS: 4*8 = 32HRS
MODIFICATION DONE:
*PROCURED PNEUMATIC WRENCH FOR CASING BOLTS REMOVAL
JOB CARRIED OUT AFTER MODIFICATION:
*NOW IT TAKES ONLY 5HRS TO REPLACE THE MESH..
*MANPOWER REQUIRED: (1F+3K).
*MINIMUM TIME TAKEN: 5 HRS= 0.75 HRS
*TOTAL MAN HOURS: 4*5 =20HRS

NO. OF MAN HOURS REDUCED:

MAN HOURS REDUCED = TOTAL MAN HOURS BEFORE MODIFICATION –


TOTAL MAN HOURS AFTER MODIFICAION
= 32– 20
= 8HRS.