KOMATSU PC 300

fwHP : hp
Bucket Type : Extreme Service Excavation
Bucket Capacity (q) : 2.1 m3
Boom :
Stick :
Operation : O/B removal - Ripped material
Material load factor (LF) : 0.8 bcm/lcm
Operator Skill (OS) : 0.85
Job Effisiensi (JE) : 0.85
Bucket Fill Factor (a) : 0.90
Mechanical availability (MA) : 0.90
Cycle Time
Load Bucket : 9 sec
Swing Loaded : 5 sec
Dump Bucket : 4 sec
Swing Empty : 4 sec
Total (CT) : 22 sec
3600
Productivity = x q x OS x JE x a x LF
CT
3600
= x 2.1 m3 x 0.85 x 0.85 x 0.9 x 0.8 bcm/lcm
22

= 178.76 bcm/hour
160.884 bcm/hour