Example by Microsoft Project PDF

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ID Task Name Duration % Start Finish B B B

Complete 29 Sep '18 13 Oct '18 27 Oct '18 10 Nov '18 24 Nov '18 08 Dec '18
T S W S T M F T S W S T M F T S W S T M
1 Prepration and decoration finish schedule for 53 days? 39% Sat 06/10/18 Wed 05/12/18
smoha Administrative building ,green plaza and
luran branshes
2 Administrative building 53 days 40% Sat 06/10/18 Wed 05/12/18
3 1st FLOOR 53 days 40% Sat 06/10/18 Wed 05/12/18
4 Setting up ,Modification and Demolish work 21 days 100% Sat 06/10/18 Mon 29/10/18
5 Main electric & plumbing connction 2 days 100% Sat 06/10/18 Sun 07/10/18 100%
6 New building setting 9 days 100% Mon 08/10/18 Mon 29/10/18
7 Electric and SMART NETwork 47 days 45% Sat 13/10/18 Wed 05/12/18
8 Setting up 5 days 100% Sat 13/10/18 Wed 17/10/18
9 Accessories &finish 6 days 0% Thu 29/11/18 Wed 05/12/18
10 Plumbing work 39 days 31% Sat 13/10/18 Mon 26/11/18
11 Setting up 4 days 100% Sat 13/10/18 Tue 16/10/18
12 Ceramic 7 days 0% Tue 13/11/18 Tue 20/11/18
13 Finish 2 days 0% Sun 25/11/18 Mon 26/11/18
14 HVAC Work 26 days 35% Sat 03/11/18 Sun 02/12/18
15 Setting up(electric &drain and main erection) 7 days 50% Sat 03/11/18 Tue 13/11/18
16 Finish 3 days 0% Thu 29/11/18 Sun 02/12/18
17 Painting and decoreation work 29 days 26% Sat 27/10/18 Wed 28/11/18
18 Softness layer 7 days 95% Sat 27/10/18 Tue 06/11/18
19 Gyosum board 5 days 0% Sun 04/11/18 Thu 08/11/18
20 floor 6 days 0% Mon 12/11/18 Sun 18/11/18
21 Painting & Decoration 8 days 0% Tue 20/11/18 Wed 28/11/18
22 Furinture and Devices 4 days 0% Sun 02/12/18 Wed 05/12/18
23 2 nd FLOOR 47 days 39% Sat 06/10/18 Wed 28/11/18
24 Setting up ,Modification and Demolish work 3 days 100% Sat 06/10/18 Mon 08/10/18
25 Modification and Demolish work 3 days 100% Sat 06/10/18 Mon 08/10/18
26 Main electric & plumbing connction 1 day 100% Sat 06/10/18 Sat 06/10/18 me
27 Electric and SMART NETwork 43 days 60% Sun 07/10/18 Sun 25/11/18
28 Setting up(demolish,wire only) 6 days 100% Sun 07/10/18 Sun 21/10/18
29 Accessories &finish 4 days 0% Wed 21/11/18 Sun 25/11/18
30 Plumbing work 41 days 25% Mon 08/10/18 Sat 24/11/18
31 Setting up(3 bathroom+1 cafe) 3 days 100% Mon 08/10/18 Wed 10/10/18
32 Ceramic 7 days 0% Sun 11/11/18 Sun 18/11/18
33 Finish 2 days 0% Thu 22/11/18 Sat 24/11/18
34 HVAC Work 20 days 28% Sat 03/11/18 Sun 25/11/18
35 Setting up(electric &drain and main erection) 3 days 65% Sat 03/11/18 Mon 05/11/18
36 Finish 4 days 0% Wed 21/11/18 Sun 25/11/18
37 Painting and decoreation work 37 days 35% Wed 10/10/18 Wed 21/11/18
38 Softness layer 6 days 75% Wed 10/10/18 Mon 29/10/18
39 Gyosum board 5 days 70% Sun 04/11/18 Thu 08/11/18
40 Floor 4 days 0% Thu 08/11/18 Mon 12/11/18
41 Painting & Decoration 8 days 0% Tue 13/11/18 Wed 21/11/18
42 Furinture and Devices 3 days 0% Mon 26/11/18 Wed 28/11/18
43 Green Plaza Branche 0.89 days? 0% Sun 07/10/18 Sun 07/10/18

Task Project Summary Manual Task Start-only Deadline Manual Progress

Project: winme Split Inactive Task Duration-only Finish-only Critical


Date: Mon 01/07/19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Progress

Page 1