Example by Microsoft Project PDF
Example by Microsoft Project PDF
Example by Microsoft Project PDF
Complete 29 Sep '18 13 Oct '18 27 Oct '18 10 Nov '18 24 Nov '18 08 Dec '18
T S W S T M F T S W S T M F T S W S T M
1 Prepration and decoration finish schedule for 53 days? 39% Sat 06/10/18 Wed 05/12/18
smoha Administrative building ,green plaza and
luran branshes
2 Administrative building 53 days 40% Sat 06/10/18 Wed 05/12/18
3 1st FLOOR 53 days 40% Sat 06/10/18 Wed 05/12/18
4 Setting up ,Modification and Demolish work 21 days 100% Sat 06/10/18 Mon 29/10/18
5 Main electric & plumbing connction 2 days 100% Sat 06/10/18 Sun 07/10/18 100%
6 New building setting 9 days 100% Mon 08/10/18 Mon 29/10/18
7 Electric and SMART NETwork 47 days 45% Sat 13/10/18 Wed 05/12/18
8 Setting up 5 days 100% Sat 13/10/18 Wed 17/10/18
9 Accessories &finish 6 days 0% Thu 29/11/18 Wed 05/12/18
10 Plumbing work 39 days 31% Sat 13/10/18 Mon 26/11/18
11 Setting up 4 days 100% Sat 13/10/18 Tue 16/10/18
12 Ceramic 7 days 0% Tue 13/11/18 Tue 20/11/18
13 Finish 2 days 0% Sun 25/11/18 Mon 26/11/18
14 HVAC Work 26 days 35% Sat 03/11/18 Sun 02/12/18
15 Setting up(electric &drain and main erection) 7 days 50% Sat 03/11/18 Tue 13/11/18
16 Finish 3 days 0% Thu 29/11/18 Sun 02/12/18
17 Painting and decoreation work 29 days 26% Sat 27/10/18 Wed 28/11/18
18 Softness layer 7 days 95% Sat 27/10/18 Tue 06/11/18
19 Gyosum board 5 days 0% Sun 04/11/18 Thu 08/11/18
20 floor 6 days 0% Mon 12/11/18 Sun 18/11/18
21 Painting & Decoration 8 days 0% Tue 20/11/18 Wed 28/11/18
22 Furinture and Devices 4 days 0% Sun 02/12/18 Wed 05/12/18
23 2 nd FLOOR 47 days 39% Sat 06/10/18 Wed 28/11/18
24 Setting up ,Modification and Demolish work 3 days 100% Sat 06/10/18 Mon 08/10/18
25 Modification and Demolish work 3 days 100% Sat 06/10/18 Mon 08/10/18
26 Main electric & plumbing connction 1 day 100% Sat 06/10/18 Sat 06/10/18 me
27 Electric and SMART NETwork 43 days 60% Sun 07/10/18 Sun 25/11/18
28 Setting up(demolish,wire only) 6 days 100% Sun 07/10/18 Sun 21/10/18
29 Accessories &finish 4 days 0% Wed 21/11/18 Sun 25/11/18
30 Plumbing work 41 days 25% Mon 08/10/18 Sat 24/11/18
31 Setting up(3 bathroom+1 cafe) 3 days 100% Mon 08/10/18 Wed 10/10/18
32 Ceramic 7 days 0% Sun 11/11/18 Sun 18/11/18
33 Finish 2 days 0% Thu 22/11/18 Sat 24/11/18
34 HVAC Work 20 days 28% Sat 03/11/18 Sun 25/11/18
35 Setting up(electric &drain and main erection) 3 days 65% Sat 03/11/18 Mon 05/11/18
36 Finish 4 days 0% Wed 21/11/18 Sun 25/11/18
37 Painting and decoreation work 37 days 35% Wed 10/10/18 Wed 21/11/18
38 Softness layer 6 days 75% Wed 10/10/18 Mon 29/10/18
39 Gyosum board 5 days 70% Sun 04/11/18 Thu 08/11/18
40 Floor 4 days 0% Thu 08/11/18 Mon 12/11/18
41 Painting & Decoration 8 days 0% Tue 13/11/18 Wed 21/11/18
42 Furinture and Devices 3 days 0% Mon 26/11/18 Wed 28/11/18
43 Green Plaza Branche 0.89 days? 0% Sun 07/10/18 Sun 07/10/18
Page 1