HOW TO CONSTRUCT A

Contract
Compliance
Matrix
A solid matrix goes a long way, identifying gaps or errors in the contract document,
providing a baseline for measuring performance as it progresses, and serving
as a clear roadmap during the close-out phase.
B Y TO M R E I D

A contract compliance matrix, which what more detail, breaking down the these entries can be hot-linked to
provides a simplified overview of every clause listing into finer granularity source documents.
contract requirement, is a tool developed (for example, specifying the contents Contract compliance matrices are
by the contract administrator. While of section 6.B [7][ii]), by adding more dynamic. They reflect the status of a
a variety of formats and headers can headings—such as whether a deliver- contract only at a single point in time.
be used, typically matrices fall into able is required under the clause and Each modification to the contract
three broad categories. if so, who is responsible—or by doing requires modification to the matrix.
The first category is simple—it some of both. Each event in a program plan, such as
identifies the clause titles and provides The third category and most complex the completion of a deliverable, must
a brief synopsis of the contents. compliance matrices evolve into be noted under the appropriate heading.
The second category provides some- full-blown contracts and program The more complex the matrix, the more
management plans. Usually created maintenance it will require. Thus, every
About the Author only in electronic format, these matrices compliance matrix task must be scaled
TOM REID, CPCM, FELLOW, is chief use a large number of headings, includ- to the user’s needs. There is not a
problem solver for Certified Contracting ing due dates, reference documents, one-size-fits-all mentality to this
Solutions, LLC, in Denver, Colorado. points-of-contact, responsibilities, process. Only headings that are helpful
He is a member of the Denver Chapter authorities, and correspondence con- to the end-user should be applied—
and presently serves as the national trol references. The contract clauses no more and no less. While it saves
vice president-elect for the South Central are listed in detail, and the entire time and expense to plan the headings
Region. Send comments on this article statement of work, as well as all refer- out in advance, modern word processing
to cm@ncmahq.org. enced documents, are included. In tools allow you to add rows and columns
Web-based environments, each of in such a table with relative ease.

40 ■ Contract Management / January 2004


The “Real-World” Context management plan. From these docu- compliance matrix. Most commonly,
A contract compliance matrix serves ments the customer will generally however, no RTM exists, and the con-
many practical purposes. It might be develop a contractor surveillance tract compliance matrix must be created
used only by the contracts department plan, specifying details on contract from “whole cloth,” so to speak.
as a tool to understand the contract, oversight and performance measure-
track events in the contract, or train ment. It all starts here. The Process
new contract administrators. As a Ideally, the contract compliance The starting point is always the contract.
stand-alone, the matrix can be a useful activity starts when the request for The contract must be gathered in a
resource to help explain contract sec- proposal (RFP) is received, and a single location and read from beginning
tions or components to management requirements traceability matrix (RTM) to end. Every modification should be
or to a customer. It can also be valu- is developed to ensure that all RFP gathered into the contract file as well.
able at contract close-out time, as a requirements are being addressed. This same approach applies to both the
checklist and tracking tool. While there are significant similarities hard- and soft-copy contract formats.
More often, however, the creation between a RTM and a contract com- It will often be necessary to gather the
of a contract compliance matrix is the pliance matrix, they are fundamentally reference documents into the same
first step toward a contract management different. The RTM is set against a rel- file location. Only with a fundamental
plan. Using the matrix to establish the atively fixed document with a very grasp of the nature and complexity of
various contract requirements allows limited life span. “Performance” under the entire contract can you begin to
you to offer input to the program the proposal is straightforward— develop a matrix.
manager on those portions of his respond to the RFP. The next step is to determine your
responsibilities that must be fulfilled The contract compliance matrix audience and what data each stake-
under the contract. This presents the will most likely become far more holder needs. Compliance matrices
baseline for discussions on who dynamic, and the amount of informa- can serve a multitude of purposes. That
specifically will track the fulfillment tion necessary to be a fully functional is why there is considerable choice in
of those requirements. Once those tool for contract management can far what headings you use. In an ideal
issues are settled, you can develop a exceed the data necessary in an RTM. setting, you would create the matrix
complete contract management plan Still, a quality RTM is an excellent using all possible headings in a
for inclusion in the master program starting point to create a contract searchable database format. Then,

January 2004 / Contract Management ■ 41


H O W T O C O N S T R U C T A C O N T R A C T C O M P L I A N C E M A T R I X

sure that a matrix—of any sort—is page breaks. This is not an area in
Ten Steps to Create developed. If the client is only com- which to be dogmatic, however—stay
a Contract Compliance fortable with a simple matrix, prepare in the familiar, comfortable format-zone
Matrix that. As noted earlier, columns and that works best for you.
rows can be added later. Divide sections of the contract in
Headers come in two basic flavors. the matrix with some identifiable,
(1) Read the contract. “Fixed headers” are those that will visual break. A shaded block works well.
appear in all matrices. Typically, those Set up each section of the contract
(2) Determine the audience will be the headings such as “clause under a separate heading. Make the
to establish the appropriate number,” “clause name,” and “contents” final document, whether printed or
headings and format. or “description.” These headers are on-screen, as user-friendly as possible.
(3) Determine the correct applicable to the simplest of matrices. Your next step is to determine the
level of detail. For more complex versions, any correct level of detail for each entry
number of “variable headers” can be in the table. For a simple matrix, you
(4) Enter the data. used. These come in as many variations will probably only want to include the
(5) Capture data for variable as you and your client can imagine. prime contract document, and for
headers and flow-down Popular additional headers include: the specifications you might only say,
requirements. “Identifies the work requirements
(1) Deliverables; under the contract.”
(6) Review contract For more complex matrices and
modifications. (2) Responsible organization/person; specific user-tailored needs, it may be
(7) Add disclaimers. appropriate to break out each section
(3) Referenced documents; of the statement of work. Most contracts
(8) Proofread, proofread, will incorporate other documents by
proofread. (4) Documents incorporated reference that will be applicable to the
(9) Distribute for comment by reference; contract in one way or another. For
before going “final.” completeness, some or all of these may
(5) Customer point-of-contact; need to be fully analyzed and the
(10) Keep the matrix current.
requirements contained in them spelled
(6) Due date; out in the matrix. The key is to make
you would selectively print versions sure you have tailored the complexity
containing only the headings neces- (7) Reporting date; of the matrix to the needs of the user.
sary for a particular application. For If you make the matrix too simple or too
example, a matrix might be useful for (8) Actual delivery date; complex, the document will be useless.
tracking the funding modifications.
But, there could also be reasons why (9) Applicability timeframe; The Program
you would not want the funding infor- Now, it is time to enter the data. In a
mation to be widely disseminated. (10) Correspondence control worst-case scenario, you may have to
While the data could reside in the reference number; type it all in longhand. If so, be sure
matrix, you would only print that to have a separate set of eyes proof-
column of data on those versions (11) Links to other databases; and read your data entry. If you have
being distributed to those who need access to a soft copy of the contract,
to know this kind of information. (12) Required format for each you will be able to cut and paste the
Next, you will want to establish the deliverable. sections where they belong.
matrix headings. Detailed interviews Be careful—a matrix is useless if all
should be held with the client to under- Next, format the document in what- it does is take the entire contents of
stand their needs and their interests. ever software you are using. While the a contract and format it in columns.
If they have never used a matrix and temptation is to use a spreadsheet, The “contents” or “description” sec-
found what a functional tool it can be, experience has shown that using tion needs to be a readable synopsis
you may have to share some examples. tables in a word processing program of the contract, not all of the legalese.
Do not undersell the need for continued works best. For one thing, you will Remember: Your user is most likely a
maintenance, but do not oversell the have a lot of words, and most spread- business executive or a program man-
need for complexity in a simple con- sheet programs do not do spell-check ager. They expect you to know what
tract. The scope must be sized to your automatically. Also, tables usually the contract says in detail. All they
user’s specific needs. At this stage, the provide you with greater flexibility in need is a brief description to under-
more important aspect is to make more readable cell sizes and formatted stand the thrust of a clause. Even for

42 ■ Contract Management / January 2004


H O W T O C O N S T R U C T A C O N T R A C T C O M P L I A N C E M A T R I X

Sample Compliance Matrix (Simple) Format


Clause # Title Description
SECTION A: SF1449

None Solicitation, Offer, and Standard form used to award a contract.


Award
SECTION B: SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 Services Being Acquired Provides the basic nature of the services to be provided and requires
[state the general nature of the work to be performed].

B.2 Estimated Cost and Fee States that the estimated cost under this contract is $__________,
and the potential fee is $________.

B.3 Availability of Provides that there are no funds available for this procurement and states that
Appropriated Funds the government will notify party when there are. It also cautions against begin-
ning work before funds are available. Any action on the part of the contractor
may not be reimbursed.

B.4 Obligation of Funds Sets forth the amount of funds obligated under the contract as modified
from time to time.
SECTION C: DESCRIPTION / SPECIFICATION / WORK STATEMENT

C.1 General Information Sets forth the basic requirements under the contract.

C.2 Statement of Work Sets forth specific requirements. See program plan for details available from
the program manager.

C.3 Deliverables Specifies deliverables the customer is expecting to see and due dates for each.
Refer to program plan.
SECTION D: PACKAGING AND MARKING

D.1 Packaging and Marking Requires use of standard commercial practices in packing and marking shipments.
It includes an additional requirement to specify the contract number and COR in
all addresses.
SECTION E: INSPECTION AND ACCEPTANCE

E.1 Inspection Of Services— Standard FAR clause—establishes the government’s right to inspect all services
Cost Reimbursement called for by the contract at all places and times.
(FAR 52.246-5) (APR 1984)

E.2 Acceptance Acceptance of all work is by the contracting officer or duly authorized representative.
SECTION F: DELIVERIES OR PERFORMANCE

F.1 Term of Contract Establishes the contract term of one year with two options.

F.2 Option to Extend the Allows the government to extend the term of the contract with 30-days notice,
Term of the Contract as long as intent was communicated at least three months before expiration.

F.3 Stop-Work Order FAR Standard FAR clause—establishes the government’s right to issue a written order
52.242-15 (AUG 1989) for the contractor to stop all or any part of the work under the contract. The
Alternate I (APR 1984) contracting officer shall make an equitable adjustment (e.g., delivery schedule,
estimated cost, fee, etc.) as appropriate.

Table 1. Compliance Matrix for Contract No. 123-4546-789 ABC, Inc., for U.S. Government

January 2004 / Contract Management ■ 43


H O W T O C O N S T R U C T A C O N T R A C T C O M P L I A N C E M A T R I X

your own use, the brief description fying the funds on the contract, the the contract. While considerable judg-
should allow you to peruse the matrix billing schedule, and the payment ment will be applied in synopsizing
and quickly hone in on a particular schedule. In simpler contracts, how- the contents of clauses, always keep
section. Too many words, especially ever, especially in smaller companies, in mind that the goal of the matrix
used verbatim, and you have defeated including this data in the matrix may is to be a useful tool in contract man-
the purpose of the matrix. be valuable and may, in fact, be the agement. Too much or too little
As you enter this data, it may be only location for such information. information will not do—find the
the right time to capture the informa- Make sure you add appropriate dis- happy medium.
tion for the variable headers. This will claimers. Most businesses will want to Distribute a draft for comment.
depend on what information you have keep compliance matrix data confi- Depending on your organization, that
available and what responsibility dential. This is particularly true with may include a large staff of 30 or one
assignments have already been made. certain headings of information. or two key people. Ask them what
If necessary, begin sharing drafts of Whether a deliverable has been met they find helpful and what else they
several pages of the matrix with the on time is not necessarily public would like to see. Emphasize that it is
client and determining the various information. Highlighting the fact that a living document and designed to be
responsibilities. If due dates are part there are deliverables required under an effective tool. You may be the only
of the variable headings, make the data your contract that have never been person in your entire organization
in the cell useful. While “30 days ADC” delivered is also a sensitive subject. that has ever read the entire contract.
may make perfect sense to us, go ahead Consequently, your legal and general (Let’s say that if there is only one
and calculate the date, so it says, management departments will have person in your organization who has
specifically, “Due on June 10, 2004.” an opinion on what data gets released. done so, it had better be you!) But
In all cases, you should capture the Use the appropriate legend that your every manager and every person
flow-down requirements. One effective company prescribes. responsible for a deliverable, however,
way to note them is to use the high- Additionally, always include needs to know what is required.
lighting function available in most word a disclaimer. Here is an example It is your job to translate.
processing programs. Alternatively, of language to use: Finally, make certain that the
you can highlight the requirement by matrix is kept current. While this
using a different color text. Make it This document is a working tool for use takes some attention, an outdated
easy for the procurement folks to in managing the subject contract. While matrix is useless and wastes the time
comply with the contract. believed accurate, only the contract invested in creating it. Once you
Be certain to review each of the document contains the full and complete have one developed, be faithful in
contract modifications. If there are agreement between the parties. While this maintaining it. For a good example,
not very many of them, do the entire matrix may provide general guidance, it see the chart on page 43.
contract and then add in the modifi- should not be relied on for detailed inter-
cations. If the modifications are pretations of the contract language or the Using the “Sight”
extensive, it might be useful to create rights or responsibilities of either (or any) A solid matrix goes a long way toward
a conformed version of the contract party. When in doubt, read the contract. identifying gaps or errors in the con-
before starting. Otherwise, you will For additional guidance, please contact the tract document, providing a baseline
be entering a great deal of data at the contracts department (or legal, or both). for measuring performance as it
beginning that will later be replaced. progresses, and serving as a clear
Be extremely careful about when con- Each page of the matrix should then roadmap during the close-out phase.
tract provisions are applicable. Even contain a reminder in the footer, such A well-prepared contract compliance
if a contract clause has been replaced as, “This document is subject to the matrix is an incredibly useful tool
or removed, it is possible that at some limitations contained on the cover. for contract administrators.
point in performance that language This is a synopsis. Rely only on the Once you are accustomed to a matrix,
was controlling. For this reason, it is official contract document for complete you will wonder how you ever man-
sometimes practical to add a heading, accuracy.” You should also be sure to aged without one. The simple exercise
indicating the period of applicability include whatever proprietary marking of preparing a matrix will familiarize
for certain clauses. your management has requested, as you with the contract like no other
In larger cost-type contracts, you discussed previously. exercise. And, when you can go back
will have a considerable number of to your customer with helpful infor-
funding modifications. If that is truly Reality Check: Proofread mation about gaps in the contract or
all that appears, there is generally no Get several sets of eyes on the matrix. can remind a manager of a due date
useful purpose in trying to capture Find a detail-oriented copy editor. before it is past, you will become
them in a matrix. Finance should Do whatever it takes to make sure the hero in their eyes that the rest
have their own mechanism for identi- that the matrix is validated against of us already know that you are! CM