Professional Documents
Culture Documents
MS Project Actual Vs Planned % Complete - NIK'S PROJECTS
MS Project Actual Vs Planned % Complete - NIK'S PROJECTS
MS Project Actual Vs Planned % Complete - NIK'S PROJECTS
Cart Checkout My account Shop About Contact
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 1/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Search …
Subscribe on YouTube
About NiksProj…
NiksProj…
00:00 00:54
Posted by niksprojects
Subscribe
In MS Project there is no default field available to calculate the Planned
% complete or the Baseline % completed. In this tutorial I will explain
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 2/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
MS Project stores the duration in minutes, so in order to use the PMBOK 6th Edition PDF
niksprojects.com/product/pmb
duration in days in our calculations create a customized number field ok-…
How to do it: In MS Project, right click any column and select insert
column. Then select field name as ‘Number 1′ and assign title as
“Duration in Days”. Then right click the newly inserted column and
select ‘Customize Fields’. On the custom attributes click on the radio
button ‘Formula’ and type in the formula as below. In the next section
click ‘Use Formula’ and then click OK. Embed View on Twitter
Formula: Val(ProjDurConv(Duration, pjdays))
Syntax: ProjDurConv( expression, durationunits )
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 3/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Based on the start date of the project and the status date, calculate
the days elapsed. This is required to calculate the percentage.
How to do it: In MS Project, right click any column and select insert
column. Then select field name as ‘Number 2′ and assign title as
“Elapsed Days”. Then right click the newly inserted column and select
‘Customize Fields’. On the custom attributes click on the radio button
‘Formula’ and type in the formula as below. In the next section click
‘Use Formula’ and then click OK.
Formula: IIf(ProjDateDiff(Start,[Status
Date])/480>=Val(ProjDurConv([Baseline
Duration],pjDays)),Val(ProjDurConv([Baseline
Duration],pjDays)),IIf(DateDiff(“d”,[Baseline Start],[Status Date])
<=0,0,ProjDateDiff(Start,[Status Date])/480))
Syntax: IIf( expr, truepart, falsepart )
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 4/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
condition is false, it means that the duration is still not completed and
we need to compute the elapsed days. But if the elapsed working days
is 0 or negative (which means the planned task is not yet started) we
need to set the elapsed days as 0. Hence you see another ‘If’ condition
in the false part of the first ‘If’ condition.
How to do it: In MS Project, right click any column and select insert
column. Then select field name as ‘Number 3′ and assign title as
“Planned Percent”. Then right click the newly inserted column and
select ‘Customize Fields’. On the custom attributes click on the radio
button ‘Formula’ and type in the formula as below. In the next section
click ‘Use Formula’ and then click OK.
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 5/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Formula: Number2/Number1
Syntax: Division (Math)
How to do it: In MS Project, right click any column and select insert
column. Then select field name as ‘Text 1′ and assign title as “Planned
% Complete”. Then right click the newly inserted column and select
‘Customize Fields’. On the custom attributes click on the radio button
‘Formula’ and type in the formula as below. In the next section click
‘Use Formula’ and then click OK.
Syntax: Format( expression[, format[, firstdayofweek[, firstweekofyear]]]
) all in ‘[‘ are optional..
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 6/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Formula Explanation: Format the Number3 field as text and adds % sign
at the end.
Hope this helps and let me know other ways of arriving at the planned
% complete.
* indicates required
Email Address *
First Name
Last Name
Subscribe
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 7/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Share this:
Twitter Facebook
Like this:
Like
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 8/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
114 comments
« « Older Comments
Lebs says:
January 26, 2019 at 3:18 pm
if you are using hours units instead of days, which parameters do you
change in the second formula?. I just replaced days with hours and my
calculation are not correct
Loading...
Reply
Why yke the planned percent doesn’t same with the % complete that have
in ms project?the planned % I just follow your step but the value are not
same with the % complete.
Loading...
Reply
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 9/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Ginny says:
August 5, 2019 at 2:46 am
I got the same problem, even the project is on schedule, there exists a
difference between planned % and actual %. Did you know the solution?
thanks in advance.
Loading...
Reply
Sandra says:
April 15, 2019 at 1:21 pm
Does any body knows how to fix the formula for the Milestones that is still
appears #ERROR at the elapsed days column?
Loading...
Reply
Brian says:
June 20, 2019 at 4:19 am
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 10/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Loading...
Reply
Joe says:
November 12, 2019 at 9:44 am
I used this.
IIf(Number2=0,0,Number2/Number1)
Loading...
Reply
amalik says:
April 5, 2020 at 10:14 am
Loading...
Reply
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 11/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
BEN says:
April 28, 2019 at 11:46 am
Hi, Nik.
Appreciate you can show in formula on how to resolve the error occur for
milestone due to divide by zero.
Loading...
Reply
Alfred says:
January 14, 2020 at 2:58 am
Loading...
Reply
Hullo Nik, I am receiving a syntax error in step2 on the formula below – the
syntax error occurs on the “d” – can you please assist:
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 12/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
IIf(ProjDateDiff(Start,[Status Date])/480>=Val(ProjDurConv([Baseline
Duration],pjDays)),Val(ProjDurConv([Baseline
Duration],pjDays)),IIf(DateDiff(“d”,[Baseline Start],[Status Date])
<=0,0,ProjDateDiff(Start,[Status Date])/480))
Loading...
Reply
Loading...
Reply
niksprojects says:
August 7, 2019 at 8:50 am
Loading...
Reply
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 13/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Loading...
Reply
manpex says:
May 28, 2019 at 9:52 am
Loading...
Reply
Wan says:
June 16, 2019 at 9:27 pm
Hi Nik,
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 14/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Wan
Loading...
Reply
Fabian says:
July 25, 2019 at 1:59 pm
Thanks for the post but It does not work (Step 2 #Error)
Loading...
Reply
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 15/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
niksprojects says:
August 7, 2019 at 8:51 am
Loading...
Reply
Samarth says:
August 10, 2019 at 3:44 am
Hi Nik, I just tried your formula but it is showing me lot of >100% and <0%
values against activities. How can I fix that? Also, how did you arrive at 480
as denominator in 2nd formula.
Loading...
Reply
zam says:
September 17, 2019 at 12:47 pm
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 16/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Loading...
Reply
Loading...
Reply
Sam says:
August 27, 2019 at 2:20 am
Hi Nick, wondering if you can help please. all I get is error codes in each
column. can you please advise
Loading...
Reply
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 17/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
grace says:
September 3, 2019 at 12:21 am
why is my Elapsed Days always 0? i put the status date to today already
Loading...
Reply
Dora says:
September 19, 2019 at 11:24 pm
Hi all,
Loading...
Reply
raiha says:
September 24, 2019 at 10:40 pm
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 18/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Hi nick, im having a problems with elapsed days exceed with planned days.
How to correct this?.
Thanks
Loading...
Reply
Ashleigh says:
October 17, 2019 at 2:12 pm
How can we managed a task that has elapsed more days than planned. I
have a task that was originally 11 days duration. Currently there are 15
days elapsed but task is only 33% complete (Actual). The formula shows
that the planned % complete should be 136%. Is there a way to change
formula to put in 100% if output is greater than 100%? Thank you
Loading...
Reply
Adela says:
November 13, 2019 at 12:37 am
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 19/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
I get ERROR for milestones, can you tell me if you know how to correct
that?
Loading...
Reply
Sushanta says:
November 25, 2019 at 4:17 am
I have used the formula for planned % complete , but I am getting error
Like
Reply
SB says:
December 2, 2019 at 3:52 pm
Does the planned percent complete always show way less than the %
complete if you are 100% completed with the tasks shown by date?
Basically we are exactly where we are supposed to be in the project, but
show 83% completed to a plan of 56%…? Makes no sense. Can you please
help?
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 20/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Like
Reply
hi i want to make this on actual start- actual finish how can i do that?
Like
Reply
IIf((Abs(IIf([Number1]=0,0,
([Number2]/[Number1]))))>=100,100,IIf((Abs(IIf([Number1]=0,0,
([Number2]/[Number1]))))<=0,0,(Abs(IIf([Number1]=0,0,
([Number2]/[Number1]))))))
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 21/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Enjoy!!!
Loading...
Reply
IIf((Abs(IIf([Number4]=0,0,
([Number5]/[Number4]))))>=1,1,IIf((Abs(IIf([Number4]=0,0,
([Number5]/[Number4]))))<=0,0,(Abs(IIf([Number4]=0,0,
([Number5]/[Number4]))))))
Like
Reply
douglas says:
January 7, 2020 at 11:57 am
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 22/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Like
Reply
how can i on the formula window click the option “Roll up to summary
level” to get the correct percentages for the summary tasks? i cant find Roll
up to summary level. please help me
Like
Reply
Anurag says:
February 27, 2020 at 1:07 am
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 23/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Original – IIf(ProjDateDiff(Start,[Status
Date])/480>=Val(ProjDurConv([Baseline
Duration],pjDays)),Val(ProjDurConv([Baseline
Duration],pjDays)),IIf(DateDiff(“d”,[Baseline Start],[Status
Date])=Val(ProjDurConv([Baseline
Duration],pjDays)),Val(ProjDurConv([Baseline
Duration],pjDays)),IIf(DateDiff(“d”,[Baseline Start],[Status Date])
<=0,0,ProjDateDiff([Baseline Start],[Status Date])/480))
Like
Reply
« « Older Comments
Leave a Reply
Enter your comment here...
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 24/25
4/11/2020 MS Project Actual vs Planned % Complete – NIK'S PROJECTS
Powered by WordPress.com.
https://niksprojects.com/2016/06/05/ms-project-actual-vs-planned-complete/ 25/25