PROTOCOL Date:
A Joint checking has been done with Switchyard operation Team as mentioned in below
Equipment Details
Interlock Details:
1. Interlock: As per scheme Breaker will be closed after satisfying following conditions.
a) 89 A in closed position
b) 89 B in closed position
c) CB-52 in open position
d) Master Trip GRP- 86A in reset condition
e) Master Trip GRP- 86B in reset condition
f) Busbar Protection healthy condition
g) Lock-out Relay in reset condition
2. Operational Check
2.1 From Local
a) Satisfying all above close interlocks
b) Put Local / Remote Selection Switch in Local Mode
c) Ensure Line Isolator 89L in open Position & Earth Switch 89LE in close position
d) Switch on all AC / DC MCB at Breaker MK
e) Ensure Breaker Springs are charged in all 3 Phases
f) SF6 Pressure is healthy
g) Check counter reading before operation
h) Take trial through T-N-C Switch for close / Trip Operation
i) Check Breaker Feedback at SCADA
j) Check counter reading after operation
Remarks If any: