Early Age Strength Characteristics of Emulsified Base Layers PDF

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

Early-Age Structural Properties of Base

Material Treated with Asphalt Emulsion


Tyler Quick and W. Spencer Guthrie

The objectives of this research were to investigate the early-age structural asphalt emulsion (6). The application of asphalt emulsion is an easy
properties of base materials stabilized with asphalt emulsion and to method by which to add asphalt binder to the road base during the
assess the rate at which emulsion-treated base (ETB) design properties reclamation process. The resulting product, emulsion-treated base
are achieved. Three experimental sections were established along a (ETB), may then be surfaced with a wearing course for trafficking.
pavement reconstruction project near Saratoga Springs, Utah. Field Several studies have been performed to assess the long-term strength
tests were performed to assess the structural properties of the ETB of ETB in the field. In pavement tests performed 6 months or more
immediately after construction and at 2, 3, 7, and 14 days; 4 months; and after pavement reconstruction, Illinois Department of Transportation
1 year. Measured values were plotted against time to determine trends personnel measured resilient modulus values as high as 200 ksi, and
in ETB strength development and to determine pavement capacity. researchers at the Texas Transportation Institute measured resilient
Modulus values were consistently low in all three sections during the modulus values as high as 275 ksi (1, 2). Although these studies deter-
first 2 weeks after construction, increased dramatically by 4 months, mined that long-term ETB strengths are sufficient to support even
and then decreased considerably by 1 year. In the first 2 weeks after heavy traffic loads, little research has been performed to determine
construction, the average ETB structural coefficient was 0.04. Only two the rate at which ETB develops strength in the period between
of the three sections reached the design structural coefficient of 0.25, construction and the time that ETB design properties are achieved.
which occurred after approximately 3 months; however, the average The ability of a pavement to withstand early trafficking depends on
structural coefficient measured for all three sections after 1 year of the strength developed in the pavement system immediately after
curing, which included a winter, was only 47% of the design strength. construction. If the strength of the pavement system is not sufficiently
The results of this research showed that, while pavement capacity was high before traffic is introduced, early trafficking will cause permanent
sufficient at 4 months, it was severely reduced during the first 2 weeks deformation in the treated layer, compromising long-term pavement
and at 1 year. Trafficking under these reduced capacities would be performance. Furthermore, if the ETB does not reach design strengths
expected to greatly compromise long-term pavement performance. for an extended period of time, continued trafficking may cause
For this reason, trafficking of materials similar to those investigated premature failure of the pavement system. For these reasons, an
in this research is not recommended during at least the first 2 weeks understanding of early strength development in ETB is vital for
after construction. pavement engineers interested in utilizing FDR in conjunction with
asphalt emulsion treatment.
The objectives of this research were, therefore, to investigate the
Over the past few decades, full-depth reclamation (FDR) has become early-age structural properties of base materials stabilized with asphalt
increasingly prevalent in the transportation industry as a means of emulsion and to assess the rate at which ETB design properties are
rehabilitating and reconstructing flexible pavements (1, 2). The FDR achieved. The following sections provide background information,
process involves recycling the existing pavement structure by pul- describe the procedures, present the results, and offer conclusions
verizing and mixing the in-place asphalt layer into the upper portion and recommendations pertaining to this study.
of the existing base to form a new base layer. FDR provides a feasible
solution to problems such as pavement geometry restrictions, lack
of quality aggregate, and the cost of asphalt disposal (3); however,
BACKGROUND
the reclamation process can cause a reduction in the strength of the
base layer because it both disturbs the existing base material and mixes The following sections provide background information on ETB
reclaimed asphalt pavement (RAP) into it. The addition of RAP has construction processes, ETB strength gain, construction and environ-
been shown to decrease the bearing capacity of some base materials mental factors affecting ETB performance, and the effects of early
and, possibly, to impede proper compaction of the base material trafficking.
(4, 5). For these reasons, stabilization is often needed to improve the
structural properties of reclaimed base materials (5). One product
that has been used in road stabilization since the early 1900s is ETB Construction Processes

Department of Civil and Environmental Engineering, Brigham Young University, The construction process for FDR with emulsion stabilization begins
Provo, UT 84602. Corresponding author: W. S. Guthrie, guthrie@byu.edu. with the pulverization and blending of the existing asphalt layer and
a specified thickness of the underlying base material. Partial milling
Transportation Research Record: Journal of the Transportation Research Board,
No. 2253, Transportation Research Board of the National Academies, Washington,
of the existing asphalt layer may be needed before reclamation to
D.C., 2011, pp. 40–50. ensure uniform RAP content within the reclaimed base layer (7 ).
DOI: 10.3141/2253-05 The reclaimed material is then graded and compacted to approximate

40
Quick and Guthrie 41

final elevations before the emulsion treatment is applied (8). Water Construction Factors Affecting ETB Performance
can be added during the initial reclamation process to facilitate a
more uniform distribution of the emulsion (9, 10). Emulsion is then Several construction factors can affect the performance of ETB
injected and mixed into the base material with a reclaimer. Additional materials, including the gradation of the reclaimed base material, the
water can be added during the injection to attain the optimum mois- strength of the subgrade, the degree of ETB compaction, and the
ture content of the ETB material. The treated base is then com- total moisture content (TMC) of the ETB. Where gradation is
pacted with sheepsfoot rollers or vibratory breakdown rollers. After concerned, the fraction of material passing the No. 200 sieve should
compaction, the ETB is graded and finish rolled. Paving of the be less than 25% to avoid weakening the ETB (6, 7). Therefore, the
ETB is often delayed by as much as 2 weeks after construction to inclusion of excessive portions of fine-grained subgrade soils into the
allow moisture to escape from the ETB during the early curing base material during the reclamation process should be avoided (1).
process (9–11); the maximum allowable ETB moisture contents The subgrade strength is especially important immediately after
before paving are typically 2% to 3% (10). On some projects, traffic construction (2). The stabilized base layer is fairly weak after pul-
is reintroduced immediately after the final compaction of the ETB verization and reclamation, so the ability of the subgrade to withstand
layer, even before paving. If no visually apparent deflections are construction and early traffic loads greatly affects the support offered
observed under a heavy truck, the ETB layer is usually judged to be to the ETB. The strength of the subgrade also affects the degree of
ready for traffic (9, 10). compaction possible in the ETB (7 ).
The degree of ETB compaction affects strength development in
the ETB. Compaction can contribute to the initial destabilization
ETB Strength Gain of the asphalt emulsion but also affects the rate of curing within the
ETB. The percentage of voids remaining after compaction should
Asphalt emulsion is typically considered to be an oil-in-water be low enough to prevent water ingress but high enough to allow
emulsion, meaning that it consists of asphalt particles that are sus- water to evaporate from the emulsion during the curing process.
pended in water through the use of an emulsifier (6, 12). Emulsifiers The TMC includes the in situ moisture that existed before the
create charges on the surfaces of the asphalt particles that cause emulsion injection and the water added during the injection process,
them to repel one another, thereby stabilizing the particles within the including the water present in the emulsion. If the TMC is not within
emulsion. Asphalt emulsions typically contain 25% to 60% water, an acceptable percentage of the optimum moisture content for the
40% to 75% bitumen, and 0.1% to 2.5% emulsifier (12). Solvents ETB material, compaction of the ETB layer to the specified density
are sometimes added to modify emulsion properties and behavior. The may not be possible. If the TMC approaches saturation, compaction
specific composition of an asphalt emulsion determines the emulsion of the ETB can be extremely difficult, if not impossible. If in situ
characteristics, such as reactivity, viscosity, and stability. moisture contents are such that the addition of emulsion will increase
The process of curing involves the gradual evaporation and the TMC to unacceptable values, the reclaimed material must be
expulsion of water from the emulsion. The curing of ETB begins allowed to dry before the emulsion can be added (11).
when the emulsion starts to destabilize due to compaction and water
evaporation (11). During compaction, the asphalt particles are
forced together, causing them to overcome static repulsion and Environmental Factors Affecting ETB Performance
begin to coalesce into larger asphalt droplets. The asphalt droplets
eventually become large enough to bind the aggregate particles Environmental factors such as temperature and moisture can also
together. The rate of curing depends on several factors, including affect the performance of ETB materials. Because of the viscoelastic
the reactivity of both the emulsion and the aggregate, the emulsion nature of asphalt, the structural properties of ETB are affected by
chemistry, and environmental factors, such as wind speed, humidity, ETB temperature (6, 13, 19). As pavement temperature increases,
and temperature (11, 13). Compaction or trafficking of the ETB the strength of the ETB layer decreases due to the softening of the
can increase the rate of curing by forcing the asphalt particles closer asphalt binder (2, 20).
together (12). Several studies have found that, during the early stages of curing,
Curing to the design strength may require a few weeks to a couple excessive moisture contents from rain or other water sources can
of years, depending on the properties of the emulsion used (11–13). cause pavement weakness and even failure (2, 21). After the emulsion
ETB exhibits low strengths immediately after construction due to has fully cured, the ability of moisture to affect the pavement system
the nature of uncured emulsion. One study found that the stiffness is limited, but high moisture contents in the period immediately after
of ETB after compaction was actually lower than in the reclaimed construction can slow the curing process and lower the early strength
material before the emulsion treatment (14); however, ETB layers of the ETB (11).
have been found to exhibit large increases in resilient moduli during Ambient air temperature and relative humidity also affect the rate
the first 28 days of curing (15, 16). Others have measured a 300% at which ETB will cure because they affect water evaporation rates.
increase in resilient moduli during the first 10 months (17 ). The Low temperatures and high humidity reduce evaporation rates, thus
Asphalt Institute suggests that ETB remains relatively weak dur- preventing water from being removed from the ETB and slowing the
ing the first month after construction, stiffens dramatically during curing rates (11).
the next few months, and then levels out after approximately 6 months.
The Asphalt Institute has also found that curing times longer than
6 months do not significantly increase ETB strength (18). Other Effect of Early Trafficking on ETB Performance
studies have found that ETB can take as long as 2 years to fully cure
(13). These results show that, although the final strength of ETB The degree to which the emulsion has cured has a large effect on
can be very high, the ETB layer remains fairly weak immediately the stiffness and strength of the ETB in the first 2 years after con-
after construction, while the emulsion is curing. struction (13). During this time, permanent deformation is usually
42 Transportation Research Record 2253

the primary failure mechanism of ETB layers because the curing The DCP testing was performed in general accordance with
process has not yet fully been completed (12). Because of the nature ASTM D6951 (Standard Test Method for Use of the Dynamic Cone
of this failure mechanism, the stiffness of the ETB will, in large part, Penetrometer in Shallow Pavement Applications). In this research,
govern its ability to support traffic loads (19). In current pavement the DCP tests were performed to a depth of 31.5 in., which allowed
design methods, the stiffness of a pavement layer is directly tied to average penetration rates for both the ETB and the subgrade layers
pavement structural capacity. If the layer modulus is low, pavement to be determined. One test was performed at each station during
structural capacity is significantly reduced. each series of testing.
One of the stated benefits of ETB is that the pavement can be On the day of construction, samples of the reclaimed base material
opened to traffic within hours of construction (1, 2, 9–11, 22); were removed from each test station before and after the emulsion
however, some ETB projects have experienced severe rutting prob- treatment. The samples of untreated material were bagged and
lems during early pavement life due to the adverse effects of traffic transported to the Brigham Young University Highway Materials
on the weak pavement (2, 22). One study found that the life of a Laboratory for sieve, moisture content, and burn-off analyses. The
pavement comprised of an ETB layer increases by more than 400% samples of the treated material were compacted on site with the
when traffic is withheld from the pavement for 48 hours after con- modified Proctor compaction protocol in general accordance with
struction, compared with when traffic is reintroduced within 2 hours ASTM D1557 (Standard Test Methods for Laboratory Compaction
of construction (22). Characteristics of Soil Using Modified Effort [56,000 ft-lbf/ft3
(2,700 kN-m/m3)]) Method B. This method involved compaction of
the ETB material in 4-in.-diameter molds in five lifts of 25 blows each.
PROCEDURES Four or five samples were created for each of the test stations. At the
laboratory, these samples were subjected to unconfined compressive
The test site chosen for this research was a section of Redwood Road strength (UCS), moisture content, and burn-off analyses.
(SR-68) located just north of Saratoga Springs, Utah. This section
of Redwood Road was part of a multiphase reconstruction project.
The pavement design applied to the test section included the use of Laboratory Procedures
1 in. of open-graded surface course on 5 in. of hot-mix asphalt (HMA)
on 8 in. of ETB. Construction of the Redwood Road test area occurred Material characterization testing was conducted on the field-
in June 2009. The test section was neither paved nor opened to sampled base material from each test station to determine the average
regular traffic for 2 weeks after construction so that it could dry after properties of each of the three test sections. A sieve analysis was
a couple of rain storms. performed on a representative sample of the untreated material in
The experimental area was divided into three 800- × 24-ft test general accordance with ASTM D422 (Standard Test Method for
sections, labeled as Sections A, B, and C. Ten individual test stations Particle-Size Analysis of Soils) to determine the soil classification
were established in each of the three sections. These stations were of the untreated material sampled from each test section. The material
randomly located across each section. The following sections of the was determined to be nonplastic, so Atterberg limits could not be
paper detail the field procedures, laboratory procedures, and data determined. A burn-off test was performed on the untreated and treated
analyses performed during the investigation. materials in general accordance with ASTM D6307 (Standard Test
Method for Asphalt Content of Hot-Mix Asphalt by Ignition Method).
The results of these tests were used to determine the asphalt content
Field Procedures of the reclaimed base material at each test station before and after
the emulsion injection. The amount of emulsion injected at each sta-
Field testing was conducted over the course of the project to char- tion was then calculated as the measured difference in the asphalt
acterize the in situ structural properties of the ETB layer. The field content of the base material before and after the emulsion treatment,
instruments utilized in this research included the portable falling divided by the design asphalt content of 64% by weight of the
weight deflectometer (PFWD) and the dynamic cone penetrometer emulsion.
(DCP). Testing with these instruments was performed several times UCS tests were performed in general accordance with ASTM
after the construction of the pavement sections. The first series of D1633 (Standard Test Methods for Compressive Strength of Molded
field tests began within 30 min of the final compaction of the ETB Soil–Cement Cylinders) on one emulsion-treated sample from each
layer. Additional tests were performed at 2, 3, 7, and 14 days, 4 months, test station at 7 days, 28 days, 3 months, and 1 year after construction.
and 1 year. The stations tested at 4 months and 1 year were limited Samples were allowed to cure at room temperature in an open-air
to those in the right lane due to constraints associated with traffic condition before testing; they were then capped with gypsum and
control. subjected to UCS testing at a strain rate of 0.05 in./min. UCS values
The PFWD test was performed in general accordance with were plotted to develop strength-gain curves for the ETB under
ASTM E2583 (Standard Test Method for Measuring Deflections laboratory curing conditions.
with a Light Weight Deflectometer). The PFWD system utilized a
44.1-lb weight dropped 30 in. onto a 7.87-in.-diameter load plate.
Three sensors were used to measure pavement deflection at radial Data Analysis
distances of 0, 12, and 24 in. from the point of impact. A seating load
was applied before the actual measurements were taken to ensure The soil properties measured in the field and during laboratory testing
that the load plate was properly situated on the pavement surface. were analyzed to determine equivalent modulus values for the ETB
Three PFWD tests were performed at each station during each series layer. Moduli were determined from the PFWD test with BAKFAA
of testing, and, in each case, the average deflections were used to backcalculation software (23). The original pavement design layer
backcalculate the modulus of each layer of the pavement system. thicknesses were used during backcalculation; these thicknesses
Quick and Guthrie 43

were confirmed through DCP testing. A Poisson’s ratio of 0.35 and remained unpaved for 2 weeks after construction, the analysis of the
full interface bonding were assumed for all backcalculations. 2-week capacity was performed for two scenarios—one in which
DCP penetration rates were used with Equations 1 and 2 to the ETB was paved and one in which it was unpaved—to provide
determine ETB modulus values (24): an understanding of pavement strengths under both conditions. All
analyses of pavement capacity after 2 weeks were performed with
292 the assumption that the ETB was paved.
CBR = (1)
PR1.12

where CBR is the California bearing ratio (%) and PR is the RESULTS
penetration rate (mm/blow).
The following sections describe the results of the laboratory and
MR = 2 ,550 i CBR 0.64 (2) field testing, as well as the results of the data analyses.

where MR is the resilient modulus (psi).


Laboratory Results
AASHTO correlation charts were used to determine an equivalent
structural coefficient (a2) for the ETB modulus values determined The results of the sieve analysis indicated that all three sections could
during testing (18). The structural coefficients were plotted against be classified as A-1-a and GW, under the AASHTO and Unified Soil
time to determine trends in ETB strength development and to deter- Classification System methods, respectively. A minimal variation in
mine the time at which the ETB had reached the design structural aggregate gradation existed between the three test sections.
coefficient value of 0.25. The results of the burn-off tests are shown in Table 1. The asphalt
The structural capacity of the pavement in each testing period was content before treatment was fairly consistent across the three sections,
calculated with the AASHTO flexible pavement design method. The implying that they had comparable RAP contents. However, the
structural coefficient of the ETB layer measured in each time period variability in the emulsion content added to each section during
was used to calculate the total structural number of the pavement treatment was higher. The design emulsion content, specified as a
system, as shown in Equation 3 (18): percentage of asphalt, water, and emulsifier by dry weight of reclaimed
base material, was 4.0% for the ETB layer. Sections A and B both had
SN = a1 i D1 + a2 i D2 i m2 (3) emulsion contents higher than the design specification, and Section C
had an emulsion content lower than the design specification.
where Results of the UCS testing are shown in Figure 1. Sections B and C
had nearly identical values; Section A had consistently lower values.
SN = structural number, The reduced compressive strength of the samples from Section A
a1 = structural coefficient of the HMA layer, may have been due to the higher amount of emulsion, which could
D1 = thickness of the HMA layer, act as a lubricant. The average UCS values for all three sections were
a2 = structural coefficient of the ETB layer, 30, 96, 145, and 179 psi at 7 days, 28 days, 3 months, and 1 year,
D2 = thickness of the ETB layer, and respectively. Although no direct correlation between UCS and
m2 = drainage coefficient of the ETB layer. modulus values for ETB materials was identified in the literature
The allowable number of passes of equivalent single-axle loads review performed in this research, the resilient modulus determined
(ESALs) before failure was then computed with Equation 4 (18): under laboratory conditions would be expected to exhibit a similar
pattern of strength development. The percentage of 1-year ETB
ΔPSI strength developed after 7 days, 28 days, and 3 months was 17%,
log 54%, and 80%, respectively. The ETB compressive strength was
log Wt18 = Z R S0 + 9.36 log ( SN + 1) − 0.20 + 2.7
very low immediately after compaction and remained below 50% of
1, 094
0..4 + the 1-year strength during at least the first 2 weeks.
(SN + 1) 5.19

+ 2.32 log MR − 8.07 (4) Field Results

where Results from the PFWD and DCP tests are shown in Table 2. PFWD
Wt18 = allowable ESALs before pavement failure, results are given as modulus values backcalculated from measured
ZR = standard normal deviate corresponding to a specified
level of reliability,
S0 = standard deviation, TABLE 1 Burn-Off Test Data
ΔPSI = allowable change in present serviceability index over
Asphalt Content Emulsion Added
pavement life, and Before Treatment (%) During Treatment (%)
MR = effective roadbed soil resilient modulus (psi).
Section Average SD Average SD
To calculate the structural number, a structural coefficient of
0.40 was used for the HMA layer, and a drainage coefficient of 1.0 A 5.0 0.6 4.8 2.0
was used for the ETB layer. To calculate the allowable number of B 4.5 0.5 4.1 1.1
ESALs, a reliability level of 95%, a standard deviation of 0.45, and C 4.8 0.4 3.3 1.2
a change in present serviceability index of 2.0 were used, with a
design subgrade modulus of 11.4 ksi. Although all three test sections NOTE: SD = standard deviation.
200
180

Compressive Strength (psi)


160
140 Section A
120
100 Section B
80
Section C
60
40 Average
20
0
0 100 200 300 400
Time (days)

FIGURE 1 Average unconfined compressive strength results for each section.

TABLE 2 PFWD and DCP Test Data

DCP

Penetration Rate
PFWD Modulus (ksi) (mm/blow) Modulus (ksi)
Curing Time
(days) Average SD Average SD Average SD

Section A
1 21.7 4.4 6.4 1.2 26.1 3.7
2 22.0 3.6 6.7 1.3 25.2 3.8
3 31.2 5.9 4.3 0.8 34.7 4.8
7 39.5 8.9 3.2 0.9 43.2 7.1
14 36.6 11.0 3.4 0.5 40.5 4.0
113 342.4 90.1 1.1 0.6 — —
365 85.4 11.9 1.4 0.1 — —
Section B
1 13.8 4.1 9.5 2.0 19.6 3.0
2 18.9 3.3 8.0 1.1 21.9 2.1
3 22.9 4.5 6.7 0.6 24.8 1.7
7 23.4 4.5 5.9 1.1 27.5 3.3
14 27.2 4.0 5.4 0.8 29.1 3.0
113 339.9 87.4 1.0 0.3 — —
365 94.3 11.1 1.8 0.3 — —
Section C
1 17.2 3.1 9.2 1.1 19.9 1.8
2 22.0 4.7 8.4 1.2 21.2 2.2
3 28.7 5.2 6.3 0.7 25.9 2.3
7 30.4 6.1 4.6 0.5 32.7 2.9
14 35.5 6.3 4.1 0.6 35.6 4.0
113 176.9 29.3 1.2 0.3 — —
365 89.2 8.2 2.0 0.1 — —
Average
1 17.6 3.9 8.4 1.4 21.9 2.8
2 21.0 3.9 7.7 1.2 22.8 2.7
3 27.6 5.2 5.8 0.7 28.5 2.9
7 31.1 6.5 4.6 0.8 34.5 4.4
14 33.1 7.1 4.3 0.6 35.1 3.7
113 286.4 68.9 1.1 0.4 — —
365 89.6 10.4 1.7 0.2 — —

NOTE: — = penetration rates below recommended range for the equations used.
Quick and Guthrie 45

50
45

ETB Resilient Modulus (ksi)


40
Section A
35
30 Section B
25
Section C
20
15 Average
10
5
0
0 5 10 15
Time (days)
(a)

50
45
ETB Resilient Modulus (ksi)

40
Section A
35
30 Section B
25
Section C
20
15 Average
10
5
0
0 5 10 15
Time (days)
(b)

FIGURE 2 ETB resilient modulus values during first 2 weeks: (a) PFWD test results and
(b) DCP test results.

deflections, and DCP results are given as penetration rates and cor- 9% and 31%, respectively, of the average ETB modulus at 4 months.
responding modulus values. Modulus values were not determined These trends were confirmed by the DCP penetration rates: the av-
from the DCP tests at 4 months and 1 year because the penetration erage penetration rates were 4.3, 1.1, and 1.7 mm/blow at 2 weeks,
rates measured in those tests were below the recommended range 4 months, and 1 year, respectively.
for the given equations (25). The average modulus values obtained Much of the increase in modulus values observed at 4 months
for each section from PFWD and DCP testing in the first 2 weeks of was probably due to the curing of the emulsion in the base, but the
testing are shown in Figure 2. With a few exceptions, the PFWD lower temperatures experienced during late fall may also have
and DCP tests produced similar curves within each section, although caused an apparent increase in stiffness. Although the air temper-
the DCP modulus values were, in general, slightly higher than the ature of 57°F at 4 months was only slightly different than the air
PFWD modulus values. Overall average modulus values for this temperature of 64°F at 2 weeks, the difference in subsurface tem-
2-week period were 26.0 and 28.6 ksi, determined from the PFWD peratures was most likely greater due to the onset of colder nights
and DCP data, respectively. by 4 months. Section C had a lower emulsion content, so it might
The average ETB modulus values obtained for each section from not have been as affected by colder temperatures, possibly causing
PFWD testing during the entire testing period are shown in Figure 3. it to exhibit lower strengths at 4 months; however, at 1 year, all three
The PFWD modulus values were consistently low in all three sections sections had approximately the same modulus value. The modulus
during the first 2 weeks, increased dramatically by 4 months, and decreased significantly between 4 months and 1 year despite the
then decreased considerably by 1 year. The average ETB moduli were additional curing of the emulsion that may have occurred during
286.4 and 89.6 ksi at 4 months and 1 year, respectively. Therefore, the this time. Although a comparatively high air temperature of 80°F
average ETB moduli during the first 2 weeks and at 1 year were only may have contributed to the apparent reduction in ETB strength at
46 Transportation Research Record 2253

400
October 2009
350

300

ETB Modulus (ksi)


Section A
250
Section B
200
Section C
150 June 2010
Average
100

50
June 2009
0
0 100 200 300 400
Time (days)
(a)

0.35
October 2009
ETB Structural Coefficient (a2)

0.30

0.25 Section A

0.20 Section B

June 2010
0.15 Section C

0.10 Average

0.05
June 2009
0.00
0 100 200 300 400
Time (days)
(b)

FIGURE 3 ETB properties during first year: (a) resilient modulus values and
(b) layer coefficients.

1 year, freeze–thaw damage may also have occurred in the layer which behaved similarly, reached a structural coefficient of 0.25
during the winter. after approximately 3 months and actually exceeded design values
Although the trend shown in Figure 3 may not account for the by about 0.05 after 4 months; however, after 1 year, Sections A and B
fluctuations in ETB strength that occurred between 2 weeks and had much lower structural coefficients: 0.11 and 0.12, respectively.
4 months or between 4 months and 1 year, the results still show that Section C did not ever reach a structural coefficient of 0.25. At
the sections exhibited strengths at least as high as those measured at 4 months, the ETB structural coefficient in Section C was only 0.21,
4 months and that those strengths were significantly reduced by 1 year. and after 1 year it had decreased to 0.12. For all three sections, the
The laboratory UCS data shown in Figure 1 depict the trend that would average structural coefficient measured after 1 year of curing was
have been expected in the field without environmental effects. only 47% of the design value. These results show that ETB materials
similar to those investigated in this research should not be expected
to reach design values in the first few months after construction; this
Data Analysis conclusion is supported by the laboratory UCS results. Furthermore,
ETB materials may exhibit substantial decreases in stiffness after
The equivalent AASHTO structural coefficients of the ETB are shown the first winter in regions characterized by freeze–thaw cycling.
in Figure 3 for each section. Because modulus values were not deter- The design ESALs for this pavement were 10.9 million. However,
mined from the DCP penetration rates measured at 4 months and the number of allowable ESALs during the first 2 weeks for the
1 year, structural coefficients were determined only by the PFWD scenario in which the ETB was unpaved was calculated to be less than
modulus values. The design structural coefficient for the ETB layer 50,000, which is 0.5% of the design requirement. For the scenario
was 0.25, as indicated by the bold line. In the first 2 weeks after in which the ETB was paved immediately after construction, the
construction, the average ETB structural coefficients for Sections A, allowable ESALs were calculated to be 0.4 million, 14.5 million,
B, and C were 0.04, 0.03, and 0.04, respectively. Sections A and B, and 1.7 million at 2 weeks, 4 months, and 1 year, respectively. These
Quick and Guthrie 47

values were equivalent to 4%, 133%, and 16% of the design capacity. trafficking of materials similar to those investigated in this research
Although pavement capacity was sufficient at 4 months, it was severely is not recommended during at least the first 2 weeks after construction.
reduced during the first 2 weeks and at 1 year. Trafficking under Furthermore, these research results suggest that ETB stiffness can be
these reduced capacities would be expected to greatly compromise affected by temperature and moisture changes and that ETB materials
long-term performance and might cause premature failure of the may sustain freeze–thaw damage during the winter in cold regions.
pavement system. Further research on these topics is needed.

CONCLUSION ACKNOWLEDGMENT

The objectives of this research were to investigate the early-age The authors acknowledge the Utah Department of Transportation for
structural properties of base materials stabilized with asphalt emulsion funding this research.
and to assess the rate at which ETB design properties are achieved.
Three experimental sections were established along a pavement
reconstruction project near Saratoga Springs. Field tests were per- REFERENCES
formed to assess the structural properties of the ETB immediately
after construction and then at 2, 3, 7, and 14 days, 4 months, and 1. Hilbrich, S. L., and T. Scullion. Evaluation of Laboratory Mix Design
1 year. Measured values were plotted against time to determine and Field Performance of Asphalt Emulsion and Cement Stabilized Full-
Depth Reclamation Project in Texas. Presented at 87th Annual Meeting
trends in ETB stiffness development.
of the Transportation Research Board, Washington, D.C., 2008.
The average UCS measured in the laboratory for all three sections 2. Thompson, M. R., L. Garcia, and S. H. Carpenter. Cold In-Place Recycling
was 30, 96, 145, and 179 psi at 7 days, 28 days, 3 months, and 1 year, and Full-Depth Recycling with Asphalt Products. Illinois Center for
respectively. The percentage of 1-year ETB strength developed after Transportation, University of Illinois at Urbana–Champaign, March 2009.
7 days, 28 days, and 3 months was 17%, 54%, and 80%, respectively. 3. MacGregor, J. A. C., W. H. Highter, and D. J. DeGroot. Structural
Numbers for Reclaimed Asphalt Pavement Base and Subbase Course
Field-measured modulus values were consistently low in all three
Mixes. In Transportation Research Record: Journal of the Transportation
sections in the first 2 weeks after construction, increased dramatically Research Board, No. 1687, TRB, National Research Council, Washington,
by 4 months, and then decreased considerably by 1 year. The average D.C., 1999, pp. 22–28.
ETB moduli measured with the PFWD were 26.0, 286.4, and 89.6 ksi 4. Guthrie, W. S., A. V. Brown, and D. L. Eggett. Cement Stabilization of
during the first 2 weeks, at 4 months, and at 1 year, respectively, and Aggregate Base Material Blended with Reclaimed Asphalt Pavement.
In Transportation Research Record: Journal of the Transportation
the DCP penetration rates followed the same trend; the corresponding
Research Board, No. 2026, Transportation Research Board of the National
average penetration rates were 4.3, 1.1, and 1.7 mm/blow. Much of Academies, Washington, D.C., 2007, pp. 47–53.
the increase in modulus values observed at 4 months was probably due 5. Guthrie, W. S., D. A. Cooley, and D. L. Eggett. Effects of Reclaimed
to the curing of the emulsion in the base, but the lower temperatures Asphalt Pavement on Mechanical Properties of Base Materials. In Trans-
experienced during late fall may also have caused an apparent increase portation Research Record: Journal of the Transportation Research
Board, No. 2005, Transportation Research Board of the National Acad-
in stiffness. The modulus decreased significantly between 4 months
emies, Washington, D.C., 2007, pp. 44–52.
and 1 year despite the additional curing of the emulsion that may 6. Terrel, R. L., J. A. Epps, E. J. Barenberg, J. K. Mitchell, and M. R.
have occurred during this time. Although a comparatively high air Thompson. Soil Stabilization in Pavement Structures—A User’s Manual,
temperature of 80°F may have contributed to the apparent reduction Volume 2. Terrel, Epps, and Associates, Seattle, Wash., 1979.
in ETB strength at 1 year, freeze–thaw damage may also have 7. Collings, D., and H. Thompson. A Critical Appraisal of the Performance
occurred in the layer during the winter. of Foamed Bitumen and Bitumen Emulsion Treated Materials. Proc.,
9th Conference on Asphalt Pavements for Southern Africa, Gaborone,
In the first 2 weeks after construction, the average ETB structural Botswana, Sept. 2007, pp. 233–255.
coefficients for Sections A, B, and C were 0.04, 0.03, and 0.04, 8. Guthrie, W. S., and M. A. Rogers. Variability in Construction of
respectively. Sections A and B reached the design structural coeffi- Cement-Treated Base Layers: Material Properties and Contractor
cient of 0.25 after approximately 3 months; however, after 1 year, Performance. In Transportation Research Record: Journal of the Trans-
Sections A and B had structural coefficients of 0.11 and 0.12, portation Research Board, No. 2186, Transportation Research Board of
the National Academies, Washington, D.C., 2010, pp. 78–89.
respectively. Section C did not ever reach a structural coefficient 9. Finberg, C., D. Quire, and T. W. Thomas. Granular Base Stabilization
of 0.25. At 4 months, the ETB structural coefficient in Section C with Emulsion in Las Vegas, Nevada. Presented at 87th Annual Meet-
was only 0.21, and after 1 year it had decreased to 0.12. For all three ing of the Transportation Research Board, Washington, D.C., 2008.
sections, the average structural coefficient measured after 1 year of 10. Kroge, M., K. McGlumphy, and T. Besseche. Full Depth Reclamation
curing was only 47% of the design strength. with Engineered Emulsion in Fairburn, Georgia. In Transportation
Research Record: Journal of the Transportation Research Board, No. 2095,
The design pavement capacity was 10.9 million ESALs. The Transportation Research Board of the National Academies, Washington,
pavement capacity during the first 2 weeks for the scenario in which D.C., 2009, pp. 136–143.
the ETB was unpaved was calculated to be less than 50,000 ESALs, 11. Mulusa, W. K. Development of a Simple Triaxial Test for Characterising
which is 0.5% of the design capacity. For the scenario in which Bitumen Stabilised Materials. MS thesis. Department of Civil Engineer-
the ETB was paved immediately after construction, the pavement ing, University of Stellenbosch, Matieland, South Africa, Jan. 2009.
12. James, A. Overview of Asphalt Emulsions. In Transportation Research
capacity, in terms of millions of ESALs, was 0.4, 14.5, and 1.7 at Circular E-C102: Asphalt Emulsion Technology. Transportation Research
2 weeks, 4 months, and 1 year, respectively. These values are Board of the National Academies, Washington, D.C., Aug. 2006, pp. 1–15.
equivalent to 4%, 133%, and 16% of the design capacity. 13. GEMS: The Design and Use of Granular Emulsion Mixes, Manual 14.
The results of this research show that, although pavement capacity Southern African Bitumen Association, Cape Town, South Africa, 1993.
is sufficient at 4 months, it is severely reduced during the first 2 weeks 14. Budge, A. S., and W. J. Wilde. Monitoring Curing of Emulsion-Stabilized
Roadways Using the Dynamic Cone Penetrometer. In Soil and Material
and at 1 year. Trafficking under these reduced capacities would be Inputs for Mechanistic–Empirical Pavement Design (GSP 169). Proc.,
expected to greatly compromise long-term performance and may Geo-Denver 2007: New Peaks in Geotechnics, Denver, Colo. ASCE,
cause premature failure of the pavement system. For this reason, Reston, Va., 2007, pp. 1–8.
48 Transportation Research Record 2253

15. Finn, F. N., R. G. Hicks, W. J. Kari, and L. D. Coyne. Design of Emul-


sified Asphalt Treated Bases. In Highway Research Record 239, HRB,
National Research Council, Washington, D.C., 1968, pp. 54–75.
16. Bondietti, M., D. Murphy, K. Jenkins, and R. Burger. Research on the
Stabilisation of Two Different Materials Using Bitumen Emulsion and
Cement. Proc., 8th Conference on Asphalt Pavements for Southern
Africa, Sun City, South Africa, Sept. 2004. http://www.capsa11.co.za/
capsa04/Documents/026.pdf. Accessed June 22, 2010.
17. DeBeer, M., and J. E. Grobler. Towards Improved Structural Design
Criteria for Granular Emulsion Mixes. Proc., 6th Conference on Asphalt
Pavements for Southern Africa, Cape Town, South Africa, 1994,
pp. III44–III68.
18. Huang, Y. H. Pavement Analysis and Design, 2nd ed. Prentice Hall,
Upper Saddle River, N.J., 2004.
19. Liebenberg, J. J. E., and A. T. Visser. Stabilization and Structural Design
of Marginal Materials for Use in Low-Volume Roads. In Transporta-
tion Research Record: Journal of the Transportation Research Board,
No. 1819, Vol. 2, Transportation Research Board of the National Acad-
emies, Washington, D.C., 2003, pp. 166–172.
20. Budge, A. S., and W. J. Wilde. A Modified Method for MR Testing to
Evaluate Temperature Effects in Emulsion-Stabilized Gravel. Proc.,
GeoCongress 2008: Characterization, Monitoring, and Modeling of FIGURE 4 Redwood Road typical pavement condition, April 2011.
GeoSystems (GSP 179), New Orleans, La., ASCE, Reston, Va., 2008,
pp. 12–19.
21. O’Flaherty, C. A. Highways: The Location, Design, Construction &
Maintenance of Pavements, 4th ed. Butterworth-Heinemann, Woburn, road was a fairly thick structure (6 in. of HMA, 8 in. of ETB, and
Mass., 2002. 4 to 5 in. of remaining aggregate base).
22. Botha, P. B., C. J. Semmelink, J. Raubenheimer, B. Perry, and The current pavement performance is good. Although the authors
A. Hodgkinson. Investigation into the Early Trafficking of Emulsion discuss pavement performance in terms of the ETB modulus, visual
Treated (ETB), Foamed Bitumen (FB) Bases Treated in Combination assessments or similar pavement rating parameters are not discussed.
with Cement and Cement (OPC) Only. In TREMTI 2005: Treatment and
Recycling of Materials for Transport Infrastructure, 2nd International
Figure 4 gives an indication of the performance of Redwood Road
Symposium, Paris, Oct. 2005, pp. 1–10. in April 2011; it was constructed in June 2009. This is one of the
23. Airport Technology, Research and Development Branch, FAA. Documents light FWD test sections and is representative of the overall road.
and Downloads Page. http://www.airporttech.tc.faa.gov/naptf/download/ The right wheelpath is still wet from rain from 2 days before. No
index1.asp. Accessed July 21, 2009. visible rutting or cracking has been observed; rutting and cracking
24. Dai, S., and C. K. Kremer. Improvement and Validation of Mn/DOT
DCP Specifications for Aggregate Base Materials and Select Granular
might be expected if the ETB modulus was significantly lower than
Test. Report MN/RC-2005-32. Office of Materials and Road Research, the design modulus.
Minnesota Department of Transportation, Maplewood, Jan. 2006. In conclusion, the authors are asked to report the data for all layers
25. Heavy-Duty Dual-Mass Dynamic Cone Penetrometer (H-4219) Instruction from the backcalculation analysis and answer the other questions
Manual. Humboldt Manufacturing Corporation, Norridge, Ill., 2003. presented in this discussion. It is also recommended that deflections be
measured with full-scale FWD apparatus.

DISCUSSION
AUTHORS’ CLOSURE
Todd W. Thomas
Road Science, LLC, 6502 South Yale Avenue, Tulsa, OK 74136, The discussant requests clarification of the methods used during PFWD
tthomas@roadsciencellc.com. testing and backcalculation analysis with respect to ASTM D5858
(Standard Guide for Calculating In Situ Equivalent Elastic Moduli of
This paper considers the rate at which asphalt ETB material design Pavement Materials Using Layered Elastic Theory). He also proposes
properties are reached. Modulus values peaked at 4 months but that the pavement performance as of April 2011 is good, based on a
dropped off significantly at 1 year, as calculated from backcalculation visual inspection of the road.
analysis from PFWD data. Specifically, the paper concludes that the In this research, PFWD testing was performed to evaluate the in
modulus values obtained at 1 year were below design values and that situ modulus values at 10 different test stations randomly distributed
this may be due to moisture changes and freeze–thaw damage. across each of three different construction sections, for a total of
An understanding of the accuracy of the light falling weight 30 stations. Figure 5 shows the station layout used for each section,
deflectometer (FWD) data is needed. ASTM D5858 provides a method which generally encompassed the full width of both lanes of north-
for evaluating the match between the actual and measured FWD bound traffic, bordered with a wide shoulder on one side and a median
deflection basins through an equation for root mean square error. on the other. Collected PFWD data were analyzed with BAKFAA,
The authors do not report the match of the deflection basins. It would as explained in the paper; details about this software may be obtained
be useful to have several other questions answered. How many iter- from the website referenced in the paper (23). In the backcalculation
ations were performed in the backcalculation process? Was a hard process, the modulus values of the specified layers were all computed;
layer assumed, and what was its depth? What were the modulus none were assumed, and no apparent stiff layer was included. The
values of the other layers, and were they assumed? Was calibration DCP data collected in this research did not consistently indicate the
of the equipment up-to-date? What were the testing locations, as presence of the remaining aggregate base cited by the discussant;
referenced from the pavement centerline? This information is therefore, all materials below the ETB layer were treated as sub-
important to the reliability of the data, given that the typical loads of grade in the PFWD data analyses. PFWD results for all layers and
a PFWD are light, only three deflection sensors were used, and the testing times are displayed in Table 3, in which dashes indicate that
Quick and Guthrie 49

800 ft
X
X X
24 ft

X X
X X X
X X

FIGURE 5 Typical station layout.

TABLE 3 PFWD Test Data

Modulus (ksi)

Asphalt ETB Subgrade


Curing Time
(days) Average SD Average SD Average SD

Section A
1 — — 21.7 4.4 19.7 5.1
2 — — 22.0 3.6 19.7 4.6
3 — — 31.2 5.9 18.7 3.8
7 — — 39.5 8.9 19.3 3.6
14 — — 36.6 11.0 21.1 5.1
113 1,065.1 307.5 342.4 90.1 26.7 3.8
365 288.3 63.9 85.4 11.9 24.6 3.3
699 251.0 49.5 52.2 14.2 25.6 11.7
Section B
1 — — 13.8 4.1 17.6 5.0
2 — — 18.9 3.3 18.6 4.1
3 — — 22.9 4.5 19.1 3.8
7 — — 23.4 4.5 18.1 3.1
14 — — 27.2 4.0 21.9 4.3
113 1,304.0 123.4 339.9 87.4 25.8 2.2
365 299.0 48.0 94.3 11.1 23.6 2.1
699 187.7 16.0 45.7 3.8 29.0 2.7
Section C
1 — — 17.2 3.1 23.0 5.8
2 — — 22.0 4.7 23.7 5.6
3 — — 28.7 5.2 23.1 4.9
7 — — 30.4 6.1 23.1 5.7
14 — — 35.5 6.3 26.4 5.0
113 770.1 122.3 176.9 29.3 28.0 1.7
365 289.9 32.3 89.2 8.2 26.5 3.0
699 227.3 48.5 58.0 29.1 30.1 6.9
Average
1 — — 17.6 3.9 20.1 5.3
2 — — 21.0 3.9 20.7 4.8
3 — — 27.6 5.2 20.3 4.2
7 — — 31.1 6.5 20.1 4.2
14 — — 33.1 7.1 23.1 4.8
113 1,046.4 184.4 286.4 68.9 26.8 2.6
365 292.4 48.0 89.6 10.4 24.9 2.8
699 222.0 38.0 51.9 15.7 28.2 7.1

NOTE: — = preceded placement of the asphalt layer.


50 Transportation Research Record 2253

the curing times preceded the placement of the asphalt layer. The the right lane in all three test sections. The affected wheelpath is the
average root mean square percent errors were 2.4%, 2.0%, and darker one, pictured on the left-hand side of Figure 5.
1.8% for Sections A, B, and C, respectively, for all data presented Variable early-age stiffness of ETB has also been documented
in the table. in research performed by the Virginia Transportation Research
Concerning pavement performance, the paper focuses on the Council (26). In that study, both lanes of the pavement section
early-age structural properties of the ETB layer at the test site. The constructed with ETB exhibited a significant reduction in effective
PFWD and DCP data both indicate that the ETB modulus values structural number between the first winter and spring, a partial
were consistently low in all three sections during the first 2 weeks recovery during the summer and fall, and then a second reduction in
after construction, increased dramatically by 4 months, and then stiffness between the second winter and spring. The authors of that
decreased considerably by 1 year. As stated in the paper, one possible study also attributed this behavior to environmental conditions, the
explanation for these results is the occurrence of freeze–thaw damage effects of which warranted further study. To this end, work is under
to the ETB layer during the winter. Since the original submission way at Brigham Young University to relate in situ ETB modulus
of the paper, the pavement has experienced a second winter, and measurements to both ETB temperature and moisture content and
PFWD data collected in May 2011 indicated that the ETB layer had also to evaluate the freeze–thaw durability of ETB materials.
experienced further reductions in modulus since the 1-year testing
was completed in June 2010. These data are labeled with a curing
time of 699 days in Table 3 and reflect a 42% reduction, on average, REFERENCE
of the ETB modulus in the as-tested condition since June 2010.
(For reference, the average ambient air and asphalt surface temper- 26. Diefenderfer, B. K., and A. K. Apeagyei. Time-Dependent Structural
atures for the tests performed at 113, 365, and 699 days were 57°F and Response of Full-Depth Reclamation. In Transportation Research
68°F, 80°F and 94°F, and 80°F and 102°F, respectively.) The results Record: Journal of the Transportation Research Board, No. 2253, Trans-
portation Research Board of the National Academies, Washington, D.C.,
of a distress survey performed in May 2011 indicated that, although 2011, pp. 3–9.
cracking of the asphalt layer had not been observed, rut depths of
2 to 3 mm had been consistently measured in the right wheelpath of The Chemical and Mechanical Stabilization Committee peer-reviewed this paper.

You might also like