Global Carriers Ltd.

M/V GLOBAL UNITY JOB ORDER MONITORING TOOL TECHNICAL DPT.


SUPER/NT DATE TO BE JOB STATUS VERIFIED
A/A DATE
INITIALS DESCRIPTION RECTIFIED REMARKS DATE MSG No DATE BY

1 02/02/19 AP Hospital exhaust fan - defective motor burn out - need to replaced new motor - req. GU/3/19. 30/04/19 COMPLETED 04/04/19

At least 6 air valves on deck are with broken wheels. To be renewed. On board exist 3 pcs as
2 07/02/19 AP 28/02/19 COMPLETED 19/02/19
spares recently received

Both anchor’s chains stoppers are fitted with hydraulic mechanism where is out of order long
3 07/02/19 AP time now. Is very hard to be operated and are using chain blocks. Temporary the hydraulic units 28/02/19 COMPLETED 14/02/19
removed for overhauling.

Engine room needs a better housekeeping in daily basis. - better control of garbages and oily
4 07/02/19 AP rags, minimize the oil leaks, repair any leaks either the minor one. 24/02/19 COMPLETED 10/02/19

5 07/02/19 AP Nr.1 fuel oil settling tank - has minor leak from top - to be repaired. In progress. 28/02/19 COMPLETED 15/02/19

6 07/02/19 AP Steam valve of hot well unit leaks - to be repaired. 28/02/19 COMPLETED 15/02/19

At forecastle there is a big deck Air compressor. Working condition unknown. To be inspected
7 07/02/19 AP 20/03/19 COMPLETED 21/03/19
by Engineers and Electrician.

8 07/02/19 AP Cranes hooks – 3 pcs noted with broken safety locks, to be repaired. 22/02/19 COMPLETED 19/02/19