Professional Documents
Culture Documents
Sonoda Et Al. - 2009 - Case Study of A Piled Raft Foundation Constructed Using A Reverse Construction Method and Its Post-Analysis
Sonoda Et Al. - 2009 - Case Study of A Piled Raft Foundation Constructed Using A Reverse Construction Method and Its Post-Analysis
Sonoda Et Al. - 2009 - Case Study of A Piled Raft Foundation Constructed Using A Reverse Construction Method and Its Post-Analysis
Abstract: A building and its foundation were constructed in sandy ground using a reverse construction method. The main
difference between a reverse construction method and a conventional construction method is that the piles are cast in place
and are partially loaded by the superstructure early during the construction process. It is only later that the raft (mat foun-
dation) is constructed to combine with the piles to bear the full building load. Therefore, the foundation is regarded as a
pile group in early stages of construction, while the foundation behaves as a piled raft after completion of the raft con-
struction. A simple conservative design approach was used for the design of the foundation. To examine the validity of
the design method, settlements of the foundation were observed during construction. The measured settlements were
smaller than those predicted in the design stage, satisfying the design requirements for the building. Post-analysis of the
deformation of the foundation was carried out using the results of the pile load test at the construction site, and the results
of the analysis are compared with the observed settlements of the foundation, aiming at an improvement in pile foundation
design.
Key words: piled raft, vertical pile load test, reverse construction method, deformation analysis, water pressure, sandy
ground.
For personal use only.
Résumé : Un bâtiment et ses fondations ont été construits sur un sol sablonneux selon la méthode de construction inverse.
La différence principale entre la méthode de construction inverse et la méthode de construction traditionnelle est que les
pieux sont installés et partiellement chargés par la superstructure au début de la construction. Ce n’est que plus tard que le
radier (tapis de fondation) est construit et combiné aux pieux pour soutenir toute la charge du bâtiment. Ainsi, la fondation
est considérée comme un groupe de pieux au début de la construction, alors que la fondation se comporte plutôt comme
un radier sur pieux une fois le radier construit. Une approche simple et conservatrice a été utilisée pour la conception de
la fondation. Afin d’évaluer la validité de la méthode de conception, le tassement des fondations a été observée durant la
période de construction. Les tassements mesurés étaient plus faibles que ceux prédits à l’étape de conception, ce qui cor-
respond aux exigences de construction du bâtiment. Une analyse de la déformation des fondations a été effectuée à partir
de résultats d’essais de chargement sur les pieux au site de construction; les résultats de cette analyse ont été comparés
avec les résultats d’observations de tassement des fondations, ceci dans le but d’améliorer la conception de fondations sur
pieux.
Mots-clés : radier sur pieux, essais de chargement vertical sur pieux, méthode de construction inverse, analyse de déforma-
tion, pression d’eau, sol sablonneux.
[Traduit par la Rédaction]
Introduction of the allowable stress design, the piles take the majority of
the load (Poulos 2001) and the designers do not need to con-
In many countries (except for Germany), most pile founda- sider the settlement of the foundation in most cases. A pile
tions for buildings are still designed as pile groups, in which foundation designed as a pile group is thought to have an ad-
the contribution of the raft resistance is ignored even though equate margin of safety; however, such a foundation design
its contribution is relatively large, as shown by field monitor- is costly and construction work is time-consuming.
ing of actual buildings (for example, Kakurai 2003). If a pile In recent years, since Burland et al. (1977) proposed the
foundation is designed as a pile group with a conventional concept of ‘‘piles as settlement reducers,’’ there has been in-
safety factor (for example, 3 in Japan) using the framework creasing recognition that the inclusion of the resistance of
Received 28 April 2007. Accepted 10 October 2008. Published on the NRC Research Press Web site at cgj.nrc.ca on 4 February 2009.
R. Sonoda. Yasui Architects and Engineers, Chiyoda-ku, Tokyo 102-0093, Japan, and Graduate School of Kanazawa University,
Kakuma-machi, Kanazawa, Ishikawa 920-1192, Japan.
T. Matsumoto1 and P. Kitiyodom. Graduate School of Kanazawa University, Kakuma-machi, Kanazawa, Ishikawa 920-1192, Japan.
H. Moritaka and T. Ono. Yasui Architects and Engineers, Chiyoda-ku, Tokyo 102-0093, Japan.
1Corresponding author (e-mail: matsumot@t.kanazawa-u.ac.jp).
Can. Geotech. J. 46: 142–159 (2009) doi:10.1139/T08-111 Published by NRC Research Press
Sonoda et al. 143
the raft in pile foundation design can lead to a considerable Fig. 1. Amuplaza building in Kagoshima, Japan, after completion
economy without compromising the safety or performance of construction.
of a foundation. The design concept of a piled raft can lead
to a rational reduction of the number or length of piles, be-
cause the raft resistance is also considered in the design. De-
signers need to estimate the settlement more accurately in
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
settlement have been carried out during and after the con- and a maximum height of 45 m (see Fig. 2). A Ferris wheel
struction of buildings (for examples, Cooke et al. 1981; was constructed on the roof of the building (Fig. 1). The
Hansbo 1993; Hooper 1973; Katzenbach et al. 1998a; building has a composite structure consisting of steel-
Sommer et al. 1991, etc.). The piled raft foundation method reinforced concrete columns and steel beams. The average
was applied to the foundation of high rise towers in Dubai contact stress on the raft disregarding the piles is 118 kPa.
(Poulos and Davids 2005). Piled raft foundations constructed The design requirements for the building were that the
using the reverse construction method are rare; an exception (average) settlement was not to exceed 25 mm and the incli-
is presented by Katzenbach et al. (1998b). nation slope of the basement due to differential settlement
Reasons for limited use of piled raft foundations con- was not to be steeper than 1/1000. Several foundation design
structed using the reverse construction method may be at- options were considered, and a piled raft foundation was fi-
tributed to insufficient field observation data of such nally adopted.
foundations and complicated design procedures. The first,
fourth, and fifth authors were involved in the design of a Site conditions
commercial building called Amuplaza (Fig. 1) constructed Boreholes were drilled at five locations (EB-1 to EB-4
in 2003 to 2004 using the reverse construction method. A and B-1) within the construction site to characterize the soil
piled raft foundation was adopted for this building. In the conditions (see Fig. 2). Boreholes EB-1 to EB-4 were car-
design, friction piles were used as ‘‘settlement reducers’’ as ried out in 1993 to explore soil stratification and to obtain
proposed by Burland et al. (1977). A conservative design distributions of standard penetration test (SPT ) blow count,
approach was employed in the design stage. Hence, observa- N, to depths of 50 to 65 m. Detailed drilling and sampling
tion of settlements of the foundation and the pore-water were carried out in 2002 at B-1, at the centre location of
pressure distribution beneath the raft were carried out during the building. In the latter borehole, primary and secondary
the construction work, to assess the validity of the design elastic wave velocity (PS)-logging was carried out to deter-
approach and to provide useful information on the behaviour mine velocities of the primary wave, Vp, and the secondary
of a piled raft constructed using the reverse construction (shear) wave, Vs, to a depth of 30 m below the ground level,
method. Furthermore, an auxiliary static load test on a test which was approximately the pile toe depth determined in
pile was carried out during the construction work, to obtain the design.
more realistic design parameters. The results of borehole investigations showed that the
This paper first reviews the design approach adopted and stratification at the construction site is almost horizontal.
presents the results of the field observations. Then, post- The soil layers to a depth of 60 m are compressible sand or
analysis of the foundation deformation is performed using sandy silt or silt. The SPT N-values are 10 to 20 to a depth
the results of the pile load test. In this post-analysis, a sim- of 50 m. The layer from a depth of 50 to 60 m is sand or
plified three-dimensional deformation analysis method (Ki- sandy silt, in which N-values vary from 20 to 42, as can be
tiyodom and Matsumoto 2002, 2003) was employed, taking seen in the borehole EB-2 of Fig. 2. Gravel with N-values
the construction procedure into account. The results of the larger than 50 exists below a depth of 60 m. It is common
analyses are compared with the measured behaviour of the practice in Japan to terminate the SPT when an N-value
Fig. 2. Elevation view of building, soil profiles, standard penetration test (SPT) N-values, and arrangement of piles. All dimensions in
metres.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
For personal use only.
greater than 50 is obtained, because the results from further Figure 4 illustrates the reverse construction method em-
penetration of the SPT sampler are thought to be not reli- ployed in the construction of the building and the foundation.
able. The time sequence of the reverse construction method
Figure 3 summarizes the results of SPT and PS-logging at was as follows:
B-1. The ground-water level was established to be a depth
of 3.0 m. The total density of the soil, rt, was estimated (1) Cast–in situ concrete piles were constructed below 6.5 m
from the soil samples. The undrained Poisson’s ratio, nu, from the ground surface (Fig. 4a).
shear modulus, G0, and undrained Young’s modulus, Eu0, of (2) Steel columns having a length of 7.5 m were attached to
the soil at a small strain level were estimated using the fol- the heads of piles (Fig. 4b).
lowing relations of elasticity: (3) Groundwater table was lowered from the original depth
of 3.0 to 7.5 m below the ground level for the excava-
ðVp =Vs Þ2 2
½1 nu ¼ tion work that followed.
2ðVp =Vs Þ2 1 (4) The ground was excavated to a depth of 2.5 m to expose
the tops of the steel columns, and steel beams for the
½2 G0 ¼ rt Vs2 ground floor were connected to the tops of the steel col-
umns (Fig. 4c).
½3 Eu0 ¼ 2ð1 þ nu ÞG0 (5) Concreting work was done to construct the ground floor
(Fig. 4d).
(6) The ground was again excavated to a depth of 6.5 m
Reverse construction method employed (Fig. 4e). Note that the constructed ground floor takes
A piled raft foundation constructed using a reverse (top- the role of a strut during this ground excavation stage to
down) construction method was adopted for the building. ensure the safety of the excavation work.
(7) Steel columns and beams of the superstructure were con- pile group stage was 70% of the final total load at the com-
structed for the first floor to the roof (Fig. 4f). pletion of the building. The remaining 30% of the final total
(8) Construction of the raft (basement floor) on the piles and load was supported by the piled raft.
construction of the superstructure progressed simulta- Figures 6a and 6b show the distributions of load incre-
neously, and construction of the raft structure was com- ments on the foundation from the building in stages of the
pleted at the end of December in 2003 (Fig. 4g). It pile group and the piled raft, respectively, while Fig. 6c
should be noted that all increments of the load from the shows the distribution of the final loads at the completion
superstructure were supported by the piles alone until of the building. The load distributions of Figs. 6a and 6b
this construction stage, because there was no raft resis- were used in the design of the foundation.
tance until this construction stage. Hence, the foundation
until this construction stage is referred to as ‘‘pile Design of foundation
group’’ in this paper.
According to the conventional foundation design concept
(9) Construction of the basement floor and the above-ground
in Japan, the subject building structure would be supported
floors progressed simultaneously (Fig. 4h). Note that
on 60 m long toe-bearing piles in the gravel below the com-
further increments of the load from the building were
pressible soils without consideration of the raft base resist-
supported by the raft and the piles in this construction
ance. However, such a design would be costly and
stage. Hence, the foundation in this stage is referred to
construction time-consuming. It was estimated that the cost
as ‘‘piled raft’’ in this paper. Note that the groundwater
for the foundation would be reduced from US$9.9 million
table was recovered to 3.0 m below the ground level at
to US$3.6 million, and the construction period reduced by
the end of February 2004.
2 months, if a piled raft foundation constructed using the re-
Tables 1 and 2 show the time sequence of construction of verse construction method was adopted. Therefore, a piled
the superstructure and the foundation structure, respectively. raft foundation constructed using the reverse construction
Figure 5 shows the time histories of the total load from the method was adopted as described below.
building and measured water pressure beneath the raft. As
mentioned above, the foundation was regarded as a ‘‘pile Design philosophy
group’’ until the end of of 2003. The foundation behaved as The following design philosophies were adopted for the
a ‘‘piled raft’’ after that time. The lowered groundwater table foundation of the building:
(7.5 m below ground level (G.L.)) was recovered to the
original groundwater table of 3.0 m at the end of February (1) The raft consists of a mat having a thickness of 0.6 m
2004. The increase in the water pressure of 35 kPa measured and beams having a height of 1.2 m to reduce differential
at the raft base (6.5 m below G.L.) corresponded to this re- settlements and to reduce its weight, as shown in Fig. 7.
covery of the groundwater table. (2) The bearing capacity of the foundation is estimated dis-
It is seen from Fig. 5 that the total load at the end of the regarding the existence of the piles, while the piles are
Fig. 4. Reverse construction method employed. (a) Construction of cast–in situ concrete piles. (b) Construction of steel columns to the
ground floor level. (c) First excavation work and construction of steel columns and beams of the ground floor. (d) Concreting work of the
ground floor. (e) Second excavation work to a depth of 6.5 m. ( f ) Construction of steel columns and beams of the superstructure, and the
foundation mat. (g) Construction of the foundation beams and concreting work of the superstructure. (h) Construction in stage of piled raft.
All dimensions in metres.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
For personal use only.
used as settlement reducers, according to regulations for distribution of the loads shown in Fig. 6a that corresponds
buildings in Japan. to the maximum vertical loads in the pile group stage.
(3) Cast–in situ concrete piles are used as the settlement re-
ducers. Design model for foundation
(4) The ultimate capacity of the piles is designed to resist the The model shown in Fig. 8 was employed to estimate de-
Area
Average floor
Floor level No. 1 No. 2 No. 3 No. 4 load (kPa)
RF (Roof floor) — 20 Jan 2004 20 Feb 2004 17 Mar 2004 7.8
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
Area
Average floor
No. 1 Nos. 1 and 2 Nos. 2 and 3 No. 3 Nos. 3 and 4 No. 4 load (kPa)
B1F (basement) 12 Dec 2003 19 Dec 2003 8 Jan 2004 16 Jan 2004 22 Jan 2004 30 Jan 2004 7.8
Raft 7 Nov 2003 12 Nov 2003 19 Nov 2003 27 Nov 2003 4 Dec 2003 8 Dec 2003 24.0
Note: Bold type indicates construction in stage of piled raft. Construction areas are defined in Fig. 13.
Fig. 5. Time histories of the total load from the building and measured water pressure at the raft base. Construction areas are defined in Fig. 13.
For personal use only.
formation of the raft alone, the pile group or the piled raft. is the embedment depth; Nc, Ng, and Nq are the well-known
The raft was modelled by the beams, the soil beneath the coefficients of bearing capacity as a function of internal
raft was treated as springs connected to the beams, and the friction angle of the soil, f, which is estimated from an
piles were treated as the springs connected to the intersec- pffiffiffiffiffiffiffiffiffi
empirical equation f ¼ 20N + 15 (8).
tions of the beams. Interaction between the springs was not
taken into account, i.e., the springs were Winkler-type The allowable bearing stress, qa, was then determined by
springs where pile–pile interaction was also neglected. Note dividing the ultimate stress by a safety factor of 3.0:
that the bending rigidity of the beams was set equal to that ½4b qa ¼ qu =3
of the raft structure of Fig. 7.
In the design of the raft alone, c = 0 and N = 10 (f = 298)
Design of raft alone were used and the allowable bearing stress of the raft, qa =
The ultimate bearing capacity of the raft, qu, was esti- 200 kPa, was calculated by means of eqs. [4a] and [4b].
mated using the following semi-empirical equation specified That is, it exceeded the average contact stress of 118 kPa
in Recommendations for design of building foundations (Ar- from the building.
chitectural Institute of Japan 2001): The subgrade reaction of the raft, kv, was estimated on the
basis of Steinbrenner’s formula (Steinbrenner 1934). This al-
½4a qu ¼ acNc þ bg 1 BNg þ g 2 Df Nq
lows for multi-layer ground with finite depth.
where a is an empirical parameter (a = 1.0 + 0.3B/L, where In the estimation of kv, the values of shear moduli, G0, of
B is the shorter length and L is the longer length of rectan- the soils estimated from PS-logging (Fig. 3) were reduced
gular raft); c is the soil cohesion; b is an empirical para- by a factor of 5 to obtain the design values of shear moduli
meter (b = 0.5 – 0.1B/L); g1 and g2 are the unit weights of Gdesign, because the strain level in soils beneath the founda-
the soil below and above the raft base level, respectively; Df tion is thought to be large compared with the strain level in
Fig. 6. Distributions of loads from the building. (a) Superstructure load increments in stage of pile group. (b) Superstructure load increments
in stage of piled raft. (c) Total superstructure loads at completion of the building.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
For personal use only.
Fig. 7. Raft structure composed of mat and beams. Fig. 8. Modelling of piled raft used in the design stage.
Fig. 9. One-dimensional model to estimate load–displacement rela- Fig. 10. Hyperbolic curve for shaft resistance versus local pile dis-
tion of a pile. placement.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
because pile load testing had not been carried out in the de-
sign stage.
For personal use only.
Fig. 12. Distributions of settlements of various foundation types es- Fig. 13. Arrangement of measurements and names of construction
timated in the design stage: (a) along section A-A’ and (b) along areas. All dimensions in metres.
section B-B’.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
along A-A’ Fig. 12a and along B-B’ Fig. 12b (see Fig. 2).
The maximum settlement of the raft alone was 29 mm and
the maximum differential settlement was 14 mm. In the
case of the piled raft, the maximum settlement was reduced
to 20 mm and the maximum differential settlement was re-
duced to 13 mm. The settlements of the foundation at the
end of the pile group stage were smaller than those at the of the settlement of the raft at 45 points and pore-water
end of the piled raft stage, because the total vertical load on pressure beneath the raft at a depth of 6.5 m. A track level
the pile group was about 70% of that for the piled raft (see was used to measure the settlement of the raft relative to a
Fig. 6). It was judged from Fig. 12 that the piles had suffi- bench mark with a precision of 0.5 mm.
cient performance to suppress the settlements of the founda-
The results of the measurements of settlements at the
tion below 25 mm during the pile group stage in the reverse
completion of the building (Fig. 14) showed that the settle-
construction method.
ments of the foundation were smaller than those estimated
in the design stage, which confirmed that the design of the
Field observations and pile load test foundation was appropriate. Details of the results of the field
In the design of the foundation, conservative values of the observations are presented in the section entitled ‘‘Post-
shear moduli of soils were used, i.e., the values of shear analysis of deformation of the foundation’’, together with
moduli of the soils estimated from PS-logging were reduced the results of the post-analysis.
by a factor of 5. To confirm that the design parameters used
in the design are appropriate to satisfy the design require- Pile load test
ments, and to provide useful information of the actual be- A test pile was constructed additionally at the location in-
haviour of the foundation for improvement of the design dicated by the ‘‘star’’ symbol in Figs. 2 and 13. The test pile
procedure in the future, field observations including meas- was a cast–in situ concrete pile having a length of 32.0 m
urements of settlements of the foundation and pore-water and a diameter of 1.0 m. Shaft friction of the pile to a depth
pressure beneath the raft and a pile load test at the construc- of 7.5 m was cut off by installing a double steel tube to this
tion site were planned at the design stage. depth. Axial forces were measured at six levels of the pile
(Fig. 15a) and shaft resistance at sections between the strain
Field observations gauge levels was derived from the measured axial forces.
Figure 13 shows the plan view of the arrangement of field Four working piles having a length of 25 m were used for
observations. The field observations included measurements the reaction piles as shown in Fig. 15b, where the distance
Fig. 15. Conditions of axial pile load test. (a) Seating of test pile, soil profile, and SPT N-values obtained at borehole EB-2. (b) Arrange-
ment of test and reaction piles.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
For personal use only.
Fig. 16. Load on pile head with elapsed time. vertical stresses in the ground. It can be seen from the figure
that the distribution of fmax is related to neither the SPT N-
values nor the effective vertical stress in the ground. This
fact encourages us to perform pile load tests to obtain the
pile performance at each pile construction site.
The results of the pile load test were effectively utilized
in the post-analysis of the deformation of the foundation.
Fig. 17. Results of axial pile load test. (a) Relationship between pile head load and pile head displacement. (b) Relationship between shaft
resistance and local pile displacement. (c) Distribution of maximum shaft resistance, fmax, together with profiles of SPT N-values and effec-
tive vertical stresses in the ground.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
For personal use only.
2pGDL
½11 KzP ¼
lnðrm =ro Þ
where
2 np 3
X
6 Gi Li rffiffiffiffiffiffiffi 7
6 i¼1 Gm 7
½12 6
rm ¼ 2:56 cLð1 ns Þ7
G L G 7;
4 m b 5
c ¼ 1 expð1 h=LÞ
where a is the equivalent radius of the raft element, ns is the
Poisson’s ratio of the soil, h is the finite soil depth, h* is the
distance between the pile toe and the rigid bed stratum, ro is
the pile radius, np is the total number of soil layers along the Fig. 19. Modelling of the test single pile and ground.
pile length, and DL and L are the pile segment length and
the pile length, respectively. Gb is the soil shear modulus
below pile toe, G is the soil shear modulus, Gm is the max-
imum soil shear modulus, and Gi and Li are, respectively,
the shear modulus and the length of pile embedded in soil
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
1 Xn
1
½14 ¼ DIi =DItotal
Es E
i¼1 si
32ð1 ns ÞGb r0
½16 KxPb ¼ KyPb ¼
7 8ns
Fig. 21. Modelling of foundation and ground. Fig. 22. Construction areas of superstructure in stages of pile group
and piled raft, and foundation model.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
Fig. 23. Calculated and measured settlements of the raft (at y = Fig. 24. Calculated and measured settlements of the raft (at y =
16.2 m). (a) Increments of settlements in pile group stage. (b) In- 40.5 m). (a) Increments of settlements in pile group stage. (b) In-
crements of settlements in piled raft stage. (c) Total settlements at crements of settlements in piled raft stage. (c) Total settlements at
the completion of construction. completion of construction.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
For personal use only.
raft stage was carried out after the end of the first stage, tak- Figures 23 to 26 show the comparisons of the calculated
ing into account the existence of the raft resistance. The and measured settlements of the raft. Figure 23 shows the
stress conditions at the end of the first stage were used for distributions of calculated and measured settlements of the
the initial conditions in the second stage. The distribution of raft in the x-direction at y = 16.2 m. Increments of settle-
load increments of Fig. 6b was applied on the raft in the ments in the pile group stage are shown in Fig. 23a, those
analysis of the piled raft, and a uniform uplift water pressure in stage of piled raft are shown in Fig. 23b, and the total
of 35 kPa due to the recovery of the lowered groundwater settlements at the final construction stage are shown in
table with respect to the original ground water table (3.0 m Fig. 23c. Similar results are shown in Fig. 24 for distribu-
below G.L.) was also applied to the raft. tions of settlements in the x-direction at y = 40.5 m, in
Fig. 25. Calculated and measured settlements of the raft (at x = Fig. 26. Calculated and measured settlements of the raft (at x =
34.8 m). (a) Increments of settlements in pile group stage. (b) In- 132.0 m). (a) Increments of settlements in pile group stage. (b) In-
crements of settlements in piled raft stage. (c) Total settlements at crements of settlements in piled raft stage. (c) Total settlements at
the completion of construction. the completion of construction.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
For personal use only.
Fig. 25 for distributions of settlements in the y-direction at Figure 27 shows the three-dimensional expression of the
x = 34.8 m, and in Fig. 26 for distributions of settlements in calculated settlements of the raft. It is seen that dish-shaped
the y-direction at x = 132.0 m. It is seen from Figs. 23 to 26 settlement patterns occur in pile group and piled raft,
that although the analysis tends to overestimate the meas- although the average settlement is less than 10 mm and the
ured settlements in the the pile group foundation stage and flexure of the raft is less than 1/2000. The use of the con-
underestimate the measured settlements in the piled raft cept of ‘‘centred piles’’ proposed by Horikoshi and Randolph
foundation stage, the analysis predicted the measured total (1998) may reduce differential settlements more effectively.
settlements fairly well. Figure 28 shows the calculated pile head loads at the
Fig. 27. Calculated distribution of settlements of the raft. (a) Increments of settlements in pile group stage. (b) Increments of settlements in
piled raft stage. (c) Total settlements at the completion of construction. Disp., displacement.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
For personal use only.
Fig. 28. Calculated pile head loads at the completion of the build- Conclusions
ing.
A case study of a piled raft foundation for a building con-
structed using the reverse construction method was pre-
sented. The foundation system acted as a pile group in
earlier construction stages and then acted as a piled raft in
later construction stages in the reverse construction method.
A conservative design method was used to design the foun-
dation system. Detailed field measurements including settle-
ments of the raft and the pore-water pressure beneath the
raft as well as a static load test of a test pile were carried
out during the construction work. The field measurements
revealed that the average and differential settlements were
sufficiently less than the allowable values.
Post-analysis of the foundation system was carried out us-
ing a simplified three-dimensional deformation analysis
method. The shear moduli of the ground at small strain lev-
els were estimated from PS-logging and shear moduli at
large stain levels were estimated from back-analysis of the
static pile load test. The shear moduli at large strain leves
completion of the building. In the design stage, the ultimate were used to estimate soil springs at the pile nodes, whereas
bearing capacity of the piles was estimated as 10 MN typi- the shear moduli at small strain levels were used to estimate
cally. The results of the analysis suggest that the pile head the interaction factors. The calculated results predicted the
loads on all the piles are less than the ultimate bearing ca- measured settlements of the foundation well in both pile
pacity of the piles. group and piled raft stages.
It should be noted here that the shear moduli of the soils national Geotechnical Seminar on Deep Foundations on Bored
at small strain levels estimated from empirical equations us- and Auger Piles, Ghent, Belgium, 19–21 October 1998. Edited
ing SPT N-values were used in the post-analysis. Hence, re- by W.F. Van Impe and W. Haegeman. A.A. Balkema, Rotter-
liability of the calculation results depends on the reliability dam, the Netherlands. pp. 215–221.
of the empirical equations. Katzenbach, R., Moormann, C., and Quick, H. 1998b. A new con-
cept for the excavation of deep building pits in inner urban areas
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
This case study suggests that estimation of shear moduli combining top/down method and pile raft foundation. In Pro-
of the soils at small strain levels via PS-logging and estima- ceedings of the 7th International Conference and Exhibition on
tion of reduced shear moduli of the soils surrounding piles Piling and Deep Foundations, Vienna, Austria, 15–17 June
via back-analysis of static pile load tests at the site are key 1998. Deep Foundation Institute, Hawthorne, N.J. Paper 347.
points in calculation of deformation of the foundation when pp. 5.17.1–5.17.13.
a simplified analytical method is used. Kitiyodom, P., and Matsumoto, T. 2002. A simplified analysis
method for piled raft and pile group foundations with batter
Acknowledgements piles. International Journal for Numerical and Analytical Meth-
The authors deeply thank Kyushu Railway Company and ods in Geomechanics, 26(13): 1349–1369. doi:10.1002/nag.248.
Kitiyodom, P., and Matsumoto, T. 2003. A simplified analysis
Kagoshima Terminal Building Corporation for their permis-
method for piled raft foundations in non-homogeneous soils. In-
sion to use the valuable field measurement data.
ternational Journal for Numerical and Analytical Methods in
Geomechanics, 27(2): 85–109. doi:10.1002/nag.264.
References Kitiyodom, P., Matsumoto, T., and Kanefusa, N. 2004. Influence of
Architectural Institute of Japan. 2001. Recommendations for design reaction piles on the behaviour of test pile in static load testing.
of building foundations. Architectural Institute of Japan, Tokyo. Canadian Geotechnical Journal, 41(3): 408–420. doi:10.1139/
[In Japanese.] t03-098.
Atkinson, J.H. 2000. Non-linear soil stiffness in routine design. Lee, C.Y. 1991. Discrete layer analysis of axially loaded piles and
Géotechnique, 50(5): 487–508. pile groups. Computers and Geotechnics, 11(4): 295–313.
Burland, J.B., Broms, B.B., and de Mello, V.F.B. 1977. Behaviour doi:10.1016/0266-352X(91)90014-7.
of foundations and structures on soft ground. In Proceedings of Majima, M., and Nagao, T. 2000. Behaviour of piled raft founda-
For personal use only.
the 9th International Conference on Soil Mechanics and Founda- tion for tall building in Japan. In Design applications of raft
tion Engineering (ICSMFE), Tokyo, 10–15 July 1977. Japanese foundations. Edited by J.A. Hemsley. Thomas Telford, London.
Geotechnical Society, Tokyo. Vol. 2. pp. 495–546. pp. 393–410.
Cooke, R.W., Bryden-Smith, D.W., Gooch, M.N., and Sillet, D.F. Mindlin, R.D. 1936. Force at a point interior of a semi-infinite so-
1981. Some observations of the foundation loading and settle- lid. Physics, 7: 195–202. doi:10.1063/1.1745385.
ment of a multi-storey building on a piled raft foundation in Ohta, Y., and Goto, N. 1976. Estimation of S-wave velocity in
London Clay. Proceedings of the Institution of Civil Engineers, terms of characteristics indices of soil. BUTSURI-TANKO. So-
70(1): 433–460. ciety of Exploration Geophysicists of Japan, 29(4): 31–41. [In
Fraser, R.A., and Wardle, L.J. 1976. Numerical analysis of rectan- Japanese.]
gular rafts on layered foundations. Géotechnique, 26(4): 613– Poulos, H.G. 2001. Piled raft foundations – design and applica-
630. tions. Géotechnique, 51(2): 95–113.
Hansbo, S. 1993. Interaction problems related to the installation of Poulos, H.G., and Davids, A.J. 2005. Foundation design for the
pile groups. In Proceedings of the 2nd International Geotechni- Emirates Twin Towers. Dubai. Canadian Geotechnical Journal,
cal Seminar on Deep Foundations on Bored and Augered Piles, 42(3): 716–730. doi:10.1139/t05-004.
Ghent, Belgium, 1–4 June 1993. Edited by W.F. Van Impe. A.A. Poulos, H.G., and Davis, E.H. 1980. Pile foundation analysis and
Balkema, Rotterdam, the Netherlands. pp. 59–60. design. John Wiley & Sons, New York.
Harr, M.E. 1966. Foundations of theoretical soil mechanics. Sommer, H., Tamaro, G., and DeBenedittis, C. 1991. Messe Turm,
McGraw-Hill, New York. foundations for the tallest building in Europe. In Proceedings of
Hooper, J.A. 1973. Observations on the behaviour of a piled raft the 4th International Conference on Piling and Deep Founda-
foundation in London clay. Proceedings of the Institution of Ci- tions, Stresa, Italy, 7–12 April 1991. Balkema, Rotterdam, the
vil Engineers, 55(Part 2): 855–877. Netherlands. pp. 139–145.
Horikoshi, K., and Randolph, M.F. 1998. A contribution to opti- Steinbrenner, W. 1934. Tafeln zur Setzungberechnung. Die Strasse,
mum design of piled raft. Géotechnique, 48(3): 301–317. 1: 121–124. (as referenced in Poulos and Davis 1980). [In Ger-
Kakurai, M. 1987. Field measurements of load transfer in piled raft man.]
foundation. In Proceedings of the 8th Asian Regional Confer- Tanaka, T., Segawa, T., Katoh, Y., Kakurai, M., and Tomono, M.
ence on Soil Mechanics and Foundation Engineering 1987. A design of foundation and the behaviour of a tall build-
(ARCSMFE), Kyoto, 20–24 July 1987. Vol. 1. pp. 327–329. ing at Kobe Port Island. In Proceedings of the International
Kakurai, M. 2003. Study on vertical load transfer of piles. Ph.D. Symposium on Geotechnical Engineering of Soft Soils, Mexico
thesis, Tokyo Institute of Technology, Tokyo. [In Japanese]. City, Mexico, 3–14 August 1987. Edited by M. Mendoza and L.
Kakurai, M., Yamashita, K., and Tomono, M. 1987. Settlement be- Montańez. Mexican Society for Soil Mechanics, Mexico City.
havior of piled raft foundations on soft ground. In Proceedings pp. 389–396.
of the 8th Asian Regional Conference on Soil Mechanics and Uto, K., Okahara, M., Ikeda, K., Maeda, Y., and Matsui, K. 1987.
Foundation Engineering (ARCSMFE), Kyoto, 20–24 July 1987. Bearing properties and reliability of friction piles. In Proceed-
Vol. 1. pp. 373–376. ings of the 32nd Symposium of the Japanese Society of Soil
Katzenbach, R., Arslan, U., and Reul, O. 1998a. Soil-structure- Mechanics and Foundation Engineering, Tokyo, 9 November
interaction of a piled raft foundation of a 121 m high office 1987. Japanese Society of Soil Mechanics and Foundation Engi-
building on loose sand in Berlin. In Proceedings of the 3rd Inter- neering, Tokyo. pp. 17–22. [In Japanese.]
Yamada, T., Yamashita, K., Kakurai, M., and Tsukatani, H. 2001. Yamashita, K., and Kakurai, M. 1991. Settlement behavior of raft
Long-term behaviour of tall building on raft foundation con- foundation with friction piles. In Proceedings of the 4th Interna-
structed by top-down method. In Proceedings of the 5th Inter- tional Conference on Piling and Deep Foundations, Stresa, Italy,
national Conference on Deep Foundation Practice, Singapore, 7–12 April 1991. Balkema, Rotterdam, the Netherlands.
5–6 April 2001. CI-Premier Pte Ltd., Singapore. pp. 411–417. pp. 461–466.
Yamakata, K., and Nagai, K. 1981. Approximate equations for re- Yamashita, K., Kakurai, M., and Yamada, T. 1994. Investigation of
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15
lationships of skin friction and settlement of piles and their sta- a piled raft foundation on stiff clay. In Proceedings of the 13th
tistics. In Proceedings of 1981 Annual Meeting of Japan International Conference on Soil Mechanics and Foundation En-
Architectural Institute, Fukuoka, Japan, 28–30 September 1981. gineering (ICSMFE), New Delhi, 5–10 January 1994. A.A.
Architectural Institute of Japan, Tokyo. pp. 2315–2316. [In Japa- Balkema, Rotterdam, the Netherlands. Vol. 3. pp. 543–546.
nese.] Yamashita, K., Yamada, T., and Kakurai, M. 1998. Simplified
Yamakata, K., Tominaga, K., and Ko, K. 1983. A consideration on method for analyzing piled raft foundations. In Proceedings of
base load-base settlement relations of cast-in-situ concrete piles. the 3rd International Geotechnical Seminar on Deep Foundations
In Proceedings of the 18th Annual Meeting of Japanese Society on Bored and Auger Piles, Ghent, Belgium, 19–21 October
of Soil Mechanics and Foundation Engineering, Kooriyama, 9– 1998. Edited by W.F. Van Impe and W. Haegeman. A.A. Balk-
11 June 1983. Japanese Society of Soil Mechanics and Founda- ema, Rotterdam, the Netherlands. pp. 457–464.
tion Engineering, Tokyo. pp. 1001–1004. [In Japanese.]
For personal use only.
1. Yaru Lv, Hanlong Liu, Charles W.W. Ng, Xuanming Ding, Anthony Gunawan. 2014. Three-dimensional numerical analysis of
the stress transfer mechanism of XCC piled raft foundation. Computers and Geotechnics 55, 365-377. [CrossRef]
2. V.A. Sawant, S.V. Pawar, K.B. Ladhane. 2012. Parametric study of piled raft for three load-patterns. Coupled Systems Mechanics
1, 115-131. [CrossRef]
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by INDIAN INSTITUTE OF TECHNOLOGY BOMBAY on 10/15/15