1 Excavation Check whether Excavation is done as per approved drawing.
2 Levelling Ensure the levelling of excavated soil before PCC.
3 PCC Ensure PCC Grade and PCC concrete level as per drawing.
4 Excavated soil Excavated soil should be at distance of 1 meter from excavated pit.
Check the Reinforcement (Steel bar) dimensions, size, quantity and position as per drw.
Reinforcement Check Reinforcement arrangement, overlapping, winding, Spacing, straighten etc.
5
check before RCC Cover block (50X50 mm) must be provided between PCC level and Reinforcement.
Ensure Reinforcement should not be touch to PCC level.
Shuttering box size should be as per design or as per foundation size.
Shuttering box fixing/connection should be done by nut‐bolts. Connections of boxes by
Form
6 Armour/steel wire not allowed.
Boxes/Shuttering
Light coat of oil should be done inside of form boxes to avoid honeycomb or repairing.
No any reinforcement should be touch to shuttering box. (Maintain a required gap)
Whether the RCC Grade is as per design.
7 RCC Mixture
Ensure mixing of Cement, Aggregate/Gravel, Sand with designated proportion.
Check concrete workability or water‐cement ratio by slump test.
8 Slump Test Is the light coat of oil and tamping rod is used during test?
Slump value should be as per material grade.
Ensure whether the cube mould (150x150 mm) is filled with Freshly made concrete for testing
purpose.
Ensure tamping rod while cube sample filling concrete and light coat of oil to inner surface of
9 Cube sample
cube mould before filling.
After making cube sample, mention the date, foundation name and signature of site
representative from client side.
Concrete
10 During RCC work, make sure the vibrator is using for concrete compaction.
Compaction
Check fixing of channel, plate, Jacking pad if any
Channel Fixing in
11 Check centre to centre distance of jacking pad in case of transformer.
RCC
Check channel, plate dimensions and fixing position.
12 Dimensions Check all the dimensions given in drawing before and after concreting.
Check visual defect after finishing concrete work Like:
13 Concrete defect Cracks, Honeycomb, Repairs, foundation shape, reinforcement exposed etc. If any then do the
additional repairing by using cement plaster.
14 Curing Is curing done after concreting. Gunny bags to be used for curing.