PASIR PANJANG,DAERAH PORT DICKSON,NEGERI SEMBILAN DARUL KHUSUS

BUILT-UP RATE FOR DISMANTLE EXISTING GABION WALL

Equipment and Labour :-

The following cost breakdown is

Excavator 1,040.00 per /day


Lorry ( 1 Tonne ) 800.00 per day
Labour Cost 80.00 per day

Excavate oversite Cost / m3


( Assume job completed in 2 days)

Excavator -1nos @ 1days@Rm 1040 2,080.00

Labour Cost

Unskill 1 nos @ 2 days @Rm80 160.00


Skill 1 nos @ 2days @Rm130 260.00
Excavator operator @2days @ Rm 130 130.00
2,630.00

Profit & Overhead @ 15% 394.50


3,154.50

Difficulties & site condition 20% 630.90

3,785.40

m3 @ say 37.85 /m3