Professional Documents
Culture Documents
Steel Preparation
Steel Preparation
P R E P E R A T I O N:
At the new building stage the steel has not yet been exposed to the corrosive, salty
environments which accelerates the corrosion process. At this stage much of the
pretreatment has been carried out and it is now that the quality of the protective system is
established and will decide the lifetime and safety of the vessel.
1. Pre-blasting preparation
All protection against corrosion begins with the steel work. This may appear obvious but
is absolutely critical in many applications.
Pre-blasting preparation should take place in the welding shop. This is the best time to
carry out the work, it is where the correct equipment is located and other workers will not
be disturbed.
Treatment A:
Treatment B:
Wire brushing of welding seams, rust and damaged shopprimer to standard ST2 (ISO
8501-1). The standard to be kept until application of first coat of paint.
Treatment D:
Blast cleaning of welding seams, rust and damaged shopprimer to standard SA 2 ½ (ISO
8501-1). The standard to be kept until application of first coat of paint.
Treatment E:
Blast cleaning of the entire area to standard SA 2½ (ISO 8501-1). The standard to be kept
until application of first coat of paint.
Blast cleaning
This important stags in the steel protection should preferably by carried out in paint
shops/ paint shed with controlled climatic conditions.
If the time between application of the shopprimer and steel cutting is not too long and the
shopprimer has not been damaged then the plates will normally be in an acceptable
condition for coating application.
If only ST 3 is allowed for, then Jotun recommend that disc grinders are used (rotating
wirebrushes can cause polishing of the surface which can affect coatings adhesion).
It is very important to remove all dirt and water soluble zinc salts from shopprimers and
water soluble welding deposits. Most coating failures are caused by inadequate pre-
treatment, painting over contaminations or the entrapment of moisture or solvents.
If the shopprimer shows signs of breakdown at the time of coating application, then
dependent upon the general condition, it should be totally removed or sweep blasted.
The importance of careful surface preparation prior to application of the paint system
cannot be over-emphasized.
PAINT APPLICATION
1. Stripe Coating
“ Stripe coating ” is the application of paint to difficult areas such as edges, welding
seams, notches etc. It should be done with the colour of the next coating as this will help
in ensuring that the protection of these areas is safeguarded.
The painter should be clearly instructed of the extreme importance of ensuring that all
areas that are difficult to access must be coated and great care taken in application. The
paint should be applied with a round brush. Only when it proves impossible to reach any
areas with a normal round brush, other equipment should be used.
“Stripe Coating” is a vital procedure as many areas cannot be reached by airless spray
and failure to coat difficult areas will result in undercutting of the paint film and
corrosion will then occur.
“Stripe Coating” must be carried out before each full coat. For any variation of sequence,
Jotun Coating Advisor may be consulted.
2. General Application
The application of the paint must be carried out by an experienced painter using good
quality airless spray equipment.
It is of great importance that number of coats and film thickness are according to the
recommendations from Jotun for the actual area. Film thickness to be measured with
calibrated equipment.
4. Drying Time
Drying times are generally related to air circulation, temperature, film thickness and
number of coats, and will be affected correspondingly. As most of the used thinners are
heavier than air, painting in tanks etc., require mechanical d
NB: The Jotun Paint Inspector is requested to approve all areas to be painted before
application starts. The approval to be documented by signed markings on drawings
showing area(s) involved. The Jotun Paint Inspector is requested to contact the person in
charge if procedures/paint work are not in accordance with specification. To be
confirmed written in report-form.