003 JSA All Civil Works
003 JSA All Civil Works
Part 3: Equipments / Tools to be used: Transit Mixture, Loader, Roller Compactor, Plate compactor, Vibrator, wheel barrows & Hand Tools,
Part 4: Contingency Plans. Standard PPE’s: First aid kit must be present at work site and the HSE personnel will be the first response in case of
emergency, ERPs & Emergency contact numbers to be in placed at job location
Part 5:JSA Review Process. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? In
case of any new hazard indentified by any of the working team member during the job, JSA review process should be carried on.
JSA No: JOB TITLE: Civil Works for Construction of foundations/building
Step Describe Job Step Potential Hazards Hazard Controls
No
1 Mobilization of equipment & Involvement of unskilled personnel Trained & skilled staff to be authorized for
Materials Movement in restricted areas working
Ensure JSA briefing to all workforce prior
to commence activity
Deliver daily TBT
Use of appropriate PPE’s
Unauthorised/ uninspected Only inspected Equipments/Tools must be
equipment/tools at site allowed at work site
Use right tools for right job
All tools must be colour coded
Personnel injury / property damage Ensure safe transportation of
Manual handling equipment/materials at work site
Slip, trip & fall Ensure use of proper PPE’s, avoid
throwing of materials
All of materials to be secured while its
transportation to work site
Close safety supervision
2 Levelling, Back filling & Personnel hit by Movement of heavy Deliver tool box talk to all of vehicles
Compaction works vehicles/equipments drivers & operators
Banks men should be available at site to
control the movement of heavy
vehicles/equipments
Keep away all unauthorized people during
movement of heavy vehicle/equipments
Ensure Close HSE monitoring /supervision
JSA No: JOB TITLE: Civil Works for Construction of foundations/building
Step Describe Job Step Potential Hazards Hazard Controls
No
Dust Ensure use of appropriate PPE’s (dust
mask)
Water sprinkling to be carried out on
regular biases to avoid dust
Slip, Trip & fall Excavated area should be properly hard
barricaded
Keep access/walk ways always clear from
any obstruction
Ensure proper housekeeping of workplace
all the time
Inclement weather condition Stop work in case of any inclement
weather conditions (Rain, storm, fog etc.)
Restrict movement of heavy
vehicles/equipments in rain/fog
Fire & explosion Ensure availability of inspected fire
extinguishers at site
Flame arrestor to be installed in all
vehicles
3 Steel Fixing, Form work & Personnel hand injury while handling Involvement of skilled labour
Concreting with steel & form work materials Ensure use of proper PPE’s
Manual handling Deliver daily TBT before commencing
Sharp edges work
Ensure use of inspected & colour coded
hand tools
Careful handling of steel & other materials
Slip ,trip & fall Ensure proper stacking of all materials
Maintain good housekeeping all the time
JSA No: JOB TITLE: Civil Works for Construction of foundations/building
Step Describe Job Step Potential Hazards Hazard Controls
No
Inappropriate PPE’s/Tools during Use of appropriate PPE’s during concrete
concrete work works (Eye protection, rubber gloves, gum
shoes)
Ensure use of inspected tools for the right
job
Skin contact with concrete or other
Availability of fresh water at site
chemicals
First aid box should be in place at site
4 Work at height , Unskilled personnel Skilled & trained scaffolders to perform
erection/dismantling of scaffolding Inappropriate materials & hand tools work
Inappropriate PPE’S Use of proper PPE’s
Sharp edges Use of inspected & colour coded hand
Improper material stacking tools
Avoid to use damaged material for
erection of scaffolding
Stack material properly at site
Scaffolding collapse, Ensure placement of base plate, sole board
Personnel fall from height, falling of (as required) to avoid collapse of
objects from height scaffolding
Improper Access Ensure proper inspection of platform
Slip, trip & fall before starting work at height
Place scaffolding tag on platforms
Use of full body harness during working at
height
Don’t allow throwing of materials from
height
Avoid any loose materials on platforms
All materials should be properly stacked,
maintain housekeeping in the area all the
time
JSA No: JOB TITLE: Civil Works for Construction of foundations/building
Step Describe Job Step Potential Hazards Hazard Controls
No
Access should be proper to avoid trip &
fall
Area should be free from obstructions of
materials
Be careful of SIMOPS
Use scaffolding platform after proper
inspection
5 Working at night shift hours Poor visibility at night hours Ensure proper lighting arrangement for
late night working hours
Vehicles/equipments hit with people, Careful movement of vehicles in night
equipment or structure hours
Place refection tapes at hard barriers,
structures
Banks men should worn high visibility
reflection vests
Slip , trip & fall No working should be allowed in poor
lighting conditions
Ensure proper housekeeping to avoid
tripping
6 Demobilization Same as item one Same as item one