to create more than 3,000 new jobs and a yearly economic impact of $3
billion.
construction and openings will span from 2020 to 2022. Some of its
The announcement came today from Phoenix Mayor Kate Gallego, joined
“We’re looking at a total construction cost of 1.5 billion dollars,” Collins said.
“Right now, that’s a very conservative figure, but we’re hoping to stick as
close to it as possible.”
The Midtown Neighborhood Association, concerned over the traffic and
noise that the complex will bring being less of a quarter of a mile away,
settled with Ryan Companies to include a 12-acre park in their plans. “It will
The project will begin with constructing the Apple store and housing
complex in June 2020 and are expected to be ready by July 2021. The
second phase will be the retail aspect, that will break ground in January
2021 with an opening date in July 2022. The final phase will be the Hyatt,
called “The Madrid,” that will break ground in July 2021 and will open in
November 2022.