2X35 MW PEAT METHOD STATEMENT FOR

Document
Project BASED POWER PROJECT AT ERECTION OF PHP CONVEYOR
SOUTH AKANYARU, RWANDA. Title TRESTLE ASSEMBLY

Document Number SP – YUMN –00 – CQC – CQI –MS– 0005 Revision 0A Sheets 1 of 9

PROJECT:
2X35 MW PEAT FIRED POWER PLANT
AT SOUTH AKANYARU, RWANDA.
EMPLOYER:

YUMN LIMITED

EMPLOYER’S ENGINEER:

SWECO INTERNATIONAL AB

SUPPLIER:
SHAPOORJI PALLONJI & CO. PVT. LTD.
(EPC DIVISON)

SUPPLIER'S ENGINEER(SE): FICHTNER CONSULTING ENGINEERS


(INDIA) PVT. LTD, CHENNAI
METHOD STATEMENT FOR ERECTION
DOCUMENT TITLE: OF PHP CONVEYOR TRESTLE
ASSEMBLY
SUPPLIER'S
DOCUMENT NUMBER:
SP – YUMN – 00 – MECH – MS– 0005

SUBMISSI
ON
REVISION STATUS R2
CATEGOR
Y
SIGN
INITIAL
S
SIGN
2 INITIAL S
25.09.2019
SK SK
S J

SIGN
1 24.09.2019
INITIAL S
SK SK
S J

SIGN
0A FIRST ISSUE 21.09.2019
INITIAL S
SK SK
S J
CV EL IC ME QA AP
PR DETAILS OF
DATE
OV REVISION
REV CLEARED
ED

SPEPC
2X35 MW PEAT METHOD STATEMENT FOR
Document
Project BASED POWER PROJECT AT ERECTION OF PHP CONVEYOR
SOUTH AKANYARU, RWANDA. Title TRESTLE ASSEMBLY

Document Number SP – YUMN –00 – CQC – CQI –MS– 0005 Revision 0A Sheets 2 of 9

(1) Objective:
The purpose of this method statement is to describe required resources and procedure for
the erection of Conveyor Trestle at PHP area.

(2) Field Application:


This procedure applies to the Erection of the Trestle. However, it may vary depending on
available resources & site conditions with written agreement with the employer.

(3) Resources:
A) Manpower
The workforce planned for this operation would include:

Section Engineer/Supervisor 1
Rigger Foreman 1
HSE Supervisor 1
Riggers 4

B) Equipment’s Required

 70 / 180 MT Crane - 1 No.


 Lifting tools & tackles
o Belt slings 12mtr – 1nos ( SWL : 10 MT)
o D-Shackles – 1 Nos. of 10 MT capacity each
 Hydras 12 Ton- 1 Nos. [if required]
 Weight to be lifted: 5 to 10 MT

(4) Procedure as per OEM guideline:


 Permit to be checked before lifting of trestle assembly.
 Rigging of trestle has to be performed strictly as per guideline of foreman.
2X35 MW PEAT METHOD STATEMENT FOR
Document
Project BASED POWER PROJECT AT ERECTION OF PHP CONVEYOR
SOUTH AKANYARU, RWANDA. Title TRESTLE ASSEMBLY

Document Number SP – YUMN –00 – CQC – CQI –MS– 0005 Revision 0A Sheets 3 of 9

 Two guide ropes will be tied up with both ends of the trestle assembly for
movement of the trestle assembly and minor adjustments.
 Trestle assembly will be lifted with the help of one crane of capacity 70 MT /180 MT
as per the lifting plan mentioned below.
 Trestle assembly will be lowered into the foundation in as per drawing.

(5) Quality & Safety Control:


 During lifting all necessary quality & safety guidelines will be maintained till
completion of the lifting operation.
 All tools-tackles to be used will be visually inspected before use. Only tested &
calibrated tools-tackles are to be used.
 The area of work will be barricaded to ensure no unauthorized entry during work.
All personnel involved would wear necessary PPE, like Safety Shoes, Safety Helmet,
high-visibility Jackets, protective eye glass etc.
 Ensure a task supervisor should be available.
 Before the work pre inspection to be done by site team.
 Ensure a safe access/egress for the above work. (i.e. Compaction of ground as per
crane requirement)
 After work, ensure a good housekeeping to be done.
2X35 MW PEAT METHOD STATEMENT FOR
Document
Project BASED POWER PROJECT AT ERECTION OF PHP CONVEYOR
SOUTH AKANYARU, RWANDA. Title TRESTLE ASSEMBLY

Document Number SP – YUMN –00 – CQC – CQI –MS– 0005 Revision 0A Sheets 4 of 9

(6) Load chart of Cranes:


180T Crane Load Chart
2X35 MW PEAT METHOD STATEMENT FOR
Document
Project BASED POWER PROJECT AT ERECTION OF PHP CONVEYOR
SOUTH AKANYARU, RWANDA. Title TRESTLE ASSEMBLY

Document Number SP – YUMN –00 – CQC – CQI –MS– 0005 Revision 0A Sheets 5 of 9
2X35 MW PEAT METHOD STATEMENT FOR
Document
Project BASED POWER PROJECT AT ERECTION OF PHP CONVEYOR
SOUTH AKANYARU, RWANDA. Title TRESTLE ASSEMBLY

Document Number SP – YUMN –00 – CQC – CQI –MS– 0005 Revision 0A Sheets 6 of 9

70T Crane Load Chart


Main boom (m)
Working
Telescopic cylinder I and outriggers completely extended, over side and
radius
over rear
(m) 11.6 15.6 19.6 25.7 31.8 37.9 44.0
3.0 70000 50000 40000
3.5 63000 50000 40000
4.0 56000 47000 40000 28000
4.5 52000 44000 40000 28000
5.0 48000 42000 38000 27000
5.5 43000 39000 36000 26000 18000
6.0 39000 37000 34000 25000 18000
6.5 35000 33000 31500 24000 18000
7.0 30000 28700 28700 23000 18000 14000
7.5 26500 25000 25000 22000 18000 14000
8.0 23500 22500 22500 21000 17500 14000
9.0 18200 18200 18200 18500 16000 14000 10000
10.0 14700 14700 15300 14500 13000 9800
11.0 12200 12200 12700 13000 12000 9500
12.0 10000 10200 11000 11500 11000 9000
14.0 7100 8200 8800 9300 8000
16.0 5300 6000 6700 7200 7000
18.0 4700 5200 5500 5900
20.0 3500 4000 4300 4600
22.0 3100 3300 3800
24.0 2300 2500 3000
26.0 1700 1900 2300
28.0 1400 1800
30.0 900 1300
32.0 1000
I 0 4.0 8.0 8.0 8.0 8.0 8.0
II 0 0 0 6.1 12.2 18.3 24.4
Reeving’ 12 9 9 5 5 3 3
s
Hook 70 t main hook
2X35 MW PEAT METHOD STATEMENT FOR
Document
Project BASED POWER PROJECT AT ERECTION OF PHP CONVEYOR
SOUTH AKANYARU, RWANDA. Title TRESTLE ASSEMBLY

Document Number SP – YUMN –00 – CQC – CQI –MS– 0005 Revision 0A Sheets 7 of 9

LIFTING PLAN:
2X35 MW PEAT METHOD STATEMENT FOR
Document
Project BASED POWER PROJECT AT ERECTION OF PHP CONVEYOR
SOUTH AKANYARU, RWANDA. Title TRESTLE ASSEMBLY

Document Number SP – YUMN –00 – CQC – CQI –MS– 0005 Revision 0A Sheets 8 of 9

Dimensions of Trestle : 7 Mtr to 33.00 mtr Mtr


Weight of Trestle: 5.0 to 10 MT
Lifting Equipment:
 70 / 180 MT Crane - 1 No.
2X35 MW PEAT METHOD STATEMENT FOR
Document
Project BASED POWER PROJECT AT ERECTION OF PHP CONVEYOR
SOUTH AKANYARU, RWANDA. Title TRESTLE ASSEMBLY

Document Number SP – YUMN –00 – CQC – CQI –MS– 0005 Revision 0A Sheets 9 of 9

 Lifting tools & tackles


o Belt slings 12mtr – 1nos ( SWL : 10 MT)
o D-Shackles – 1 Nos. of 5 / 10MT capacity each
 Hydras 12 Ton- 1 Nos. [if required]
 Weight to be lifted: 5.0 to 10.0 MT

Brief Description of Lift:

Lifting activity of Trestle will be performed with one crane (Crane capacity: 70 MT / 180 MT).
Put trestle into the foundation and provide proper welding to the same.
Crane will be released after completion of welding.