Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Repair of Very Large

Steam Turbines
BARNEY McLAUGHLIN Recently, Sulzer Hickham – a Sulzer Turbomachinery
SULZER TURBO- Services company – entered the market for repair and
MACHINERY SERVICES service of very large steam turbines. The reblading of
a 625-MW steam turbine generator exhibits Sulzer
Hickham’s ability to respond rapidly to the customer’s
demand, find and apply innovative repair techniques,
as well as offer a favorable price.

In early February 2003, a diameter tenons used in the con-


large Southern U.S. utility trol stage of the high-pressure tur-
approached Sulzer Hickham and bine, and the installation of a new
asked for a proposal to reblade a integral-shroud blade design on
625-MW high-pressure/interme- stages 9 and 10 without OEM sup-
diate-pressure rotor (Fig. 1) and port.
perform blade repairs to two low-
pressure rotors (Fig. 2). It was un- Challenging Peening Process
derstood that the effort would Tenon peening is a normal tech-
involve specific engineering de- nique employed by turbine manu-
velopment in order to meet the facturers for the securing of
clients’ turnaround time. shrouding to blading. The blades
The challenges centered about the are covered by a shroud band.
so-called peening of very-large- Tenons are used to fix the shrouds

14 SULZER TECHNICAL REVIEW 3/2003 4098


1 Sulzer Hickham was awarded the repair of a huge steam turbine rotor whose blades were worn.

onto the blades. A peening ma- What systems will be needed to examined under magnification,
chine hits on the tenons, thus up- execute the heating, peening, and hardness measurements were
setting them like a rivet (Fig. 3). and qualifying of the tenons? performed.
The challenge in the particular
case of this big steam turbine was Trials with Test Samples Peening Finished without
the very large tenon size and the Samples of the tenons and shrouds Incident
ability to incorporate semi-auto- were manufactured from identical Following the arrival of the rotors
matic upsetting procedures. Con- material. The mock-up work be- in the shop and the deblading, the
sistency in upsetting (peening) of gan using hand-held torches to reblading process on the control
each tenon is the key to a success- heat the tenon prior to peening. stage began as scheduled. Togeth-
ful reblading operation. This in- From torches, the engineering er with a newly designed peening
cludes heating of the tenons to team moved to high-frequency support structure, the semi-auto-
make them sufficiently ductile, induction heating. It proved to be matic peening system allowed the
with the temperature of the metal the best method, however, se- task to be completed on time and
being a critical parameter. quencing of the heating coil over without incident.
Sulzer Hickham was awarded the the tenon with the peening ma- Accurate positioning of the tenon
work with a turnaround time of chine became an issue. Several
three weeks in shop. The research coils were destroyed in the mock-
2 The contract also
and development on the large- up process. Eventually electronic
included the repair
tenon peening was begun two limit switches were wired into the of two identical low-
weeks before the rotors were system, and the peening process pressure rotors.
scheduled to arrive. approached the semi-automatic
The engineering team faced the regime.
following issues: Control of the tenon heating de-
Is the existing peening equip- pended upon accurate measure-
ment adequate to peen the large ment. By using an infrared device,
tenons? the peening was controlled in a
How can the tenons be heated – narrow range.
consistently and uniformly? Part of the qualification process in-
How can the tenon temperature volved Sulzer Hickham’s metal-
be ensured during the peening lurgical laboratory. The sample
process? peened tenons were sectioned and

SULZER TECHNICAL REVIEW 3/2003 15


under the peening system was en- manufacturing extensive tooling
sured by mounting a laser pointer for measurement of the radial po-
on the peening structure. With the sition and machining of the blade
laser pointer fixed and rigid, the shrouds. This tooling was critical
54,000-lb (24.5-t) rotor could be to meet the timeframe allotted to
rotated and fixed at the exact cen- loading the stage-9 and -10 blades.
ter point on each tenon. In all, 104 blades were individual-
ly measured, machined at the
New Integral-Shroud Blade shroud, and loaded into the rotor 1

Design in just under three days.


For stages 9 and 10, the existing
blading was a standard peened- Customer Fully Satisfied
shroud design. It has been re- Sulzer Hickham dispatched field 2

placed by an upgraded design engineers to establish the reloca-


which incorporates an integral tion point of the seals on the blade 4 New integral-shroud blade design
shroud (Fig. 4). Since these stages ring to center over the machined of stage 10.
are axially loaded, each blade blade shroud. The stationary blade 1 Stage 9
shroud face must be machined ring was sent to Sulzer Hickham, 2 Stage 10
individually upon installation to and the seal location was modi-
accomplish the following: fied. Concurrently, the blades for
To keep the root loaded evenly stage 9 and 10 were moment-
by positioning the blade on the weighed, installed, and machined
radial line prior to balancing the rotor.
To set the shroud pitch so that At installation, the client com-
the row will close with interfer- mented on the timeliness and
ence on the shroud faces keep- quality of work. Subsequently, the
ing the shroud tight same utility additionally awarded
Sulzer Hickham accomplished stationary-component repairs on
these goals by designing and de- another 265-MW unit to Sulzer
veloping detailed procedures, and Hickham.

3 A tenon, heated
by induction,
is upset by the
peening machine
3
and thus secures
the shroud over
the blades.
4
1 Tenon before
peening CONTACT
2 Heating coil Hickham Industries, Inc.
2
3 Peening machine Barney F. McLaughlin
4 Shroud
11518 Old La Porte Rd.
5 Blade
La Porte, TX 77571
6 Tenon after
peening USA
Phone +1 (1)713-567 27 13
Fax +1 (1)713-567 28 30
1 5 6 barney.mclaughlin
@hickham.com

16 SULZER TECHNICAL REVIEW 3/2003

You might also like