Prvi Semestralni Rad
Prvi Semestralni Rad
RGGF
Odsjek: Građevinski
1. V=0,70⋅198,422-263,00⋅198,42+24804,00=178,89 x106m3
2. V=0,70⋅198,432-263,00⋅198,43+24804,00=179,04 x106m3
3. V=0,70⋅198,442-263,00⋅198,44+24804,00=179,18 x106m3
V i+1−V i
VR= 24 h
V i+1−V i 178,89−178,592
VR1= 24 h
= 24 h = 0,01231167 x10 m 6 3
V i+1−V i 179,04−178,89
VR2= 24 h
= 24 h = 0,00616458 x10 m 6 3
V i+1−V i 179,18−179,04
VR3= 24 h
= 24 h = 0,00617042 x10 m 6 3
A=15,8⋅106m2
T1-T2=16,2-21,4=-5,2˚C
ET=5,603mm/dan
ET=5,603⋅0,115740741 (l/s/ha)=0,6485 (l/s/ha)
ET=0,6485⋅1580 ha=1024,83l/s = 1,025 m3/s
Isticanje:
I=P+E+QT gdje je: I-isticanje
P-potrošači
E-evaporacija(isparavanje)
QT-temeljni ispusti
Primjer proračuna isticanja za pojedine dane:
I1=16,2+1,025+19,6=36,825 m3/s
I2=16,2+1,025+19,61=36,835m3/s
I3=16,2+1,025+19,62=36,845 m3/s
Dotok:
dv dv
Qd = dt ⋅ 1000000/3600 +I dt
- razlika zapremine (106m3/h)
Qd2=0,00616458⋅1000000/3600+36,835=38,547m3/s
Qd3=0,00617042⋅1000000/3600+36,825=38,559m3/s