Siklus Cor Proyek RSUD
Siklus Cor Proyek RSUD
umur beton
durasi
65 cek
TOTAL WAKTU PELAKSANAAN 65 5-Jul 7-Sep
ATAP
bongkar 7-Sep 7
cor lantai 1
B3 31-Aug 8
pembesian 3 28-Aug 30-Aug
bekisting lantai 3 27-Aug 29-Aug
cor lantai 1
C2 23-Aug 10
A3 28-Aug 10
pembesian 5 18-Aug 22-Aug 23-Aug 27-Aug
bekisting lantai 5 17-Aug 21-Aug 22-Aug 26-Aug
cor lantai 1
A2 13-Aug 10
B2 18-Aug 10
pembesian 5 8-Aug 12-Aug 13-Aug 17-Aug
bekisting lantai 5 7-Aug 11-Aug 12-Aug 16-Aug
cor lantai 1
B1 3-Aug 10
C1 8-Aug 10
pembesian 5 29-Jul 2-Aug 3-Aug 7-Aug
bekisting lantai 5 28-Jul 1-Aug 2-Aug 6-Aug
cor lantai 1
C 24-Jul 10
A1 29-Jul 10
pembesian 5 19-Jul 23-Jul 24-Jul 28-Jul
bekisting lantai 5 18-Jul 22-Jul 23-Jul 27-Jul
cor lantai 1
A 14-Jul
B 19-Jul
pembesian 5 9-Jul 13-Jul 14-Jul 18-Jul
bekisting lantai 5 8-Jul 12-Jul 13-Jul 17-Jul
PEMBAGIAN ZONE :
luas 1 lantai rata-rata
luas 1 zone (rata-rata)
758.50 m2
379.25 m2