0.

385746
Coarse sand with the value of Blight C= 12
Flood discharge Q 300 cumecs
length of weir 40 m
height of weir above low water 2m
falling shutter 0.6 m
top width of weir 2m
bottom width of weir B= 3.5 m

Solution
Total HL 2.6 m
L=C*HL 31.2 m
L2=2.21*CHL/13= 11.8601 m 12
q=1.7H^3/2 q=Q/L 7.5
H=(q/1.7)^3/2 2.689934
U/s HFL bed level as 100m and crest level a 102 m
bed= 100 102+2.68= 104.6899
f= 1
R=1.35(q^2/f)^1/3 5.172589

Depth of u/s sheet pile from below u/s HFL1.5*R 7.758883


level of bottom of U/s sheet pile 104.68-7.75= 96.93105
provide a depth of 100-96.88= 3.068949
length of cut-off= 3m
Q 8100 cumce
bed level 257 m
High Flood level 262.2 m
Pond level 260.6 m
Afflux 1m
Crest level 1.3 m
Waterway :The waterway, as per Lacey's wetted perimeter equation, is given by
P=4.75*sqor Q 427.5
1.2*P 513
HFL barrage = 262.2
U/s HFL=d/s HFL+afflux 263.2
discharge intersity=q=Q/L 18.9
Scour depth R=1.35*(q^2/f)(1/3)= 9.59 1.689478
f= 1
Velocity of approaxh V=q/R 1.97
Velocity Head V^2/2*g 0.199
u/s TEL=u/s HFL+ velocity Head= 263.399
H=u/s TEL-bed 6.399 m
Crest level= 258.300
H=u/sTEL- Crest level 5.099 m
Q1=1.7*(L-KnH)*H3/2 1880 cumec
Q21.84*(L-0.1nH)*H^3/2 6260 cu\
Q=Q1+Q2= 8140 > 8100 ok

1) High flood condition


(a) Assuming no concentration and retrogression
u/s TEL=d/s HFL+Afflux+Velocity head= 263.399 m
d/s TEL= d/s HFL+velocity head= 262.399 m
Head loss HL= 1.000 m
Discharge intensity q=CH3/2= 27.52

(b) High flood condition with 20% concentration and 0.5 m retrogression
20%= 1.2
1.2*q 33.02
q=C*H3/2=>H=(q/C)^2/3 7.23 m
u/s TEL=bed+H 264.23
d/s HEL is depresed by 0.5 261.7
d/sTEL=d/sHEL+Velocity head 261.899
HL= 2.327 m

Table 11.9 Undersluice Portion of Barrage


High Flood Flow Pond level flow
S.No Item a b a b

1q 27.5 33.02 11.61 13.93


2 U/s HFL 263.200 263.20 260.600 260.6
3 D/s HFL 262.2 261.7 260.2 259.7
4 U/s TEL 263.399 264.23 260.695 261.065
5 D/sTEL 262.399 261.7 260.295 259.80
6 HL 1.000 2.327 0.400 1.270
7 Ef2 7.4 9 4 5
8 Jump d/s TEL-Ef2 254.999 252.700 256.295 254.795
9 Ef1=Ef2+HL 8.400 11.327 4.400 6.270
10 y1 2.4 2.5 1.65 1.3
11 y2 6.4 8 3.3 4.5
12 Length=5(y2-y1) 20 27.5 8.25 16
13 F1= q/sqor*gy1^3 2.36 2.67 1.75 3.00

Depth of Sheet Pile Lines from Scour Considerations


discharge Q= 1880
Overall L= 85
q= 22.12
R=1.35*(q^2/f)^1/3 10.64 11
d/s cut-off=1.5*R 245.2
d/s cut-off at depth of 245.2-257= 7.500 m
u/s cut-off=1.25*R 249.45
u/s cut-off at depth= 7.55 m

Total Floor length and Exit Gradient


safe exit GE=1/6
Head H=260.6-252.7= 7.900
cut-off d=252.7-245.2 7.500
(a) Pre-jump profile:

distance form the d/s

7.2
32.26156

0.035112

(2) Pond Level.FlowCondition


(a) With no concentration anq retrogression

H=bad-pond level= 3.6 m


2.300 m
Q=Q1+2= 2690 cumecs

Discharge intensity q=Q/L= 6.292


scoured depth R=1.35*(q^2/f)1/3= 4.601
Velocity of approach V=q/R= 1.3675
velocity head=V^2/2g 0.0953
u/s TEL= pond leve+ velocity head 260.695
the d/s water level discharge of 2690 260.2
d/s TEL=260.2+0.09 260.295
HL=d/s TEL-u/sTEL 0.40
Discharge intensity q=1.7*H^3/2 11.61
(b) Pond level flow with 20% = 0.5
20%= 1.2*q 13.93
new head H=(q/1.7)^2/3 4.065
u/s TEL= bed +H 261.065
d/s HFL which was 260.2-0.5 259.7
d/s TEL= d/s HFL+Velocity head= 259.80
HL=u/s TEL-d/s TEL= 1.270
Design of Other Barrage Bays Portion
crest level is 258.3 m
u/s HFL 263.2 m
u/sTEL 263.39 m
d/s HFL 262.2 m
d/s TEL 262.39 m
HL=u/sTEL-d/sTEL 1m
q=1.84*(H^3/2)= 21.13