Professional Documents
Culture Documents
Materials Inspection Request
Materials Inspection Request
SPECIFICATION :
REFERENCES :
ACTIVITY :
REMARKS:
1 APPROVED
2 APPROVED AS NOTED
3 RESUBMIT AFTER CORRECTIONS
4 REJECTED
Notes:
A- Installation shall proceed only when Action Code is 1 / or 2.
B- Quantity verification to be substantiated by the Contractor.
C- Inspection does not relieve the Contractor from responsibility of compliance with all requirements of Contract documents.
D- Contractor must mention the delivered materials at suitable stores as per manufacturer recommended conditions.
Ref: PD.SF010.R1
472103967.xls
Date: Jan, 1st, 2011